Name of Work:- Slope protection to Daya left embankment from RD 36.490Km. to 36.660Km. Near village Sisuapada
Sl. No.
Item Description
1
Earth work in excavation of foundation in all kinds of soil by manual means/mechanical means with all leads, lifts & delifts including leveling and dressing the foundation bed upto design bed level and depositing the excavated earth away from the working area including breaking clods maximum 5cm to 7cm in size and laying in layers not exceeding 0.30mtr. in depth including bailing out water and dewatering if required etc. Complete as per direction of Engineer-In-Charge
2
Filling foundation and plinth with sand including watering & ramming with all labour and T&Ps with all leads, lifts and delifts including cost carriage & royalty of all materials etc. Complete as per direction of Engineer-in-Charge
3
Cement concrete (1:3:6) using 4cm size hard granite crusher broken metal free from weathered skin surface of uniform colour and texture from approved quarry and approved quality conferming to specification, mixing by concrete mixture including hoisting and laying concrete in position with all leads, lifts, and delifts including cost conveyance, royalty and taxes of materials including dewatering by suitable means, supplying T&P quaring for specified period with hire and running charges of machineries required for the work, construction and maintenance of coffer dam and approach road if required till completion of work etc. Complete as per direction of Engineer-in-Charge.
4
Rigid smooth centering and shuttering for RCC/CC work including false work and dismantling them after casting and removing the debris away from the working area and stacking the useful materials for reuse including cost, carriage, royalty and taxes of all materials with all labour to the site of work etc. Complete as per direction of the Engineer-in-Charge.
5
Providing and laying cement concrete with M-20 grade with 20mm downgraded hard granite chips free from weathered skin and other deleterious materials of approved quality of uniform colour and texture aggregate and sharp sand of approved grading and quality for RCC/CC confirming to the specifications with all leads, lifts delifts and transportation by mechanical /manual means including cost, carriage, royalties and taxes of all materials including de watering by suitable means mixing concrete by concrete mixer and placing by manual/Mechanical means supplying T&P curing for specified days by suitable means, curing for required days etc. Complete as per direction of Engineer-in-Charge.
6
Filling foundation and plinth with excavated materials including watering ramming with all labour and all T&Ps with all leads, lifts and delifts including cost carriage & royalty of all materials etc. Complete as per direction of Engineer-in-Charge.
7
Collecting, supplying and stacking good quality Moorum & sand in regular box heaps of size 1.50mx 1.50m x 0.50m to be measured as one cum and admixing moorum and sand in 60:40 proportion and laying in sub base in layers to the required thickness not exceeding 22.50 Cum in depth (15cm compacted thickness) with all leads, lifts and delifts including cost, conveyance, royality and taxes of all materials etc. with all labour and hire charges of T&P materials required for the work, watering and compacting to the required density in OMC condition with PRR including hire and running charges of machineries etc. Complete as per direction of Engineer-in-Charge.
8
Earth work in all kinds of soil from approved borrow areas except sand, sandy and slushy soil and transportation of excavated earth by mechanical /manual means with all leads, lifts and delifts including breacking clods maximum 5cm to 7cm and laying in layers not exceeding 0.30m in depth over the properly prepared surface including uprooting stumps with cost of hire and running charges of transport vehicle, T&P, royality and all other incidential charges etc. Complete as per direction of Engineer-in-Charge. (The earth should be arranged by the bidder at his own cost and royality will be deducted as applicable). Measurement will be taken on finished level section.) Please Enable Macros to View BoQ information
We takes all possible care for accurate & authentic tender information, however Users