| 1 | [10.1]Providing and laying of base course of floors consisting of 100 mm thick cement 1:8:16 and 100 mm sand or stone filling. [Through Rate] |
| 2 | [10.76]Providing and laying 60mm thick factory made cement concrete interlocking paver block of M -30 grade made by block making machine with strong vibratory compaction, of approved size, design and shape, laid in required colour and pattern over (BIS 15658:2006) and including 50mm thick compacted bed of coarse sand, filling the joints with line sand etc. all complete as per the direction of Engineer-in-charge. [Through Rate] |
| 3 | [17.5.3]Compacting Original Ground 3. Compaction of Earthwork Compaction of & preparation of sub grade including loosening, levelling of earth 225 mm thick top layer, rough dressing of soil, final dressing of earth to give level, camber, watering, rolling with road roller, compacting the bed to achieve minimum dry density as given in the Table 3000-2 as per technical clause 305 of MORT&H specifications [Through Rate] |
| 4 | [17.6]Construction of Embankment with Material obtained from Borrow pits NA Construction of Embankment CBR 8% (for new road/ raising/ berms/ etc.) with approved material obtained from borrow pits, including compensation of earth with all lead and lift transporting to site, spreading, grading to required slope and compacting to meet requirement of table 300-2, as per technical clause 305 of MORT&H specifications. [Through Rate] |
| 5 | [34.2.2]Cast in Situ Cement Concrete M 20 Kerb with ChannelConstruction of cement concrete kerb with channel with top and bottom width 115 and 165 mm respectively, 250 mm high in M 20 grade PCC on M10 grade foundation 150 mm thick, kerb channel 300 mm wide, 50 mm thick in PCCM20 grade, sloped towards the kerb, kerb stone with channel laid with kerb laying machine, foundation concrete laid manually, all complete as per clause 408 2. Using Concrete Batching and Mixing Plant [Through Rate] |
| 6 | [4.12.1]Earth work in excavation by mechanical means (Hydraulic excavator)/manual means over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 sqm on plan) including getting out and disposal of excavated earth lead up to 50 m and lift up to 1.5 m, as directed by Engineer-in-charge. 1. All kinds of soil [Through Rate] |
| 7 | [6.1.2]Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work below plinth level and up to Floor IV level: 2. 1:2:4 (1 cement : 2 coarse sand (zone-III) : 4 graded stone aggregate 20 mm nominal size) [Through Rate] |
| 8 | [6.1.8]Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work below plinth level and up to Floor IV level: 8. 1:5:10 (1 cement : 5 fine sand : 10 graded stone aggregate 40 mm nominal size) [Through Rate] |
| 9 | [7.21.1]Brick work with common burnt clay non-modular bricks of class designation 10.5 in foundation and plinth in: 1. Cement mortar 1:4 (1 cement : 4 coarse sand) [Through Rate] Please Enable Macros to View BoQ information |