| 1 | Part A (Materials Provided by contractor) |
| 2 | 11 KV RMU 3 Way |
| 3 | 1x16 mm² LT cable |
| 4 | GI Pipe 6inch dia |
| 5 | Dead end clamp |
| 6 | F Bracket |
| 7 | 11 KV Polymer Pin Insulator |
| 8 | 11 KV ‘XLPE’ C/J Kit 3x70 mm² Outdoor |
| 9 | 11 KV ‘XLPE’ C/J Kit 3x185mm² Outdoor |
| 10 | 11 KV ‘XLPE’ C/J Kit 3x185mm² St. Through |
| 11 | Number Plate with Clamp |
| 12 | Danger Board with Clamp |
| 13 | Barbed wire |
| 14 | Bolts, Nuts, & Washers |
| 15 | LT Schakle Insulator |
| 16 | MS Earthing Complete |
| 17 | LT AB Cable clamp with nut & bolt |
| 18 | I Hook |
| 19 | I clamp |
| 20 | Suspension clamp |
| 21 | Neutral PRC |
| 22 | Al. Paint |
| 23 | Red oxide Paint |
| 24 | 11 KV Top channel/Dropper angle clamp |
| 25 | 11 KV Dropper angle |
| 26 | Clamp for GI Pipe & Cable |
| 27 | 11 KV Polymer Disc Insulator |
| 28 | 11 KV Polymer Disc fitting |
| 29 | PG clamp for Dog |
| 30 | 11 KV Stay Set Complete |
| 31 | Stay wire 7/8 SWG |
| 32 | Different size al. lug as per requirement |
| 33 | MS channel T-off 125x65x1300 mm |
| 34 | Clamp for T off |
| 35 | 11 KV TPMO |
| 36 | 11 KV Fuse Set |
| 37 | T/F Base angle 75x75x6x2028 mm |
| 38 | Copper Z clamp |
| 39 | fencing for T/F safety |
| 40 | Three Phase Distribution Box |
| 41 | Holding clamp for Distribution Box |
| 42 | Henley type tailless Unit protection Cubical pannel 500amp for 250 KVA T/F |
| 43 | PART - B- WORKShifting, Loading Carriage & Unloading of following materials from store centre Gorakhpur to work site |
| 44 | ST Pole 9 m long |
| 45 | ST Pole 11 m long |
| 46 | ACSR weasel Conductor |
| 47 | ACSR Dog Conductor |
| 48 | 3x70 mm² ‘XLPE’ cable 11 KV |
| 49 | 3x185 mm² ‘XLPE’ cable 11 KV |
| 50 | 3x120+1x95+1x16 mm² LT AB Cable |
| 51 | 1x400 mm² LT Cable |
| 52 | 3.5x150 mm² LT Cable |
| 53 | 11 KV X arm |
| 54 | 11 KV Top channel 100x50x2240 mm |
| 55 | New 250 KVA T/F |
| 56 | Erection of Single pole structure on 9 mtr ST Pole for LT AB Cable Single Circuit including all works of evocation of pit, pole erection, making plinth for poles 30 cm above, grouting in the ratio 1:4:8 (cement, sand, 40mm brick ballast), back filling of earth, proper ramming & fitting of all accessories (LT clamps with bolt and nut danger board with clamp, Aluminium paint, red oxide paint, barbed wire, Installation of distribution Box, earthing, etc. complete). |
| 57 | Erection of Single pole structure on 9 mtr ST Pole for LT AB Cable Three Circuit including all works of evocation of pit, pole erection, making plinth for poles 30 cm above, grouting in the ratio 1:4:8 (cement, sand, 40mm brick ballast), back filling of earth, proper ramming & fitting of all accessories (LT clamps with bolt and nut danger board with clamp, Aluminium paint, red oxide paint, barbed wire, Installation of distribution Box, earthing, etc. complete). |
| 58 | Erection of Double pole structure on 11 mtr ST Pole for 11 KV cable rising including all works of evocation of pit, pole erection, making plinth for poles 30 cm above, grouting in the ratio 1:4:8 (cement, sand, 40 mm brick ballast), back filling of earth, proper ramming & fitting of all accessories for (top channel 100 x 50 x 2240 mm with clamps, Dropper angle danger board with clamp, Aluminium paint, red oxide paint, barbed wire earthing, etc. complete) . |
| 59 | Erection of Double pole structure on 11 mtr ST Pole for 11 KV one side overhead and one side cable rising including all works of evocation of pit, pole erection, making plinth for poles 30 cm above, grouting in the ratio 1:4:8 (cement, sand, 40 mm brick ballast), back filling of earth, proper ramming & fitting of all accessories for (top channel 100 x 50 x 2240 mm with clamps, Dropper angle, Disc Insulator with fitting, danger board with clamp, Aluminium paint, red oxide paint, barbed wire earthing, etc. complete). |
| 60 | Labour charges for Hanging of LT AB Cable on new erected pole with LT AB Cable clamp, complete. |
| 61 | Stringing of ACSR Dog Conductor on new erected ST pole as Neutral wire. |
| 62 | Making plinth, Installation of RMU, connection, earthing and complete work. |
| 63 | Labour charges for Dismentalling of old Existing 11 kv cable and Relaying of old cable covering with sand and brick & rising of 11kv cable and jumpering complete work. |
| 64 | Charges for making section and jumpering with related Weasel/Dog conductor as per site requirement. |
| 65 | Laying of 11 KV 3x185 mm² cable(D/C) by Digging pit & making tranch in proper size (2m depth x 1m wide) or as per side requirement by fixing bricks both side of tranch wall and 9\\" brick work at the centre of the tranch along the cable. fixing brick slab on the top after filling sand around both the cable including the cast of sand and bricks.as per site required. |
| 66 | Laying of 11 KV 3x185 mm² cable(D/C) by HDD Method below ground level. (2M depth or as per site requirement). |
| 67 | Extra cost for drilling horizontal hole 4 Mtr below the ground level or as per side requirement & inserting 6” dia. HDPE Pipe/CI Pipe as per RESSPO for passing of 11 KV XLPE cable 3x185 mm² for Railway Crossing/Four lane /Pulliya Crossing at different places in the path of Laying of cable. (Complete work with HDPE Pipe/ CI Pipe & other required Materials provided by contractor). |
| 68 | Digging & laying of 11 KV XLPE Cable 3X185 Sqmm (Double ckt) in Cable trench. As Per Site Requirment (Tranch provided by PWD) . |
| 69 | Laying of 11 KV 3x70 mm² cable(D/C) by Digging pit & making tranch in proper size (1m depth x 1m wide) or as per side requirement by fixing bricks both side of tranch wall and 9\\" brick work at the centre of the tranch along the cable. fixing brick slab on the top after filling sand around both the cable including the cast of sand and bricks.as per site required. |
| 70 | Laying of 11 KV 3x70 mm² cable(D/C) by HDD Method below ground level. (2M depth or as per site requirement). |
| 71 | Digging & laying of 11 KV XLPE Cable 3X70 Sqmm (Double ckt) in Cable trench. As Per Site Requirment (Tranch provided by PWD) |
| 72 | Rising of 11 KV ‘XLPE’ cable in air after providing 6” dia. M.S pipe 3 m long Complete work. |
| 73 | jointing charges of 11 KV XLPE C/J Kit Outdoor/Straight through. |
| 74 | special Pipe Earthing Complete for Cable jointing Kit with materials provided by contractor. |
| 75 | Shifting, loading, Carriage and re-installation of Existing 400/250 kVA T/F From Existing place to Shifted Place with installation related all materials i.e. installation of fitting and equipment. as per site requirement and instruction of supervision authority. (including T/F plinth, installation of fencing and Special Chemical earthing, making Plinth of LT fuse set) complete work. |
| 76 | Installation of New 250 KVA T/F 11/0.4 KV For Avoid Road crossing with installation related all materials i.e. installation of fitting and equipment, including T/F plinth, installation of fencing and Special Chemical earthing, installation of LT fuse set) as per site requirement and instruction of supervision authority. |
| 77 | Shifting, loading, Carriage and re-installation of Existing 25/63/100 KVA T/F From Existing place to Shifted Place with installation related all materials i.e. installation of fitting and equipment. as per site requirement and instruction of supervision authority. (including Special Chemical earthing, TPMO Fuse Set) complete work. |
| 78 | Grouting of stay rods (16 x 1800) mm including all work of excavation, cement concrete in size (0.60 x 0.60 x 0.30) m in ratio 1:4:8 cement, sand, 40mm brick ballast) as per drg including back filling, proper ramming etc. Fixing tightening & nozzling of stay wire with stay rod with the poles of required tension. |
| 79 | Dismentling charges of existing 9 mtr. ST Pole. |
| 80 | Dismentling charges of existing 11 mtr. ST Pole. |
| 81 | Dismentling charges of existing PCC Pole 8.5 mtr. |
| 82 | Dismentling charges of existing 11 mtr. Rail/Joist Pole. |
| 83 | Dismentaling of old ACSR Dog conductor and rolling in pieces. |
| 84 | Dismentaling of old ACSR Weasel conductor and rolling in pieces. |
| 85 | Dismentaling of old AB Cable and rolling in pieces. |
| 86 | Shifting, Loading, Carriage & Unloading of old and damaged 11 KV/LT Line materials from work site to Store centre Gorkahpur Distt. Gorakhpur. |
| 87 | Temporary Line Shifting |
| 88 | Erection of Single pole structure on 11 mtr ST Pole for Temporary Hangning of 11 KV XLPE Cable 3x185sqmm & fitting of all accessories (11 KV Cross arm with clamp earthing, etc. complete). |
| 89 | Hanging of 11 KV Cable on new Erected pole with Cable Hanging hooks, Stay wire and Cable clamps Temporary with GPS Location & Photograph. |
| 90 | Cable jointing charges of 11 KV XLPE Cable 3x185sqmm |
| 91 | Erection of AB Cable 3x120+1x95+1x16sqmm with all required clamps and other materials with GPS Location & Photograph. |
| 92 | After Construction of road by PWD, Dismentling of Temporary line, cable will be use as permanent UG line (Shifting and ready to useble by contractor) |
| 93 | Dismentling of ST pole with all Fitting and Receive back to store center Gorakhpur. |
| 94 | Dismentling of AB Cable with all Fitting and Receive back to store center Gorakhpur. Please Enable Macros to View BoQ information |