| 1 | Transporting poles by hired vehicle to a distance upto 5km and carrying upto 4 poles excluding loading & unloading. |
| 2 | Loading HT PSC pole from the stacking place and unloading the same at work site (transport by vehicle). |
| 3 | Fitting and erecting one HT PSC Pole in position incl. fitting cross arm, digging & back filling pit, drawing earth leads. |
| 4 | Laying of 11 KV, XLPE UG cable by HDD Method under normal soil conditions |
| 5 | Lifting/ Loading 1 No C/V/M module of RMU |
| 6 | Lifting /Loading 1No CCC/CCV unit of RMU |
| 7 | Transporting Transformers by hired vehicle upto 5km and upto 2 No. of 63 to 250kVA Transformers / RMUs excluding loading & unloading. |
| 8 | Providing one Earth using earth pipe incl. digging separate pit at standard distance away from the pole/structure & backfilling. |
| 9 | Doing straight joint on cables of sizes beyond 3x185 sqmm and upto and incl. 3x300 sq mm using the cable jointing kit supplied departmentally as per specification. |
| 10 | Doing one cable end termination on cables of sizes beyond 3x185 sqmm and upto and incl. 3x300 sq mm using the cable jointing kit supplied departmentally. |
| 11 | Mounting the cable ends of all sizes upto and incl. 3x300 sq mm with special type cable clamps incl. cost of extra materials if needed and giving necessary connections. |
| 12 | Cost of installation & commissioning including transportation of materials of Data Aquisition compatible Extensible type Ring Main Unit without of different specifications - RMU Bus Couplers / Add-On units with Load Break switch(s) & Earth switch |
| 13 | Cost of installation & commissioning including transportation of materials of Data Aquisition compatible Extensible type Ring Main Unit without of different specifications - RMUs with two nos load break switches & one VCB |
| 14 | DSR 2018.2.6.1. Earth work in excavation by mechanical means (Hydraulic excavator)/manual means over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 sqm on plan) including disposal of excavated earth, lead up to 50 m and lift up to 1.5 m, disposed earth to be levelled and neatly dressed- All kinds of soil |
| 15 | Fitting one set (3No.) 11kV LA and giving connections excluding earthing. |
| 16 | Providing and laying in position specified grade of reinforced cement concrete, excluding the cost of centering, shuttering, finishing and reinforcement All work up to plinth level |
| 17 | 50.6.2.3 Solid block masonry using pre cast solid blocks (Factory made) of size 30x20x15cm or nearest in : CM 1:6 ( 1 cement : 6 coarse sand) etc complete |
| 18 | Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level : 1:3:6 (1 Cement : 3 coarse sand (zone-III): 6 graded stone aggregate 40 mm nominal size) |
| 19 | Laying HT XLPE UG cable (of sizes beyond 3x185 sqmm and upto and incl. 3x300 sqmm) as per specification excl. excavation and backfilling. |
| 20 | Cost of installation & commissioning including transportation of materials of Data Aquisition compatible Extensible type Ring Main Unit without of different specifications - Coupling of Busbars |
| 21 | Providing one Coil Earth using GI earth wire, digging separate pit at standard distance away from the pole/structure & backfilling |
| 22 | Providing Transformer fencing , using 50x50x6mm Angle iron, 40 x 6 mm MS flat and 8 mm MS rod as specified, incl cost of transportation & foundation Please Enable Macros to View BoQ information |