| 1 | Providing lowering, laying, aligning, fixing in position U shape T-25 heavy load bearing Precast Drain 1200x1200 mm and cover lid for 1200x1200 mm precast drain to cross carriageway including cost of carriage, loading and unloading complete in all respect as per satisfaction of Engineer-In-charge |
| 2 | [3.1.2]By Mechanical Transport including loading, unloading and stacking 2. Earth [1km] |
| 3 | [34.57]Retro Reflective Printed Sign Board Facia with 10 year warranty Design, manufacturing and assembly of retro reflective sign face (measured in Sq. or rectangular shape) made from micro prismatic Type XI sheeting as per ASTM D-4956-09 pasted on 4mm thick ACP/ ACM. Special Inks used for printing letters/ legends/ directions/ theme shall be certified for low volatile organic compound emission & shall be water based ink (non solvent & non eco solvent ink) with durability of 10 years atleast. The reflective sheeting signage facia shall be covered with ultra voilet overlaminate transparant film. The signage facia shall be warranted for 10 years as per IRC 67 and shall be supplied with government test report of 3 year outdoor weathering test conducted in India condition on base reflective sheeting as per IRC 67-2012. [Through Rate] |
| 4 | [4.1]Clearing jungle including uprooting of rank vegetation, grass, brush wood, trees and saplings of girth up to 30 cm measured at a height of 1 m above ground level and removal of rubbish up to a distance of 50 m outside the periphery of the area cleared. [Through Rate] |
| 5 | [4.14.1]Earth work in excavation by mechanical means (Hydraulic excavator) / manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan), including dressing of sides and ramming of bottoms, lift up to 1.5 m, including getting out the excavated soil and disposal of surplus excavated soil as directed, within a lead of 50 m. 1. All kinds of soil. [Through Rate] |
| 6 | [5.25]Demolishing R.C.C. work manually/ by mechanical means including stacking of steel bars and disposal of unserviceable material within 50 metres lead as per direction of Engineer - in- charge. [Through Rate] |
| 7 | [6.14.1]Providing and laying in position specified grade of reinforced cement concrete, excluding the cost of centering, shuttering, finishing and reinforcement - All work up to plinth level : 1. 1:1.5:3 (1 cement : 1.5 coarse sand (zone-III): 3 graded stone aggregate 20 mm nominal size) [Through Rate] |
| 8 | [6.22.1.2]Providing and laying in position ready mixed plain cement concrete, with cement content as per approved design mix and manufactured in fully automatic batching plant and transported to site of work in transit mixer for all leads, having continuous agitated mixer, manufactured as per mix design of specified grade for plain cement concrete work, including pumping of R.M.C. from transit mixer to site of laying and curing, excluding the cost of centering, shuttering and finishing, including cost of curing, admixtures in recommended proportions as per IS : 9103 to accelerate/ retard setting of concrete, improve workability without impairing strength and durability as per direction of the Engineer-in-charge. 1.2. All works above plinth and up to floor IV level : M-15 grade plain cement concrete (cement content considered @ 240 kg/cum) [Through Rate] |
| 9 | [6.25.1]Providing and laying in position machine batched and machine mixed design mix M-25 grade cement concrete for reinforced cement concrete work, using cement content as per approved design mix, including pumping of concrete to site of laying but excluding the cost of centering, shuttering, finishing and reinforcement, including admixtures in recommended proportions as per IS: 9103 to accelerate, retard setting of concrete, improve workability without impairing strength and durability as per direction of Engineer-in-charge. 1. All works up to plinth level [Through Rate] |
| 10 | [6.26.1]Extra for providing richer mixes up to plinth and at all floor levels. 1. Providing M-30 grade concrete instead of M-25 grade BMC/ RMC. (Note:- Cement content considered in M-30 is @ 340 kg/cum) [Through Rate] |
| 11 | [6.29.1]Centering and shuttering including strutting, propping etc. and removal of form work for : 1. Foundations, footings, bases for columns [Through Rate] |
| 12 | [6.30.3]Centering and shuttering including strutting, propping etc. and removal of form for 3. Suspended floors, roofs, landings, balconies and access platform [Through Rate] |
| 13 | [6.36.1]Steel reinforcement for R.C.C. work ready to use `cut and bend` rebars of approved make from factory/workshop to construction site including placing in position and binding all complete above plinth level. 1. Thermo-Mechanically Treated bars of grade Fe-500D or more. [Through Rate] Please Enable Macros to View BoQ information |