| 1 | Safe cartage of 8.5 Mtr. long PCC poles | Safe cartage of 8.5 Mtr. long PCC poles |
| 2 | Safe cartage of 9/11 Mtr. long ST poles | Safe cartage of 9/11 Mtr. long ST poles |
| 3 | Safe cartage of line material | Safe cartage of line material |
| 4 | Erection of new 8.5 Mtr. long PCC poles as single support structure, including complete HT/LT fittings as per direction of Engineer incharge/RESSPO manual, including the work of replacement of damaged poles, if required. | Erection of new 8.5 Mtr. long PCC poles as single support structure, including complete HT/LT fittings as per direction of Engineer incharge/RESSPO manual, including the work of replacement of damaged poles, if required. |
| 5 | Erection of new 9/11 Mtr. long ST poles as single pole structure, including complete HT/LT fittings as per direction of Engineer incharge/RESSPO manual, including the work of replacement of damaged poles along with cartage from work site to ESC, if required. | Erection of new 9/11 Mtr. long ST poles as single pole structure, including complete HT/LT fittings as per direction of Engineer incharge/RESSPO manual, including the work of replacement of damaged poles along with cartage from work site to ESC, if required. |
| 6 | Erection of new 8.5 Mtr. long PCC poles as double pole structure, including complete HT/LT fittings as per direction of Engineer incharge/RESSPO manual, including the work of replacement of damaged poles, if required. | Erection of new 8.5 Mtr. long PCC poles as double pole structure, including complete HT/LT fittings as per direction of Engineer incharge/RESSPO manual, including the work of replacement of damaged poles, if required. |
| 7 | Erection of new 9/11 Mtr. long ST poles as double pole structure, including complete HT/LT fittings as per direction of Engineer incharge/RESSPO manual, including the work of replacement of damaged poles along with cartage from work site to ESC, if required. | Erection of new 9/11 Mtr. long ST poles as double pole structure, including complete HT/LT fittings as per direction of Engineer incharge/RESSPO manual, including the work of replacement of damaged poles along with cartage from work site to ESC, if required. |
| 8 | Concreting/Grouting of newly erected 8.5/9/11 Mtr. long PCC/STP poles as single support/double pole structures. The support shall be grouted with cement, sand and brick ballast/stone ballast in ratio 1:4:8 (0.285 Cu. Mtr. each), including the cost of arrangement of cement, sand, brick ballast/stone ballast, stone pad etc. as per actual site requirement & direction of enginner incharge. | Concreting/Grouting of newly erected 8.5/9/11 Mtr. long PCC/STP poles as single support/double pole structures. The support shall be grouted with cement, sand and brick ballast/stone ballast in ratio 1:4:8 (0.285 Cu. Mtr. each), including the cost of arrangement of cement, sand, brick ballast/stone ballast, stone pad etc. as per actual site requirement & direction of enginner incharge. |
| 9 | Laying, sagging, stringing, binding and jumpering of new ACSR Weasel/Dog Conductor on the erected poles in 11 KV HT/LT lines as per direction of supervising engineer/RESSPO manual also providing in-place of damaged/misplace conductor, if required. | Laying, sagging, stringing, binding and jumpering of new ACSR Weasel/Dog Conductor on the erected poles in 11 KV HT/LT lines as per direction of supervising engineer/RESSPO manual also providing in-place of damaged/misplace conductor, if required. |
| 10 | Laying, stringing, binding and termination etc. of ABC Cable of various size on the erected poles as per direction of supervising engineer/RESSPO manual and also providing in-place of damaged/misplace conductor, if required. | Laying, stringing, binding and termination etc. of ABC Cable of various size on the erected poles as per direction of supervising engineer/RESSPO manual and also providing in-place of damaged/misplace conductor, if required. |
| 11 | Laying, stringing, binding and termination etc. of XLPE Cable of various size on the erected poles as per direction of supervising engineer/RESSPO manual and also providing in-place of damaged/misplace conductor, if required. | Laying, stringing, binding and termination etc. of XLPE Cable of various size on the erected poles as per direction of supervising engineer/RESSPO manual and also providing in-place of damaged/misplace conductor, if required. |
| 12 | Erection, fixing, commissioning and transportation of cable jointing kit indoor/outdoor/straight through type of 11 KV, including the cost of labour, T&P etc. required for proper completion of work with includes replacement of damage cable boxes, if required. | Erection, fixing, commissioning and transportation of cable jointing kit indoor/outdoor/straight through type of 11 KV, including the cost of labour, T&P etc. required for proper completion of work with includes replacement of damage cable boxes, if required. |
| 13 | Cartage and installation of 16 KVA Transformer on single pole structure with making proper connections from 11 KV system and proper testing as well as commissioning of Transformer as per RESSPO manual, including replacement due to damage, if required. | Cartage and installation of 16 KVA Transformer on single pole structure with making proper connections from 11 KV system and proper testing as well as commissioning of Transformer as per RESSPO manual, including replacement due to damage, if required. |
| 14 | Cartage and installation of 25 KVA Transformer on single/double pole structure with making proper connections from 11 KV system and proper testing as well as commissioning of Transformer as per RESSPO manual, including replacement due to damage, if required. | Cartage and installation of 25 KVA Transformer on single/double pole structure with making proper connections from 11 KV system and proper testing as well as commissioning of Transformer as per RESSPO manual, including replacement due to damage, if required. |
| 15 | Cartage and installation of 63 KVA Transformer on single/double pole structure with making proper connections from 11 KV system and proper testing as well as commissioning of Transformer as per RESSPO manual, including replacement due to damage, if required. | Cartage and installation of 63 KVA Transformer on single/double pole structure with making proper connections from 11 KV system and proper testing as well as commissioning of Transformer as per RESSPO manual, including replacement due to damage, if required. |
| 16 | Cartage and installation of 100 KVA Transformer on single/double pole structure with making proper connections from 11 KV system and proper testing as well as commissioning of Transformer as per RESSPO manual, including replacement due to damage, if required. | Cartage and installation of 100 KVA Transformer on single/double pole structure with making proper connections from 11 KV system and proper testing as well as commissioning of Transformer as per RESSPO manual, including replacement due to damage, if required. |
| 17 | Erection, fixing and transportation of 11 KV CT/PT Pole Mounted Unit 10/5 A with fitting of all accessories as per RESSPO manual, including replacement due to damage, if required. | Erection, fixing and transportation of 11 KV CT/PT Pole Mounted Unit 10/5 A with fitting of all accessories as per RESSPO manual, including replacement due to damage, if required. |
| 18 | Erection, fixing and transportation of 11 KV Pilfer proof metering cubicle with fitting of all accessories as per RESSPO manual, including replacement due to damage, if required. | Erection, fixing and transportation of 11 KV Pilfer proof metering cubicle with fitting of all accessories as per RESSPO manual, including replacement due to damage, if required. |
| 19 | Erection and grouting of stay set including the work of nozelling etc. as per RESSPO manual and also including the cost of all grouting material. | Erection and grouting of stay set including the work of nozelling etc. as per RESSPO manual and also including the cost of all grouting material. |
| 20 | Guarding of 11 KV/LT Lines at road/river crossing by laying two nos. GI wire paralell and fixing of lacings (Tilli) at a distance at 2-3 mtr. as per direction of supervising engineer/RESSPO manual. | Guarding of 11 KV/LT Lines at road/river crossing by laying two nos. GI wire paralell and fixing of lacings (Tilli) at a distance at 2-3 mtr. as per direction of supervising engineer/RESSPO manual. |
| 21 | Fixing of earthing rod as per direction of supervising engineer/RESSPO manual. including the cost of labour, T&P etc. required for proper completion of work. | Fixing of earthing rod as per direction of supervising engineer/RESSPO manual. including the cost of labour, T&P etc. required for proper completion of work. |
| 22 | Supply & fixing of nut-bolts with washers of suitable size. | Supply & fixing of nut-bolts with washers of suitable size. |
| 23 | Erection, fixing and transportation of 11 KV distribution boxes with fitting of all accessories as per RESSPO manual, including replacement due to damage, if required. | Erection, fixing and transportation of 11 KV distribution boxes with fitting of all accessories as per RESSPO manual, including replacement due to damage, if required. |
| 24 | Supply & fixing of Top/T-Off/Dropper Channels with clamp alongwith fitting of all accessories as per RESSPO manual, including replacement due to damage, if required. | Supply & fixing of Top/T-Off/Dropper Channels with clamp alongwith fitting of all accessories as per RESSPO manual, including replacement due to damage, if required. |
| 25 | Chopping of Tree Branches coming in the vicinity of the lines during the execution of above work. | Chopping of Tree Branches coming in the vicinity of the lines during the execution of above work. |
| 26 | Note: Any quantity of item from sl no. 1 to sl no. 25 may vary to any limit within the financial value of agreement against this tender. | Note: Any quantity of item from sl no. 1 to sl no. 25 may vary to any limit within the financial value of agreement against this tender. |