| 1 | [10.1]Providing and laying of base course of floors consisting of 100 mm thick cement 1:8:16 and 100 mm sand or stone filling. [Through Rate] |
| 2 | [10.100.2]Cement Concrete 1:8:16 Flooring 2. Cement Concrete 1:8:16 with stone aggregate 40 mm size in foundation and plinth. [Through Rate] |
| 3 | [10.30.1]Providing and laying of chequered precast cement concrete tiles 22 mm thick in footpath and courtyard, jointed with neat cement slurry mixed with pigment to match the shade of tiles, including rubbing and cleaning etc. complete, on 20 mm thick bed of cement mortar 1:4 (1 cement: 4 coarse sand). 1. Light shade pigment using white cement [Through Rate] |
| 4 | [10.30.2]Providing and laying of chequered precast cement concrete tiles 22 mm thick in footpath and courtyard, jointed with neat cement slurry mixed with pigment to match the shade of tiles, including rubbing and cleaning etc. complete, on 20 mm thick bed of cement mortar 1:4 (1 cement: 4 coarse sand). 2. Medium shade pigment using 50% white cement 50% Grey cement [Through Rate] |
| 5 | [11.5.3]12 mm cement plaster of mix : 3. 1:4 (1 cement: 4 fine sand) [Through Rate] |
| 6 | [11.97.3]Finishing with Deluxe Multi surface paint system for interiors and exteriors using Primer as per manufacturers specifications : 3. Painting Steel work with Deluxe Multi Surface Paint to give an even shade. Two or more coat applied @ 0.90 litre/10 sqm over an under coat of primer applied @ 0.80 litre/10 sqm of approved brand and manufacture [Through Rate] |
| 7 | [13.29.2]Steel work welded in built up sections/ framed work, including cutting, hoisting, fixing in position and applying a priming coat of approved steel primer using structural steel etc. as required. 2. In gratings, frames, guard bar, ladder, railings, brackets, gates and similar works [Through Rate] |
| 8 | [17.6]Construction of Embankment with Material obtained from Borrow pits NA Construction of Embankment CBR 8% (for new road/ raising/ berms/ etc.) with approved material obtained from borrow pits, including compensation of earth with all lead and lift transporting to site, spreading, grading to required slope and compacting to meet requirement of table 300-2, as per technical clause 305 of MORT&H specifications. [Through Rate] |
| 9 | [4.12.1]Earth work in excavation by mechanical means (Hydraulic excavator)/manual means over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 sqm on plan) including getting out and disposal of excavated earth lead up to 50 m and lift up to 1.5 m, as directed by Engineer-in-charge. 1. All kinds of soil [Through Rate] |
| 10 | [6.1.2]Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work below plinth level and up to Floor IV level: 2. 1:2:4 (1 cement : 2 coarse sand (zone-III) : 4 graded stone aggregate 20 mm nominal size) [Through Rate] |
| 11 | [7.21.2]Brick work with common burnt clay non-modular bricks of class designation 10.5 in foundation and plinth in: 2. Cement mortar 1:6 (1 cement : 6 coarse sand) [Through Rate] |
| 12 | [7.28.2]Half brick masonry with common burnt clay non-modular bricks of class designation 10.5 in superstructure above plinth level up to floor IV level. 2. Cement mortar 1:4 (1 cement :4 coarse sand) [Through Rate] |
| 13 | [9.16]Providing and fixing pressed clay tile (Mangalore tiles) of size 200mm x 125mm x 10mm on slopping roof top/ window projections with 12mm thick cement, coarse sand mortar 1:3 including cost of ridge wherever required as per approved design complete in all respect up to 4 storey or 15 Meter Height. [Through Rate] Please Enable Macros to View BoQ information |