| 1 | Labour charges includes loading at site, dragging, carriage/ Transporation upto Firms works,unloading at Firms works,dragging including insurance during transit etc ( Complete Job) |
| 2 | 3.15 MVA , 33/11k KV |
| 3 | 4 MVA , 33/11k KV |
| 4 | 5 MVA 33/11/6.6 KV |
| 5 | 6.3MVA, 33/11/6.6 KV |
| 6 | 10 MVA, 33/11/6.6 KV |
| 7 | Detanking of whole Transformer complete Job including refitting back after repairs |
| 8 | 3.15 MVA , 33/11k KV |
| 9 | 4 MVA , 33/11k KV |
| 10 | 5 MVA 33/11/6.6 KV |
| 11 | 6.3MVA, 33/11/6.6 KV |
| 12 | 10 MVA, 33/11k KV |
| 13 | Supply, Fabrication and insulation of New HV / LV copper conductor (Fixed Rate) |
| 14 | Reconditioning and insulation of old HV / LV copper conductor |
| 15 | High density parmali wood |
| 16 | New insulting press board |
| 17 | New EHV Grade transformer oil of approved make (Fixed Rate) |
| 18 | Filtration of new transformer oil after refitting of transformer to get desired BDV values. |
| 19 | Cleaning & spray painting of tank, radiators, conservator , tap changer, marshalling box etc. with one coat of primer & two coats of approved paint and inside the tank with epoxy paint. |
| 20 | Providing and installation of New Off load Tap Switch |
| 21 | 20 Paper cover copper flexible wire (25 mm sq. / 40mm sq.) |
| 22 | Providing and installation of New On load Tap Changer |
| 23 | Repair of on load Tap Changer |
| 24 | Providing and installation of 36 KV HV Bushing |
| 25 | Providing and installation of 12 KV LV Bushing |
| 26 | Providing and installation of 36 KV HV Brass Stud with Nuts |
| 27 | Providing and installation of 12 KV LV Brass Stud with Nuts |
| 28 | Providing and installation of C.I clamp for 33 KV Bushing |
| 29 | Providing and installation of C.I clamp for 11 KV Bushing |
| 30 | Providing and installation of Arcing Horn Assembly for 33 KV/ 11KV Bushing |
| 31 | Providing and installation of Copper thimble of sorts |
| 32 | Providing and installation of Phase separator with insulation between coil |
| 33 | Providing and installation of Galvanised H.W. items |
| 34 | Providing and installation of New transparent type silica gel breather. |
| 35 | Providing and installation of Buchholz relay (with alarm & trip contact |
| 36 | Providing and installation of Wheel Valve(Flange Type)50 mm |
| 37 | Providing and installation of BSP Gun metal wheel valve with cap( 1.5”/2.0” |
| 38 | Providing and installation of Radiator Shut off valve |
| 39 | Providing and installation of Oil level gauge in conservator |
| 40 | Providing and installation of Oil Temperature Indicator (with alarm & trip contact) |
| 41 | Providing and installation of Winding Temperature Indicator (with alarm & trip contact) |
| 42 | Providing and installation of Oil level indicator |
| 43 | Miscellaneous items like insulating paper, cotton Tap, Weaving Taps,SRBP Tube,Sleeving etc |
| 44 | Removal & blocking of OLTC Permanently , if needed. |
| 45 | Repairing of tank by way of complete assessment of all leakages and repair of same by way of welding etc. |
| 46 | Repairing of Radiator |
| 47 | Repairing of Conservator , marshalling box |
| 48 | Filtration of old Transformers Oil (carbonized/Old) |
| 49 | Replacement of Gasket with all materials as per direction of Engineering In-Charge where ever Require |
| 50 | Main tank |
| 51 | Radiator |
| 52 | H.V Bushing |
| 53 | L.V Bushing |
| 54 | Conservator Tank |
| 55 | Re-conditioning of Silica gel Breather |
| 56 | Heat Treatment (to be applied till desired values are achived) |
| 57 | Hot oil bath of power transformer incl. flushing out of sludge, carbon deposits from whole power transformer incl. core conductor radiator transformer tank valves etc. |
| 58 | Shifting of repaired Transformer from works site to Rec station / store ( job include loading / unloading /dragging /carriage and commissioning at site including insurance during transit . |
| 59 | 3.15 MVA , 33/11k KV |
| 60 | 4 MVA , 33/11k KV |
| 61 | 5 MVA 33/11/6.6 KV |
| 62 | 6.3MVA, 33/11/6.6 KV |
| 63 | 10 MVA, 33/11k KV |
| 64 | Replacement of burnt out / damaged transformer core with new one (cargo) |
| 65 | Desludging of old in-circuit (functional) Power transformer for flushing out sludge and carbon deposits including hot oil bath of windings , tank , core and radiators and heat treatment till desired values are achieved |
| 66 | Repairing including painting of damaged core with approved paint |
| 67 | Scrap old copper conductor (Red) |
| 68 | Scrap old / carbonized transformer oil |
| 69 | Scrap Red iron Ms iron parts |
| 70 | Scrap Red Brass parts |
| 71 | Scrap core material. (Red) Please Enable Macros to View BoQ information |