| 1 | Clearing grass and grubbing of road land including uprooting rank vegetation grass, bush, shrubs and trees of grith up to 300 mm removal of stumps of trees cut earlier and disposal of unserviciable materials and stacking of serviciable material to be used or auctioned, up to a lead of 1000 mtr including removal and disposal of to organic soil not exceeding 150 mm in thickness with all labour chages , T&P, cess etc .excluding GST . Complete in all respect as directed by the Engineer in Charge |
| 2 | Eartwork excavation in hard soil or gravelly soil with all leads, lifts, delifts including dressing and leveling the bed to design section and depositing excavated materials away from working area in spoil banks with all leads, lifts and delifts including all cost, conveyance, labour and cess and all other taxes, cess etc. complete as per the approved drawing, design, specification and direction of the Engineer-in-Charge. |
| 3 | Filling foundation and plinth with sand including watering and ramming with all labour, T&P etc complete to the required level including cost, carriage, royalty, DMF,EMF,additional charges & cess, taxes of all materials excluding GST, etc complete as per the approved drawing, design, specification and direction of the Engineer-in-Charge. |
| 4 | Providing cement concrete design mix of M15 grade with 40mm and down graded black hard granite crusher broken stone chips including hoisting and laying concrete works, supply of all materials, labour and machineries, finishing the concrete surface,watering etc.complete in all respects including cost, carriage, royalty, DMF,EMF,additional charges & cess, taxes of all materials excluding GSTof all materials etc. and as directed by the Engineer-in-Charge. |
| 5 | Providing Cement concrete design mix of M15 grade with 20mm.and down graded black hard granite crusher broken stone chips including hoisting and laying concrete works, supply of all materials, labour and machineries, finishing the concrete surface,watering etc. complete in all respects including cost, carriage, royalty, DMF,EMF,additional charges & cess, taxes of all materials excluding GSTof all materials etc. and as directed by the Engineer-in-Charge. |
| 6 | Providing formwork for concrete with F1 finish for both face of c.c.wall, guard wall & structures etc, exposed & unexposed surface of foundation, block joints etc with steel shutters rigidly fixed and removal of forms and making good to the surfaces where necessary complete with all labour, materials, supervision charges, conveyance and T&P, cess & taxes of all materials excluding GST, etc complete as directed by the Engineer in charge & as pr the approved drawing & design & specification. |
| 7 | Filling foundation and plinth with excavated materials of approved quality, free from any objectionable material, well watered and rammed including all cost, conveyance, royalty, cess and taxes of materials, excluding GST, but including labour charges etc .complete with all leads, lifts, delifts etc as per specification and direction of the Engineer in charge. |
| 8 | Dumping stones for rock toe/ launching appron and packing the same to design thickness and the slopes using 30 cm and above size hard broken stones of approved quality and from approved quarry free from other deleterious materials including filling the interstices with small stones including wedges and packing surface to proper line and levels by manually or mechanically including fixing wave breakers, dewatering if any, complete with all leads, lifts, delfits, T&P, all labour, cost, conveyance, royalty, DMF, EMF, additional charges, cess & taxes of all materials excluding GST etc complete as per direction of the Engineer in charge |
| 9 | Providing weep holes in Brick masonary / plain / Reinforced Concrete aboutment, wingwall / Return wall with 100 mm dia AC pipe, extending through the full width of the structure with slope of 1 v : 20 H towards drawing face etc. Complete in all respects as directed by the Engineer in charge & as per the approved drawing & design & specification. Please Enable Macros to View BoQ information |