| 1 | Dewatering supplying of all amterials labout & T&P 5.00 HP Desiel pump set with POL pump Operater etc and dewatering the cleaning water /muddy water etc all complete as required for the work complete as directed by the Engineer-in-charge. ( Volume of water to be ascertained basing on battymetric survay/ contour survay report) volume as per Global mapper= ( Note:- Gravity flow drain -out of pond water has to be explored instead of 100% pumping by pump sets) Hire and running charge for pump s with 5 HP Desel Engine |
| 2 | Earthwork in Slushy soil ( in water up to 0.60 m Depth required the aids of pan and vessels ) with in 50 m initial lead and 1.50 m initial lift as directed by the Engineer-in-charge. |
| 3 | Earthwork in all kinds of soil in excavation of foundation trenches for columns, basement, tie beams, walls and steps in all kinds of soil including moorum, hard stoney earth and earth mixed with boulders except sheet rocks and boulders requiring blasting with all leads and lifts including dressing and leveling the bed sides up to required depth and depositing the excavated materials at places away from the work site with all leads and lifts, T&P for shoring, shuttering, dewatering if required etc. complete as per the drawing, designing including cost of all labour, T&P etc. as required for the work complete as directed by the Engineer-in-charge. |
| 4 | Dismantling of Cement concrete from exing C C road including stacking the useful materials for reuse and removing the debris within 50m lead including cost of all labour, materials, T&P required etc. complete as per the direction of Engineer-in-charge. |
| 5 | Supplying and filling the foundation trenches in si o oudtoni pc & plinth with clean coarse river sand of approved quality from approved quarry, laying in layers not exceeding 150mm thick,watering and ramming including cost , coveyance , royalty and taxes of all materials, cost of all labour,T&P etc. as required for the work complete as per the direction of EIC. |
| 6 | Providing cement concrete for unreinforced cement concrete works of proportion (1:4:8) with 40mm size crusher broken hard granite (CBHG) metal of approved quality and from approved quarry in foundation bed and floors including cost of labour, materials (inclusive of cost, conveyance, royalties, taxes, loading and unloading) & equipments for handing, transportation, batching, mixing, placing in position vibrating, curing for __ days complete as per specification drawing and direction of the Engineer-in-charge. |
| 7 | Supply Fitting and fixing of cement concrete chair with all cost of materials and labour T7p etc all complete |
| 8 | R.C.C. work of M20 having minimum compressive strength (working stress) 200kg./cm2 in 15cm cubes at 28 days after mixing and test conducted in accordance with I.S. 456 and I.S. 516 using 12mm to 20mm size (1/2” to 3/4”) crusher broken hard black granite chips of 20mm size (not to exceed 25%) of approved quality & from approved quarry including hoisting, lowering, laying and compacting concrete with vibrator, watering and curing for 28 days, cost of rigid and smooth centering & shuttering and finishing to exposed surface smooth providing, grooves or beads wherever necessary as per direction of the Engineer-in-charge including cost, conveyance, royalties & taxes of all materials and cost of all labour, T&P etc. as required for the work complete in all respects as per direction of Engineer-in-charge but excluding cost of M.S. rod/Tor steel and binding wires and labour charges for bending, binding and tying the grills.Drain Wall Top Portion (15 cm)Column |
| 9 | Straightening, cutting, bending and binding, welding and jointing (if necessary) coiled/bent up M.S. rods/Tor Steel/deformed rods etc. including hoisting, placing in position, tying the grills binding with 18 to 20 guage binding wire required for R.C.C. work including cost, conveyance, taxes of all materials, cost of all labour, T&P etc. as required for the work complete (weight of binding wires will not be considered) as directed by Engineer-in-charge. (Payment will be made on actual weight of M.S. rods or Tor steel linear measurements of rod for finished item of works. 5 % wastage and lap length are included in the finished rate). |
| 10 | Providing Centering and Suttering for R C C work including fitting fixing etc complete.(A) Base |
| 11 | (B) Wall |
| 12 | Supplying all Materials ,Labour and T& p for Providing Mild Steel tubular posts and Trusses and base plates made out of ERW tubes, Grade YST 210 conforming to ISS no.1161/79 (3rd Revision ) duly Painted with red oxide primer including cost of nuts & bults washers fabrication charges, all labour ,T&P etc complete. |
| 13 | Supplying all Materials ,Labour and T& p for Providing Mild Steel tubular or rectangular purlins with runners bracing for tubular Trusses made out of ERW tubes conforming to ISS no .1161/79 (3rd Revision ) duly Painted with red oxide primer including cost of nuts & bults washers fabrication charges, all labour ,T&P etc complete. |
| 14 | Labour for Fitting and Fixing & Allumininium Coated of TATA Brand 0.47 mm tick G C I sheet in roof drilling hole in wind tiles including fixing of ridges valleys wind tiles including cost of materials , labour for fixing etc all complete |
| 15 | Supplying, fitting and fixing of Stainless steel of 304 grade in hand railing using 50mm dia of 2mm thick circular pipe with Balustrade of size 32mm x 32mm x 2mm @ 0.90mtr. C/C and stainless square pipe bracing of size 32 mm x 32 mm x 2 mm in 3 rows in stair case as per approved design and specification, buffing, polishing etc with cost, conveyance, taxes of all materials, labour, T&P etc. required for the complete in all respect.C/C and stainless square pipe bracing of size case as per approved design and specification, buffing, polishing etc with cost, conveyance, taxes of all materials, labour, T&P etc. required for the complete in all respect. |
| 16 | Matt Floor Tile (Size-400mmX400mm) including all cost and Labour and materials etc all complete |
| 17 | Priming one coat with any approved primer including cost of all labour, materials T & P with taxes, transportation etc all complete. |
| 18 | Wall painting 2 coats with Plastic Emulsion Paint/Weather Coat of approved shade on new work to give an even shade in Ground Floor. |
| 19 | Removal of excaveted earth by mechanical means with in 5 km initial lead and lift etc all complete |
| 20 | Deisplayboard Please Enable Macros to View BoQ information |