| 1 | Stringing of 11 kV Aerial bunched cable of size 3 x 120 + 1 x 95 sqmm with bare/insulated Messengerthrough existing poles |
| 2 | Dismantling (without damage) one HT stay including digging pit in all classes of soil and backfilling, and bringing back to section store. |
| 3 | Providing concrete muffing of size 0.45x0. 45x1.5m (0.5m above GL and 1m below GL). Excavation 0.45x0.45x1m, concrete (1:3:6, 20mm) 0.45x0.45x1.5m, Plastering (1:3) 12mm 0.45x0.45mx5sides |
| 4 | Dismantling one section fuse from structure and bringing back to section store. |
| 5 | Fitting one No. Section fuse on LT line with dropping cables, crimping sockets, connecting with bolt & nut etc |
| 6 | Providing one Coil Earth using No.8 GI-earth wire (50mm dia, 115 turns) including digging separate pit (0.45x0.45x1.5m) at standard distance away from the pole/structure in ordinary soil & backfilling. |
| 7 | Additional rate for providing one disc set, PG clamp etc. complete, on any type of HT pole for making cut point. |
| 8 | Fitting and erecting one HT Double Pole Structure using PSC pole in position including fitting 2 channel cross arms, digging and back filling pit in ordinary soil, drawing sufficient length of GI earthing leads through all cross arms to the ground for earthing (excluding provision of earthing). |
| 9 | Providing one Earth using GI earth pipe of size 38.1mm dia, 2.5m length including digging separate pit (0.45x0.45x2.5m) at a minimum distance of 1.5m away from the pole/structure and maintaining standard distance between different earth pipes in ordinary soil & backfilling |
| 10 | Additional rate for excavation of Pit for A type pole in Laterite. |
| 11 | Additional rate for excavation of one Pit for HT Pole/HT Stay in Laterite |
| 12 | Dismantling (without damage) one LT PSC/RCC pole after disconnecting stays, strut etc. attached thereon and stacking the same. |
| 13 | Dismantling of 11 kV Aerial bunched cable XLPE insulated of size 3 x 120+ 1 x 95 sqmm with bare insulated Messenger |
| 14 | Stringing of one km 3 PH 11kV line with XLPE Insulated ACSR Raccoon or equivalant (3 conductors) after fitting insulators, binding conductors to pin insulators using suitable tie and anchoring with wedge type anchoring clamps including cutting and removing tree branches wherever necessary excluding cut point work. |
| 15 | Labour charges for loading HT PSC pole from the stacking place and unloading the same at work site (transportation by any vehicle) |
| 16 | Labour charges for loading HT A type pole from the stacking place and unloading the same at work site (transportation by any vehicle). |
| 17 | Disconnecting and lowering down the three phase WP service connection with guy wire from the OH line and reconnecting the same after completing the line work |
| 18 | Fitting and erecting one HT A type Single Pole in position, including fitting cross arm, digging and back filling pit in ordinary soil (as per standards), drawing sufficient length of GI earthing leads from F clamp through V cross arm to the ground for earthing (excluding provision of earthing). |
| 19 | Fitting and erecting one HT PSC Single Pole in position, including fitting cross arm, digging and back filling pit in ordinary soil (as per standards), drawing sufficient length of GI earthing leads from F clamp through V cross arm to the ground for earthing (excluding provision of earthing) |
| 20 | Transporting poles by hired vehicle to a distance upto 5km and carrying upto 4 numbers of poles excluding loading& unloading charges |
| 21 | Insertion of one HT PSC pole in existing HT/LT line including digging & back filling of pit in ordinary soil, fitting cross arm, insulator, binding etc. , drawing sufficient length of GI earth leads to the ground for earthing (excluding provision of earthing) |
| 22 | Additional rate for refitting/redoing one Shackle Set, including reshacling one span, while renewing any type of LT pole. |
| 23 | Transferring LT three phase 4/5 wire OH line to newly erected HT/LT pole including dismantling existing cross arm and insulators, refitting the same on the new pole, binding etc. complete. |
| 24 | Transferring LT single phase 2/3 wire OH line to newly erected HT/LT pole including dismantling existing cross arm and insulators, refitting the same on the new pole, binding etc. complete. |
| 25 | Dismantling one ordinary street light/CFL/LED fitting from existing pole andrefitting the same on newly erected pole including disconnecting and reconnecting wires. |
| 26 | Disconnecting and lowering down the single phase WP service connection with guy wire from the OH line and reconnecting the same after completing the line work. |
| 27 | Fitting and providing one HT Stay for 11kV pole, including digging and back filling pit in ordinary soil. |
| 28 | Fitting and providing one Strut using HT PSC pole including digging and back filling pit in ordinary soil |
| 29 | Dismantling (without damage) one LT PSC/RCC Strut pole including removal of clamps and stacking. |
| 30 | Fitting one set AB switch, DO fuse (3No.), LA (3No.), giving all connections from HT line to Transformer bush and drawing earth leads to the ground for earthing excluding provision of earthing and fixing channels |
| 31 | Additional rate for excavation of one Earth Pit (2.5m depth) in Laterite. |
| 32 | Additional rate for excavation of one Pit for Coil Earthing in Laterite |
| 33 | Installing one DTR Meter with box (normal size 40x25x100cm) on existing poles including fixing of 3 CTs on bus bar, laying and termination of control cable using proper lugs, fixing of meters, capacitors, control fuses and giving the complete connections including conveyance of materials |
| 34 | Fitting one LT 2 line cross arm on HT or LT existing poles including fitting insulators and binding the same with LT Line. |
| 35 | Fitting one LT 4 line cross arm on HT or LT existing poles including fitting insulators and binding the same with LT Line. |
| 36 | Dismantling one LT 2 line cross arm with clamp from existing pole and stacking |
| 37 | Dismantling one LT 4 line cross arm with clamp from existing pole and stacking. |
| 38 | Drilling hole of various sizes on existing Channel/Cross Arm. |
| 39 | Fitting one Additional 75x40mm, 1.8m Channel cross arm in existing single pole including conveyance of materials. |
| 40 | Fitting one Additional V cross arm in existing single pole including conveyance of materials. |
| 41 | Fitting one Additional 2.4m/3m Channel cross arm (100x50x6mm), in existing 11kV DP including conveyance of materials. |
| 42 | Fitting one Additional 2.4/3m Channel cross arm (75x40x6mm), in existing 11kV DP including conveyance of materials. |
| 43 | Dismantling (without damage) one 11kV PSC/RCC pole after disconnecting stays, strut etc. attached thereon and stacking the same. Please Enable Macros to View BoQ information |