| 1 | Engagement of labourers for clearance of site etc. |
| 2 | Clearing jungle including uprooting of rank vegetation, grass, brush wood, trees andsaplings of girth upto 30 cm measured at a height of 1 m above ground level andremoval of rubbish upto a distance of 50 m outside the periphery of the area cleared. |
| 3 | Earth work in excavation by manual means in trenches for foundations, drains, pipes, cables etc. (not exceeding 1.5 m in width) and for shafts, wells, cesspits and the like not exceeding 10 sqm on plan, including dressing of sides and ramming of bottoms lift upto 1.5 m, including getting out excavated earth and disposal of surplus excavated earth as directed: (1 meter from cutting edge ) All kinds of soil |
| 4 | Providing and laying stone soling/ hand packed (above 75 mm) including all sorts of carriages by all means of transport upto site of work complete job . |
| 5 | Providing & laying boulder filling got by lorries including Loading, unloading. Ramming, dressing, and all sorts of carriages complete job as per the directions of EIC |
| 6 | Providing and laying in position cement concrete of specified grade including curing but excluding the cost of centring and shuttering. All work upto plinth level with: 1:4:8 (1 cement : 4 coarse sand : 8 graded stone aggregate 40 mm nominal size) |
| 7 | Reinforced cement concrete work in walls (any thickness) including attached pilasters, buttresses, plinth and string courses, fillets, columns, pillars, piers, abutments, posts and struts upto floor five level including curing but excluding cost of centering shuttering, finishing and reinforcement. 1:1½:3 (1 cement : 1½ coarse sand : 3 graded stone aggregate 20 mm nominal size) |
| 8 | Providing and laying in position specified grade of reinforced cement concrete including curing but excluding the cost of centering, shuttering, finishing and reinforcement. All works upto plinth level 1:1½:3 (1 cement : 1½ coarse sand : 3 graded stone aggregate 20 mm nominal size) |
| 9 | Steel reinforcement for R.C.C. work including straightening, cutting, bending, placing in position and binding all complete upto plinth level complete job including all carriages complete job.(TMT Bars) |
| 10 | Form work centering / shuttering including Strutting, Propping etc and removal of form work for:(a) Walls any thickness ) Including attached plasters, buttresses, Plinth and String Course etc. |
| 11 | Form work centering / shuttering including Strutting, Propping etc and removal of form work for:(a) Foudation, footings, basis, coloums etc |
| 12 | Carriage of materials by mechanical transport from source upto the site of work complete job .A) Stone agg 40mm from Athwajan 10 kms lead |
| 13 | b) Stone agg 20mm from Athwajan 10 kms lead |
| 14 | Sand from Ganderbal 24 Km lead |
| 15 | P/F of PVC pipe/fittings line heavy duty (Prince made). (Grade-B) with fittings complete job. A) 75 mm dia |
| 16 | Supply and fixing of sign board at site of required size including taking /printing out geo tagged Photographs before, during and after execution of work complete job as per the directions of EIC Please Enable Macros to View BoQ information |