| 1 | Removal of conductor from both side spans of damaged pole and removal of HT / LT line accessories from damaged pole. |
| 2 | Digging of pit of damaged pole in Pakka (Hard soil) with the help of road cutter/digging machine, Tractor etc. for dismantling the damaged pole. |
| 3 | Digging of pit of damaged pole in Kachha side road (Soft soil) for dismantling the damaged pole. |
| 4 | Dismantling of damaged single support PCC Pole/ST Pole from pit and S.T Pole carriage from work site to J.E's store and damaged PCC Pole will be carriage from wotk site to dumping yard including loading & unloading at both ends. |
| 5 | Carriage of material from Cetral Store, Shaibabad/Sector 20, Noida/J.E Store / any other store to work site including safe loading and unloading at both ends. |
| 6 | ST Pole 9 / 11 / 13 Mtr. Long. |
| 7 | PCC Pole 8.5 / 9 Mtr. Long. |
| 8 | PCC Pole 11 Mtr. Long. |
| 9 | 33 KV V-Type cross arm. |
| 10 | 33 kv Pin insulator |
| 11 | 33 kv Pin with nut |
| 12 | Erection & fabrication of following material including fitting of all reqired accessories of HT / LT line as per RESPO schedule. |
| 13 | ST Pole 9 / 11 / 13 Mtr. Long. |
| 14 | PCC Pole 8.5 / 9 Mtr. Long. |
| 15 | PCC Pole 11 Mtr. Long. |
| 16 | 33 KV V-Type cross arm. |
| 17 | 33 kv Pin insulator |
| 18 | 33 kv Pin with nut |
| 19 | Grouting and concreting of single support on pole with cement, stone ballast & coarse sand in ration of 1:3:6 complete in all respect. |
| 20 | Plinth of ST Pole complete in all respect. |
| 21 | Re-laying and resagging of conductor in both side spans of erected pole in HT / LT line. |
| 22 | Providing and fixing of 33 KV F-Bracket with nut & bolts |
| 23 | Providing and fixing of Holding Clamp with nut & bolts |
| 24 | Providing and fixing of 33 KV Cross Arm Clamp with nut & bolts |
| 25 | Providing and fixing of Stone Pad (300x300x75mm). |
| 26 | Providing and fixing of MS Bolts with nuts. |
| 27 | Welding of damaged/rusted ST Pole in H.T./L.T line by providing M.S Angle and plintihing also. |
| 28 | Repairing of broken/badly damaged S.T Poles (damaged at ground level) in existing H.T/L.T lines due to extra ordinary rusting & scaling. From bottom side welding of 4/5 pieces( approx 75 cm. long) of angle iron of size 50x50x6 mm. Ist of all digging of pit around the pole of size 1.0 mtr. x 1.0 mtr. x 1.0 mtr. is to be done and then cleaning of rust & de-scaling with the help of hard wire brush & chisel and then MS angle iron of size 50x50x6 mm in 4/5 pcs. of required length as per site requirement varying from 70 cms to 75 cm to cut down and then to be welded with the healthy top and bottom portion of the pole with Ist class electric welding with own welding generator set in such as way that on top of bottom potion over-lapping of healthy part is covered 200 mm length approx. before welding the poles where top & bottom portion are separated, the same are to be kept in alignment safely & after completing the above work, the pit should be refilled. Concreting of S.T Pole for grouting (0.285 cu mt.) cement, stone blast) Making plinth of above repaired ST pole in round shape of height 0.30 meters from ground level having outer dia of 500 mm size in CC 1:3:6 in cement, sand , Stone ballast etc. and complete the work in all respect. Please Enable Macros to View BoQ information |