| 1 | Civil Work: |
| 2 | Construction of embankment with approved materials obtained from borrow pits with a lift upto 1.5m with normal lead upto 50m transporting to site, spreading grading to required slope and compacting to meet requirement of table 300.1 and 300.2 as per. Technical specification Clause 301.5 Mord 301.5 |
| 3 | Construction of granular sub-base by providing well graded material, spreading in uniform layers with motor grader on prepared surface, mixing by mix in place method with rotavator at OMC, and compacting with smooth wheel roller to achieve the desired density, complete as per Technical Specification Clause 401. |
| 4 | Providing, laying, spreading and compacting stone aggregates of specific sizes 45-63 mm to water bound macadam specification including spreading in uniform thickness, hand packing, rolling with three wheel 80-100 kN in stages to proper grade and camber, applying and brooming, screening /binding to fill-up the interstices of coarse aggregate, watering and compacting to the required density Grading 2 as per Technical Specification Clause 405. |
| 5 | Providing, laying, spreading and compacting stone aggregates of specific sizes 22.4-53 mm to water bound macadam specification including spreading in uniform thickness, hand packing, rolling with smooth wheel roller 80-100 kN in stages to proper grade and camber, applying and brooming, screening to fill-up the interstices of coarse aggregate, watering and compacting to the required density Grading 3 as per Technical Specification Clause 405. |
| 6 | Brick edging on both side of the road with Straight overburnt bricks 8 cm. wide and 12 cm. deep laid with mud mortar including labour and s/o brick finished to required template and in proper alignment and also including dressing and ramming the excavated earth as per direction of Engineer-in-charge. |
| 7 | Providing and applying primer coat with bitumen emulsion (SS-1) on prepared surface of granular base including cleaning of road surface and spraying primer at the rate of 0.85 kg/sqm using mechanical means as per Technical Specification Clause 502 |
| 8 | Providing and applying Tack Coat with bitumen Emulsion (RS-1) using emulsion distributor at the rate of 0.275 kg per sqm on the prepared dry and hungry bituminous surface cleaned with hydraulic broom as per technical specification clause 503 (ii). |
| 9 | Providing, laying and rolling of open-graded premix carpet of 20 mm thickness composed of 13.2 mm to 5.6 mm aggregates either using penetration grade bitumen or emulsion to required line, grade and level to serve as wearing course on a previously prepared base, including mixing in a suitable plant, laying and rolling with a three wheel 80-100 kN static roller capacity, finished to required level and grades to be followed by seal coat of Type C as per Technical Specification Clause 508. Case - II By Mechanical Means |
| 10 | Providing and laying seal coat sealing the voids in a bituminous surface laid to the specified levels, grade and cross fall using Type C, as per Technical Specification Clause 510, Case - III By Mechanical Means |
| 11 | Construction of Subgrade and Earthen Shouder with approved soil with all lifts and leads laying in layers, breaking clods, dressing to required lines curves,grade and sections watering and compaction to meet at least 100 % procter density complete to specification requirement Shoulder Sl.No. 3.3+3.5 MORD 301.5 |
| 12 | Construction of 600 mm dia hume pipe culvert including supply of all material, labour T & P etc complete as per direction engineer-in-charge.Excavation in foundation in ordinary soil as directed by the Engineer-incharges.as per SI.No. 251 |
| 13 | Concrete with 4cm. Gauge stone ballast ,fine sand of 1.25 FM & cement in proportion 8:4:1 in foundation and floors as per SI.No. 275 |
| 14 | Supply and laying dry brick ballast (OBB) under and half round of the pipe |
| 15 | M15 Brick work in 1:4 one cement and four coarse sand mortar including supply of all materials, labour & tool & plants etc. required for proper completion of work. SI.no. 305b |
| 16 | Supply & laying of 600mm dia NP3 hume pipe including fixing of collar with 1:2 cement mortar. |
| 17 | Struck cement pointing in 1:2 cement & fine sand motar including supply of all material, labour and T&P etc, required for proper completion of the work. SI.No. 574 |
| 18 | 12mm thick in 1:3 cement and Coarse sand plaster as per SI.No. 583 |
| 19 | Finishing walls with water proof cement paint as per SI.No. 660 |
| 20 | Providing and fixing inaugration black granite (Polished) 20 mm thick stone size 0.90x0.75 cm. including lettering, printing, border etc will be painted of superior quality is required shade and colour including fixing exavation of foundation (1.40x0.50x0.40cm), P.C.C. 1:6:12 (1.40x0.50x0.15cm), brick work 1:3 cement coarse sand up to G.L. (1.40x0.23x1.35cm), 12 mm thick plaster 1:3 cement coarse sand and finihing walls with water proffing white cement paint of approved make and quality such as super snowcem paint etc. all complete. as per analysis Please Enable Macros to View BoQ information |