| 1 | Item Rate BoQ BoQ_Ver3.0 Item Rate Normal INR Only INR Select, Excess (+), Less (-) Less (-) Tender Inviting Authority: Executive Engineer JPDCL Electric Div-I, Parade, Jammu. “Survey, Supply, Transportation, Erection, Testing & Commissioning for Permanent Restoration of damages occurred to Electrical Infrastructure due to heavy rainfall/Flash Flood from 25th of August to 3rd of September 2025 under the Jurisdiction of Electric Division Div.-I (JPDCL) Jammu on Turn Key Basis under SASCI.” Contract No:ED-I/e-NIT/18 of 2026-27 Dated 30.04.2026 Bidder Name : PRICE SCHEDULE(This BOQ template must not be modified/replaced by the bidder and the same should be uploaded after filling the relevent columns, else the bidder is liable to be rejected for this tender. Bidders are allowed to enter the Bidder Name and Values only ) NUMBER # TEXT # TEXT # NUMBER # TEXT # NUMBER NUMBER TEXT TEXT # NUMBER # TEXT# TEXT # NUMBER # NUMBER NUMBER NUMBER NUMBER TEXT TEXT NUMBER NUMBER NUMBER NUMBER TEXT TEXT NUMBER NUMBER NUMBER NUMBER TEXT TEXT NUMBER NUMBER NUMBER NUMBER TEXT TEXT NUMBER NUMBER NUMBER NUMBER TEXT TEXT NUMBER NUMBER NUMBER # NUMBER # TEXT TEXT NUMBER # NUMBER # DATE NUMBER # NUMBER # TEXT # |
| 2 | Item Description |
| 3 | Work A- Supply, Erection, Testing and commissioning for Replacement of Damaged/ Washed-away 9mtr long ST Poles on HT Network |
| 4 | ST Poles 9 Mtr Long (ST -410 SP 33) |
| 5 | GI V cross-arm with top Brackets including clamp |
| 6 | GI Channel X-arm including clamp and braces |
| 7 | 11 KV Polymer composite Pin Insulators 12KV, 5KN, Lighting impulse 75KV positive and 80KV negative, creepage distance 320mm |
| 8 | Galvanized nuts & Bolts |
| 9 | Danger Plates with Clamps |
| 10 | Anti Climbing Device with Clamps |
| 11 | Earthing Complete by GI Pipe 40 mm or GI Rod 20mm 2.5mtr long through GI Strip |
| 12 | Cement Bottoming 1:2:4 mix as per REC Standards 0.5cum/pole |
| 13 | Red-Oxide |
| 14 | Aluminium Paint |
| 15 | Work B- Supply, Erection, Testing and commissioning for Replacement of Damaged/Washed-away 8mtr Long PCC Poles on LT Network |
| 16 | PCC Poles 8 Mtr Long (WL 200 Kg) |
| 17 | GI U-Clamps for Shackle Insulator |
| 18 | 16 kN Polymer Shackle Insulator |
| 19 | Galvanized nuts & Bolts |
| 20 | Work C- Supply, Erection, Testing and commissioning for Replacement of Damaged/ Washed-away 8mtr long ST Poles on LT Network |
| 21 | ST Poles 8 Mtr Long (ST-410 SP 15) |
| 22 | GI U-Clamps for Shackle Insulator |
| 23 | 16 KN Polymer Shackle Insulator |
| 24 | Galvanized nuts & Bolts |
| 25 | Earthing Complete by GI Pipe 40mm or GI Rod 20mm 2.5mtr long through GI Strip |
| 26 | Cement Bottoming 1:2:4 mix as per REC standards .45 cum/pole |
| 27 | Red oxide |
| 28 | Aluminium Paint |
| 29 | Aluminium Jointing sleeves |
| 30 | LT Line Spacer |
| 31 | Galvanized Stay Set with 50X8mm Stay clamp, Guy insulator (2Nos), anchor plate (200X200X6mm), Nuts & Bolts, 2nos turn buckles,1.8mm long, 16mm diameter solid GS stay rod and 7/3.15mm dia GI standard wire complete |
| 32 | Work D- Supply, Erection, Testing and commissioning for Replacement of Damaged/Washed-away 120mmsq, 11 KV AB Cable |
| 33 | 11 KV, Three core 120mm² Aluminium round wire Armoured AB Cable |
| 34 | Heat Shrinkable Outdoor Cable Termination Kit |
| 35 | Earthing Complete by GI Pipe 40mm or GI Rod 20mm 2.5mtr long through GI Strip. |
| 36 | Mid Span Straight Through Jointing Kit for 11 KV ABC |
| 37 | Work E- Supply, Erection, Testing and commissioning for Replacement of Damaged/Washed-away ACSR Conductor |
| 38 | ACSR Weasel Conductor (30 mm²) |
| 39 | ACSR Rabbit Conductor (50 mm²) |
| 40 | Work F- Supply, Erection, Testing and commissioning for Re-erection of 63 KVA Uprooted Distribution Sub-Station (Transformer available at site) |
| 41 | 11/0.433 KV, 3 Phase 63 KVA Distribution Transformer with Bi-Mettalic Terminal Connectors (Energy Level-2) Aluminium wound and with LV Cable Box having detachable Aluminium Gland Plate (Labour only). |
| 42 | Gapless Surge Arrester, 9 KV, 10 KA, LA with Polymer housing Station Type |
| 43 | 11 KV GO, AB Switch 3 Phase, 3 Pole, 200 amp, vertical type |
| 44 | ST Poles 9 Mtr Long (ST -410 SP 33) |
| 45 | 11 KV Horn Gap Fuse Set 3 Phase, 200Amp |
| 46 | 11 KV Polymeric Composite Disc Insulators 12KV, min following load 45 KN, Lightening impulse 75KV positive and 80KV negative, creepage distance 320mm with Fittings |
| 47 | Galvanized Nuts & Bolts |
| 48 | Earthing of Sub-Station -Excavation of earth pit of diameter 650mm and deapth 3000mm, installation of earthing pipe of 40mm nominal bore and 4mm wall thickness and length 2.5m long as per IS 1239 GI Strip for neutral earthing of size 25mm into 3 mm for connection of transformer body, GO Set and lightening arrestor as per IS 2629/85, GI Nuts & Bolts, refilled with earth enhancement material |
| 49 | 11 KV Polymeric composite Pin Insulators 12KV, 5KN, lighting inpulse 75KV positive and 80KV negative, creepage distance 320mm |
| 50 | 70 mmsq PVC Cable single core |
| 51 | Cement Bottoming 1:2:4 mix as per REC Standards 0.5cum/pole |
| 52 | Work G- Supply, Erection, Testing and commissioning for Re-erection of 250 KVA Uprooted Distribution Sub-Station (Transformer available at site) |
| 53 | 11/0.433 KV, 3 Phase 250 KVA Distribution Transformer with Bi-Mettalic Terminal Connectors (Energy Level-2) Copper wound and with LV Cable Box having detachable Aluminium Gland Plate (Labour only). |
| 54 | Gapless Surge Arrester, 9 KV, 10 KA, LA with Polymer housing Station Type |
| 55 | 11 KV GO, AB Switch 3 Phase, 3 Pole, 200 amp, vertical type |
| 56 | ST Poles 9 Mtr Long (ST -410 SP 33) |
| 57 | 11 KV Horn Gap Fuse Set 3 Phase, 200 amp |
| 58 | 11 KV Polymeric Composite Disc Insulators 12KV, min following load 45 KN, Lightening impulse 75KV positive and 80KV negative, creepage distance 320mm with Fittings |
| 59 | Galvanized Nuts & Bolts |
| 60 | Earthing of Sub-Station -Excavation of earth pitof diameter 650mm and deapth 3000mm, installation of earthing pipe of 40mm nominal bore and 4mm wall thickness and length 2.5m long as per IS 1239 GI Strip for neutral earthing of size 25mm into 3mm for connection of transformer body, GO Set and lightening arrestor as per IS 2629/85, GI Nuts & Bolts, refilled with earth enhancement material |
| 61 | 11 KV Polymeric composite Pin Insulators 12KV, 5KN,lighting inpulse 75KV positive and 80KV negative, creepage distance 320mm |
| 62 | 185 mmsq PVC Cable single core 2(ckt) |
| 63 | Cement Bottoming 1:2:4 mix as per REC Standards 0.5cum/pole |
| 64 | Work H- Supply, Erection, Testing and commissioning for Re-erection of 400KVA Uprooted Distribution Sub-Station (Transformer available at site) |
| 65 | 11/0.433 KV, 3 Phase 400 KVA Distribution Transformer with Bi-Mettalic Terminal Connectors (Energy Level-2) Copper wound and with LV Cable Box having detachable Aluminium Gland Plate (Labour only). |
| 66 | Gapless Surge Arrester, 9 KV, 10 KA, LA with Polymer housing Station Type |
| 67 | 11 KV GO, AB Switch 3 Phase, 3 Pole, 200 amp, vertical type |
| 68 | ST Poles 9 Mtr Long (ST -410 SP 33) |
| 69 | 11 KV Horn Gap Fuse Set 3 Phase, 200 amp |
| 70 | 11 KV Polymeric Composite Disc Insulators 12KV, min following load 45 KN, Lightening impulse 75KV positive and 80KV negative, creepage distance 320mm with Fittings |
| 71 | Galvanized Nuts & Bolts |
| 72 | Earthing of Sub-Station -Excavation of earth pit of diameter 650mm and deapth 3000mm, installation of earthing pipe of 40mm nominal bore and 4mm wall thickness and length 2.5m long as per IS 1239 GI Strip for neutral earthing of size 25mm into 3 mm for connection of transformer body, GO Set and lightening arrestor as per IS 2629/85, GI Nuts & Bolts, refilled with earth enhancement material |
| 73 | 11 KV Polymeric composite Pin Insulators 12KV, 5KN,lighting inpulse 75KV positive and 80KV negative, creepage distance 320mm |
| 74 | 240 mmsq PVC Cable single core 2(ckt) |
| 75 | Cement Bottoming 1:2:4 mix as per REC Standards 0.5cum/pole |
| 76 | Work I- Supply, Erection, Testing and commissioning for Re-Creation of Washed Away/Damaged 25KVA Distribution Sub-Station |
| 77 | 11/0.433 KV, 3 Phase 25 KVA Distribution Transformer with Bi-Mettalic Terminal Connectors (Energy Level-2) Aluminium wound and with LV Cable Box having detachable Aluminium Gland Plate. |
| 78 | Gapless Surge Arrester, 9 KV, 10 KA, LA with Polymer housing Station Type |
| 79 | 11 KV GO, AB Switch 3 Phase, 3 Pole, 200 amp, vertical type |
| 80 | 11 KV Horn Gap Fuse Set 3 Phase, 200 amp |
| 81 | 50mm² Cable, 1.1 kV Grade, PVC Insulated Stranded Conductor FRLS type. |
| 82 | ST Poles 9 Mtr Long (ST -410 SP 33) |
| 83 | 11 KV Polymeric Composite Disc Insulators 12KV, min following load 45 KN, Lightening impulse 75KV positive and 80KV negative, creepage distance 320mm with Fittings |
| 84 | GI Channel/Angle/Flat of sizes including clamps |
| 85 | Galvanized Nuts & Bolts |
| 86 | Earthing of Sub-Station -Excavation of earth pitof diameter 650mm and deapth 3000mm, installation of earthing pipe of 40mm nominal bore and 4mm wall thickness and length 2.5m long as per IS 1239 GI Strip for neutral earthing of size 25mm into 3 mmfor connection of transformer body, GO Set and lightening arrestor as per IS 2629/85, GI Nuts & Bolts, refilled with earth enhancement material |
| 87 | Cement Bottoming 1:2:4 mix as per REC Standards 0.5cum/pole |
| 88 | Sundry items like Aluminium Lugs, Jumpers, Binding Tape Aluminium Thimbles etc. |
| 89 | Work J- Supply, Erection, Testing and commissioning for Re-Creation of Washed Away/Damaged 63KVA Distribution Sub-Station |
| 90 | 11/0.433 KV, 3 Phase 63 KVA Distribution Transformer with Bi-Mettalic Terminal Connectors (Energy Level-2) Aluminium wound and with LV Cable Box having detachable Aluminium Gland Plate. |
| 91 | Gapless Surge Arrester, 9 KV, 10 KA, LA with Polymer housing Station Type |
| 92 | 11 KV GO, AB Switch 3 Phase, 3 Pole, 200 amp, vertical type |
| 93 | 11 KV Horn Gap Fuse Set 3 Phase, 200 amp |
| 94 | 70mm² Cable, 1.1 kV Grade, PVC Insulated Stranded Conductor FRLS type. |
| 95 | ST Poles 9 Mtr Long (ST -410 SP 33) |
| 96 | 11 KV Polymeric Composite Disc Insulators 12KV, min following load 45 KN, Lightening impulse 75KV positive and 80KV negative, creepage distance 320mm with Fittings |
| 97 | GI Channel/Angle/Flat of sizes including clamps |
| 98 | Galvanized Nuts & Bolts |
| 99 | Earthing of Sub-Station -Excavation of earth pitof diameter 650mm and deapth 3000mm, installation of earthing pipe of 40mm nominal bore and 4mm wall thickness and length 2.5m long as per IS 1239 GI Strip for neutral earthing of size 25mm into 3 mmfor connection of transformer body, GO Set and lightening arrestor as per IS 2629/85, GI Nuts & Bolts, refilled with earth enhancement material |
| 100 | 11 KV Polymeric composite Pin Insulators 12KV, 5KN,lighting inpulse 75KV positive and 80KV negative, creepage distance 320mm |
| 101 | Galvanized Stay Set with 50X8mm Stay clamp, Guy insulator (2 Nos), anchor plate (200X200X6mm) Nuts & Bolts, 2nos turn buckles,1.8mm long, 16mm diameter solid GS stay rod and 7/3.15mm dia GI standard wire complete |
| 102 | Wedge Connectors/ PG Calmps |
| 103 | Danger Plates with Clamps |
| 104 | GI Barbed wire for Anti Climbing |
| 105 | Cement Bottoming 1:2:4 mix as per REC Standards 0.5cum/pole |
| 106 | Painting of Poles Red-Oxide |
| 107 | Painting of Poles Aluminium Paint |
| 108 | Sundry items like Aluminium Lugs, Jumpers, Binding Tape Aluminium Thimbles etc. |
| 109 | Work K- Supply, Erection, Testing and commissioning for Re-Creation of Washed Away/Damaged 100KVA Distribution Sub-Station |
| 110 | 11/0.433 KV, 3 Phase 100 KVA Distribution Transformer with Bi-Mettalic Terminal Connectors (Energy Level-2) Aluminium wound and with LV Cable Box having detachable Aluminium Gland Plate. |
| 111 | Gapless Surge Arrester, 9 KV, 10 KA, LA with Polymer housing Station Type |
| 112 | 11 KV GO, AB Switch 3 Phase, 3 Pole, 200 amp, vertical type |
| 113 | 11 KV Horn Gap Fuse Set 3 Phase, 200 amp |
| 114 | 185 mm² Cable, 1.1 kV Grade, PVC Insulated Stranded Conductor FRLS type. |
| 115 | ST Poles 9 Mtr Long (ST -410 SP 33) |
| 116 | 11 KV Polymeric Composite Disc Insulators 12KV, min following load 45 KN, Lightening impulse 75KV positive and 80KV negative, creepage distance 320mm with Fittings |
| 117 | GI Channel/Angle/Flat of sizes including clamps |
| 118 | Galvinized Nuts & Bolts |
| 119 | Earthing of Sub-Station -Excavation of earth pit of diameter 650mm and deapth 3000mm, installation of earthing pipe of 40mm nominal bore and 4mm wall thickness and length 2.5m long as per IS 1239 GI Strip for neutral earthing of size 25mm into 3 mmfor connection of transformer body, GO Set and lightening arrestor as per IS 2629/85, GI Nuts & Bolts, refilled with earth enhancement material |
| 120 | 11 KV Polymeric composite Pin Insulators 12KV, 5KN,lighting inpulse 75KV positive and 80KV negative, creepage distance 320mm |
| 121 | Galvanized Stay Set with 50X8mm Stay clamp, Guy insulator (2 Nos), anchor plate (200X200X6mm) Nuts & Bolts, 2 nos turn buckles,1.8mm long, 16mm diameter solid GS stay rod and 7/3.15mm dia GI standard wire complete |
| 122 | Wedge Connectors/ PG Calmps |
| 123 | Danger Plates with Clamps |
| 124 | GI Barbed wire for Anti Climbing |
| 125 | Cement Bottoming 1:2:4 mix as per REC Standards 0.5cum/pole |
| 126 | Painting of Poles Red-Oxide |
| 127 | Painting of Poles Aluminium Paint |
| 128 | Sundry items like Aluminium Lugs, Jumpers, Binding Tape Aluminium Thimbles etc. |
| 129 | Work L- Supply, Erection, Testing and commissioning for Re-Creation of Washed Away/Damaged 250KVA Distribution Sub-Station |
| 130 | 11/0.433 KV, 3 Phase 250 KVA Distribution Transformer with Bi-Mettalic Terminal Connectors (Energy Level-2) Copper wound and with LV Cable Box having detachable Aluminium Gland Plate. |
| 131 | Gapless Surge Arrester, 9 KV, 10 KA, LA with Polymer housing Station Type |
| 132 | 11 KV GO, AB Switch 3 Phase, 3 Pole, 200 amp, vertical type |
| 133 | 11 KV Horn Gap Fuse Set 3 Phase, 200 amp |
| 134 | 185mm² Cable (2-CKT), 1.1 kV Grade, PVC Insulated Stranded Conductor FRLS type. |
| 135 | ST Poles 9 Mtr Long (ST -410 SP 33) |
| 136 | 11 KV Polymeric Composite Disc Insulators 12KV, min following load 45 KN, Lightening impulse 75KV positive and 80KV negative, creepage distance 320mm with Fittings |
| 137 | GI Channel/Angle/Flat of sizes including clamps |
| 138 | Galvanized Nuts & Bolts |
| 139 | Earthing of Sub-Station -Excavation of earth pitof diameter 650mm and deapth 3000mm, installation of earthing pipe of 40mm nominal bore and 4mm wall thickness and length 2.5m long as per IS 1239 GI Strip for neutral earthing of size 25mm into 3 mmfor connection of transformer body, GO Set and lightening arrestor as per IS 2629/85, GI Nuts & Bolts, refilled with earth enhancement material |
| 140 | 11 KV Polymeric composite Pin Insulators 12KV, 5KN,lighting inpulse 75KV positive and 80KV negative, creepage distance 320mm |
| 141 | Galvanized Stay Set with 50X8mm Stay clamp, Guy insulator (2 Nos), anchor plate (200X200X6mm) Nuts & Bolts, 2 nos turn buckles,1.8mm long, 16mm diameter solid GS stay rod and 7/3.15mm dia GI standard wire complete |
| 142 | Wedge Connectors/ PG Calmps |
| 143 | Danger Plates with Clamps |
| 144 | GI Barbed wire for Anti Climbing |
| 145 | Cement Bottoming 1:2:4 mix as per REC Standards 0.5cum/pole |
| 146 | Painting of Poles Red-Oxide |
| 147 | Painting of Poles Aluminium Paint |
| 148 | Sundry items like Aluminium Lugs, Jumpers, Binding Tape Aluminium Thimbles etc. |
| 149 | Work M- Supply, Erection, Testing and commissioning for Laying of HT Line on 9 Mtr Long ST Poles using ACSR Rabbit conductor due to Shifting/ Realignment of HT Network at sinking roads/ Landslide prone areas |
| 150 | ST Poles 9 Mtr Long (ST -410 SP 33) |
| 151 | GI V cross-arm with top Brackets including clamp |
| 152 | GI Channel X-arm including clamp and braces |
| 153 | ACSR Rabbit Conductor (50 mm²) |
| 154 | PG Clamps for 50mm² ACSR conductor |
| 155 | 11 KV Polymer composite Pin Insulators 12KV, 5KN, Lighting impulse 75KV positive and 80KV negative, creepage distance 320mm |
| 156 | 11 KV Polymer composite Disc Insulator 12KV,min falling load 45KN, Lighting impulse 75KV positive and 80KV negative, creepage distance 320mm |
| 157 | Galvanized nuts & Bolts |
| 158 | Danger Plates with Clamps |
| 159 | Anti Climbing Device with Clamps |
| 160 | Earthing Complete by GI Pipe 40 mm or GI Rod 20 mm 2.5 mtr long through GI Strip |
| 161 | Cement Bottoming 1:2:4 mix as per REC Standards 0.5cum/pole |
| 162 | Red-Oxide |
| 163 | Aluminium Paint |
| 164 | Aluminium Jointing sleeves |
| 165 | Galvanized Stay Set with 50X8mm Stay clamp, Guy insulator (2 Nos), anchor plate (200X200X6mm) Nuts & Bolts, 2 nos turn buckles,1.8mm long, 16mm diameter solid GS stay rod and 7/3.15mm dia GI standard wire complete |
| 166 | Work N-Supply, Erection, Testing and commissioning for Laying of LT Line on 8 Mtr Long ST Poles using ACSR Rabbit conductor due to Shifting/ Realignment of HT Network at sinking roads/ Landslide prone areas |
| 167 | ST Poles 8 Mtr Long (ST-410 SP 15) |
| 168 | GI U-Clamps for Shackle Insulator |
| 169 | ACSR Rabbit Conductor (50 mm²) |
| 170 | 16 kN Polymer Shackle Insulator |
| 171 | Galvanized nuts & Bolts |
| 172 | Danger Plates |
| 173 | Anti Climbing Devices with Clamps |
| 174 | Earthing Complete by GI Pipe 40 mm or GI Rod 20 mm 2.5 mtr long through GI Strip |
| 175 | Cement Bottoming 1:2:4 mix as per REC standards .45 cum/pole |
| 176 | Red oxide |
| 177 | Aluminium Paint |
| 178 | Aluminium Jointing sleeves |
| 179 | LT Line Spacer |
| 180 | Galvanized Stay Set with 50X8mm Stay clamp, Guy insulator (2 Nos), anchor plate (200X200X6mm) Nuts & Bolts, 2 nos turn buckles,1.8mm long, 16mm diameter solid GS stay rod and 7/3.15mm dia GI standard wire complete Total in Figures 0.0 0.0 INR Zero Only Quoted Rate in Figures Select 0.0 0.0 Zero Only Quoted Rate in Words INR Zero Only Please Enable Macros to View BoQ information |