| 1 | Taking out existing CC interlocking paver blocks from footpath/ central verge, including removal of rubbish etc., disposal of unserviceable material to the dumping ground, for which payment shall be made separately and stacking of serviceable material within 50 metre lead as per direction of Engineer-in-Charge. (DSR/2023 - 16:83) |
| 2 | Construction of GSB sub-base by providing close graded material (Grade-1), spreading in uniform. Layers with motor grader on prepased surface, mixing with place method with rotavater at OMC, and compacting with vbratory to achive the disired dencity, complete as per MORTH Clause 401.(A/R) |
| 3 | Laying old cement cocrete interlocking gaver blocks of any design/ shape laid in required line, level, curvature, colour and pattern over and including 50 mm thick compacted bed of coarse sand, filling the joints with fine sand etc. all complete as per the direction of Engineer-in-charge. (Old CC paver blocks shall be supplied by the department free of cost).(DSR/2023 - 16:84) |
| 4 | Brick work with common burnt clay modular bricks of class designation 7.5 in foundation and plinth in Cement mortar 1:4 (1 cement : 4 coarse sand)(DSR/2023 - 6.2.1) |
| 5 | Providing and laying cement concrete in kerbs, steps and the like at or near ground level excluding the cost of centering, shuttering and finishing. (1 Cement: 1½ coarse sand(zone-III) derived from natural sources : 3 graded stone aggregate 20 mm nominal size derived from natural sources)(DSR/2023 - 4.4.1) |
| 6 | Supply of seprate membrain plastic sheet. (DSR/2023 - 323) |
| 7 | Cement concrete manufactured in automatic batching plant (RMC plant) including transportation to site in transit mixer.(DSR/2023 - 16:43:2) |
| 8 | Extra for providing and mixing hardening compound of approved quality as per manufacturer's specification in cement concrete.(DSR/2023 - 16:44) |
| 9 | Mild steel and Medium Tensile steel bars.(DSR/2023 - 5.22A.1) |
| 10 | Providing and fixing pre-moulded joint filler in expansion joints of RCC roads / CC pavements after making the joints dust free with high pressure air jet cleaners, all complete as per direction of the Engineer-in-Charge. (Pre-moulded joint fillers shall be made of bitumen hot sealing compound impregnated fibre board having impregnation more than 35%, conforming to IS:1838 for fibre board and IS: 1834 for hot sealing bitumen compound grade A.)(DSR/2023 - 16:45) |
| 11 | Cartage of dismanteled material/garbage up to 3.0km (Sor-2025) |
| 12 | Foundations, footings, bases of columns, etc. for mass concrete.(DSR/2023 - 5.9.1) |
| 13 | 12 mm cement plaster of mix.1:4 (1 cement: 4 coarse sand)(DSR/2023 - 13.4.1) |
| 14 | Painting with synthetic enamel paint of approved brand and manufacture of required colour to give an even shade. Two or more coats on new work over an under coat of suitable shade with ordinary paint of approved brand and manufacture.(DSR/2023 - 13.62.1) |
| 15 | Dudct cost of Interlocking C.C. paver block ( 60 mm thick, M-30) (including carriage)(DSR/2023 - 8689) Please Enable Macros to View BoQ information |