| 1 | Carriage of PCC Pole 8.5 mtr long From ESC, Sitapur to Dump site |
| 2 | Carriage of ST Pole 11 mtr long From ESC, Sitapur to Dump Site |
| 3 | Carriage of ASCR Weaseal Conductor From ESC, Sitapur to Dump Site |
| 4 | Carriage of AB Cable & XLPE Cable |
| 5 | Carriage of 25/63/100 KVA Transformer From ESC, Sitapur to work site |
| 6 | Shifting of PCC Pole 8.5 mtr long From Dump site to work site |
| 7 | Shifting of ST Pole 11mtr long From Dump site to work site |
| 8 | Shifting of ASCR Weaseal Conductor From Dump site to Work Site |
| 9 | Shifting of AB Cable & XLPE Cable |
| 10 | Carriage of other line material From ESC, Sitapur to dump Site |
| 11 | Shifting of other Line material from Dump site to Work site |
| 12 | Fabrication & erection of single pole for 11 KV line on 8.5/9.0 M long PCC Pole with fixing of necessary clamp & other acessories like Nut & Bolt & Fbracket, etc. contractor shall provide, all material except pole as per RESPO norms |
| 13 | Fabrication & erection of Double pole for 11 KV line on 8.5/9.0 M long PCC Pole with fixing of necessary clamp & other acessories like Nut & Bolt & F bracket, etc. contractor shall provide, all material except pole as per RESPO norms |
| 14 | Fabrication & erection of Single pole for 11 KV line on 13 M long ST Pole with ffixing of necessary clamp & other acessories like Nut & Bolt & Fbracket, etc. contractor shall provide, all material except pole as per RESPO norms |
| 15 | Laying of ACSR Weaseal conductor 3 phase 3 wire |
| 16 | Laying of XLPE Cable |
| 17 | Laying of AB Cable |
| 18 | Mounting of 25/63/100 KVA T/F |
| 19 | Well type pipe earthing depth 40 fit with GI Pipe (20 mm Dia) and 50x6 mm GI Strip with clamp. (All material provided by the contractor) |
| 20 | Hoisting of 11 KV XLPE cable on double pole with GI pipe of size 4\\" dia 3 M long including its jumpering complete with clamps, nuts and bolts(all material arranged by contractor except 11 kv cable). |
| 21 | Fixing of Metering Cubical |
| 22 | Fixing and Mounting of CT PT Unit |
| 23 | Making outdoor/Indoor Jointing kit |
| 24 | Earthing of PCC Pole |
| 25 | Earthing of ST Pole |
| 26 | Fixing of Stay |
| 27 | Making T-off arrnagement |
| 28 | Gaurding of Line |
| 29 | Grouting of PCC Pole |
| 30 | Grouting of ST Pole |
| 31 | Grouting of Stay |
| 32 | Safe Carriage of Loading & Un Loading Scrap/used line material From work site to JE Store/ESC, Sitapur Please Enable Macros to View BoQ information |