| 1 | SUPPLY INSTALLATION TESTING & COMMISSIONING OF STP Pole 13 Mtr Long (SP-70). Complete in all respect as per direction of E/I |
| 2 | SUPPLY & INSTALLATION of V Type cross arm.Complete in all respect as per direction of E/I |
| 3 | SUPPLY & INSTALLATION OF F-Bracket PROPER COMPLETION OF WORK AS PER DIRECTION OF E/In |
| 4 | Supply & Installation of packing piece and clamp for above with bolts and nuts. complete in all respects as per direction of E/I |
| 5 | Making of proper earthing of pole.Including Earthwire Clamp with nut & bolts .complete in all respects as per direction of E/I |
| 6 | Supply & Fixing of armour rod with ferules for dog. COMPLETION OF WORK AS PER DIRECTION OF E/In |
| 7 | Supply & Fixing of 33 KV Polymeric Pin Insulator with pin and nut .COMPLETION OF WORK AS PER DIRECTION OF E/In |
| 8 | Supply & Fixing of ACSR Panther Conducter for Jumper. COMPLETION OF WORK AS PER DIRECTION OF E/In |
| 9 | SUPPLY & Fixing of MS BOLTS & nujts with washer COMPLETION OF WORK AS PER DIRECTION OF E/In |
| 10 | SUPPLY & FIXING OF Aluminium binding wire 6SWG.COMPLETION OF WORK AS PER DIRECTION OF E/In |
| 11 | Painting of Pole over red oxide primer with aluminium paint COMPLETION OF WORK AS PER DIRECTION OF E/In |
| 12 | SUPPLY & FIXING OF Danger Board with clamp and Nut Bolt. PROPER COMPLETION OF WORK AS PER DIRECTION OF E/In |
| 13 | SUPPLY & FIXING OF number plate with clamp and Nut Bolt. PROPER COMPLETION OF WORK AS PER DIRECTION OF E/In |
| 14 | Supply and Fixing of Barbed wire. PROPER COMPLETION OF WORK AS PER DIRECTION OF E/In |
| 15 | Suply and fixing of guarding for 33 KV line complete in all respect as per direction of E/I |
| 16 | Supply and fixing of tripole structure on 13 mtr. Long STP for 33 kv line complete in all respect as per direction of E/I |
| 17 | Supply and Installation of STP 11 Mtr. Long (SP-55) Pole. PROPER COMPLETION OF WORK AS PER DIRECTION OF E/In |
| 18 | Supply and Installation of MS channer (Dropper) 100X50X2028 mm(for fuse set) PROPER COMPLETION OF WORK AS PER DIRECTION OF E/In |
| 19 | Supply and Fixing of Clamps for LT T-off with bolts & Nuts. PROPER COMPLETION OF WORK AS PER DIRECTION OF E/In |
| 20 | Supply and Fixing of Holding Clamps for top channel, TPMO & fuse set etc. with bolts & Nuts. PROPER COMPLETION OF WORK AS PER DIRECTION OF E/In |
| 21 | Supply and Fixing of MS Angle 75X75X6X2028 mm with clamp & bolts & Nuts (T/F base). PROPER COMPLETION OF WORK AS PER DIRECTION OF E/In |
| 22 | Supply and Fixing of MS Top Channel(125X65X2240mm). PROPER COMPLETION OF WORK AS PER DIRECTION OF E/In. |
| 23 | Supply and Fixing of MS Channel 125X65X1300(T-off). PROPER COMPLETION OF WORK AS PER DIRECTION OF E/In. |
| 24 | Supply and Fixing of 11 KV Polymeric Pin Insulator. PROPER COMPLETION OF WORK AS PER DIRECTION OF E/In. |
| 25 | Supply and Fixing of 11 KV Pin with Nut. PROPER COMPLETION OF WORK AS PER DIRECTION OF E/In. |
| 26 | Supply and Fixing of 3 Ph. D.O.Fuse Set. PROPER COMPLETION OF WORK AS PER DIRECTION OF E/In. |
| 27 | Supply and Fixing of LT Fuse Set Protection Unit for 25 Kva DT with SMC Box. PROPER COMPLETION OF WORK AS PER DIRECTION OF E/In. |
| 28 | Supply and Fixing of LT PVC Cable 4X16 sq.mm. PROPER COMPLETION OF WORK AS PER DIRECTION OF E/In. |
| 29 | Supply and Fixing of Stay Set Complete.PROPER COMPLETION OF WORK AS PER DIRECTION OF E/In. |
| 30 | Concreting of Stay.PROPER COMPLETION OF WORK AS PER DIRECTION OF E/In. |
| 31 | Existing/Old & Used 25 KVA T/F Shifting from D/P to Newly Constructed D/P and reinstallation of existing T/F Safely on D/P inclunding dismantling and cartage. PROPER COMPLETION OF WORK AS PER DIRECTION OF E/In.. |
| 32 | Supply and Fixing of 11KV XLPE Cable 3x185 sqmm .PROPER COMPLETION OF WORK AS PER DIRECTION OF E/In. |
| 33 | Supply and Making of 11KV Jointing Kit 3x185 sqmm.PROPER COMPLETION OF WORK AS PER DIRECTION OF E/In. |
| 34 | Supply and Fixing of ACSR Ins Dog Conductor for Jumpering..PROPER COMPLETION OF WORK AS PER DIRECTION OF E/In. |
| 35 | Supply and laying/ Errection of 3.5c x240sqmm XLPE Cable.PROPER COMPLETION OF WORK AS PER DIRECTION OF E/In. |
| 36 | Supply & Making of LT straight through 240sqmm |
| 37 | Supply and laying/Errection 3.5Core x150 sqmm XLPE Cable |
| 38 | B2 Type Distribution Panel with motorised change over switch 250 Amp. & ATS Control System Incoming:- 250 Amp MCCB(FP) Outgoing:- 125 Amp 06 Nos. MCCB TP+N. SWITCHGEAR MAKE:SCHEINDER/ABB/SIEMENS/L&T |
| 39 | Making of cable end termination using total double compresion gland 240 Sqmm(weather proof) .complete in all respects as per direction of E/I |
| 40 | Making of cable end termination using total double compresion gland 150 Sqmm(weather proof) .complete in all respects as per direction of E/I |
| 41 | Supply and Fixing of LT Distribution Board(Type C) with structure. PROPER COMPLETION OF WORK AS PER DIRECTION OF E/In |
| 42 | Supply and Fixing of Aluminium Lug 240 sqmm PROPER COMPLETION OF WORK AS PER DIRECTION OF E/In |
| 43 | Supply and Fixing of Aluminium Lug 150 sqmm PROPER COMPLETION OF WORK AS PER DIRECTION OF E/In |
| 44 | Supply and Fixing of Chemical Earthing of B Panel. PROPER COMPLETION OF WORK AS PER DIRECTION OF E/In |
| 45 | Shifting Charges of existing A Type Panel from existing site and Installation Charges for existing A Type Panel with new Structure at proposed site .PROPER COMPLETION OF WORK AS PER DIRECTION OF E/In |
| 46 | MS Fencing of existing A Type Panel & 250 KVA T/F.PROPER COMPLETION OF WORK AS PER DIRECTION OF E/In |
| 47 | Shifting Charges of existing C Type Panel from existing site and Installation Charges for existing C Type Panel with new Structure at proposed site .PROPER COMPLETION OF WORK AS PER DIRECTION OF E/In |
| 48 | Supply and Fixing of 2cx10 Sqmm Armoured cable. PROPER COMPLETION OF WORK AS PER DIRECTION OF E/In |
| 49 | Supply and Fixing of PVC pipe of 2\\" Diameter. PROPER COMPLETION OF WORK AS PER DIRECTION OF E/In |
| 50 | Supply and Fixing of 10 Sqmm Aluminium Thimble . PROPER COMPLETION OF WORK AS PER DIRECTION OF E/In |
| 51 | Supply and Fixing of Single Phase Static Whole Current Meter with Meter Box. PROPER COMPLETION OF WORK AS PER DIRECTION OF E/In |
| 52 | Supply and Fixing of 3.5 C x 35 sq mm armoured . PROPER COMPLETION OF WORK AS PER DIRECTION OF E/In |
| 53 | Supply and Fixing of PVC pipe of 3” Diameter. PROPER COMPLETION OF WORK AS PER DIRECTION OF E/In |
| 54 | Supply and Fixing of 35 Sqmm Aluminium Thimble . PROPER COMPLETION OF WORK AS PER DIRECTION OF E/In |
| 55 | supply and fixing of three phase static whole current meter with meter box ,proper completion of work as per direction of E/I. |
| 56 | Dismentaling and cartage of dismenteld charges for existing 33 kv line and pole from site to store as per direction of E/I.. |
| 57 | Dismentaling and cartage charges for existing T/F D.P. and other accesaries as per direction of E/I.. |
| 58 | Dismentaling charges for existing LT line panel and other accesaries as per direction of E/I.. Please Enable Macros to View BoQ information |