Power Government Departments Closing in 0 days TDR #55275092

Tender For Tender For Prov.&Erection 11 Kv Ht Line To Proposed 11/0.4 Kv 100 Kva Dtr At Lower Haroli For Submersible Pump 40Bhp Motor Tubewell Connection Near Jal Shakti Vibhag Rest House At Haroli Under Esd Hpsebl Haroli.

Issued by Government Departments · Haroli, Himachal Pradesh
Tender Value
14.80 Lakhs
Estimated cost
Bid Submission
06 May 2026
0 days left
EMD
14807
Bank guarantee accepted
Document Fee
590
Non-refundable
Tender Type
Online

Tender Overview

Competition Type
NCB
Bidding Type
Tender
Location / State
Haroli → Himachal Pradesh
EMD Exemption
Not Available
Quantity
Not Available

Project Description

Tender for Tender For Prov.&Erection 11 Kv Ht Line To Proposed 11/0.4 Kv 100 Kva Dtr At Lower Haroli For Submersible Pump 40Bhp Motor Tubewell Connection Near Jal Shakti Vibhag Rest House At Haroli Under Esd Hpsebl Haroli.

BOQ

Name of Work:- Tender for prov.&erection 11 KV HT Line to proposed 11/0.4 KV 100 KVA DTR at lower Haroli for submersible Pump 40BHP motor T/well connection near Jal Shakti Vibhag rest House at Haroli under ESD HPSEBL Haroli.
Sl. No. Item Description
1Erection Part of 11 KV HT Line /2025-26
2Erection of S.T Single Pole 9 Mtr. Long :- Digging of Pit,fixing of insulator, disc and drilling of holes in X-Arm , Bracing Set, Top Clamp, erection of pole, fixing of barbed wire and danger plate, filling of Pit, Alluminium Paint and ramming & painting of poles complete in all respect.
3Erection of S.T Single Pole 11 Mtr. Long :- Digging of Pit,fixing of insulator, disc and drilling of holes in X-Arm , Bracing Set, Top Clamp, erection of pole, fixing of barbed wire and danger plate, filling of Pit, Alluminium Paint and ramming & painting of poles complete in all respect.
4Erection of Double Pole 9 Mtr. Long Digging of Pit fixing of insulator, disc and drilling of holes in X-Arm , Bracing Set, Top Clamp, erection of pole, fixing of barbed wire and danger plate, filling of Pit, Alluminium Paint and ramming & painting of poles complete in all respect.
5Erection of Double Pole 11 Mtr. Long for Tapping Structure :- Digging of Pit fixing of insulator, disc and drilling of holes in X-Arm , Bracing Set, Top Clamp, erection of pole, fixing of barbed wire and danger plate, filling of Pit, Alluminium Paint and ramming & painting of poles complete in all respect.
6Erection of Earthing Set.:- Fixing of earthing pipe of pit for coal earthing, fixing of G.I wire to system filling of pit and remaning work complete in all respect.
7Erection of Stay Set HT:- Digging of Pit fixing of Stay Rod, filling of Pit, Nozeiling & Tightning complete in all respect.
8Stringing and sagging conductor:- Laying of conductor (AAAC 7/3.81 mm 80 mm²) stringing and sagging, binding with insulator complete in all respect.
9Laying of G.I Wire, Stringing, Sagging and binding complete in all respect.
10Fixing jumper complete in all respect.
11Erection of GO switch complete in all respect.
12Erection of DO Fuse complete in all respect.
13Transportation and Loading of materials HT lines materials on truck at Divisional Store and same material unloading at road to site of work with manual carriage.
14Erection Part of 11/0.4 KV, 100 KVA Transformer
15Erection of S/Stn. Str.:-Digging of Pit for S/T Pole and earthing, drilling of holes in X-arm, preparation of plate form str. Member CI, Alluminium Paint AI i.e X-arml, Knee bracing set, erection of D-pole,errection of plate form, ercetion of x-Arm, drop out, fuse unit, linghting arrestor, MCCB Switch of LT Box, Energy Meter, Erection of T/F, and earthing conn. to T/F G.O Switch lightning etc. erection of Stay Set, Erection of Jumper, Pipe earthing 3 Nos., Erection of LT cable, brabed wire and painting, 3 Nos. earthing to S/Stn. by prov. 50Kg Salt charcole in each earthing i/c construction of trench for earthing as per REC Board Standard complete in all respect. ( 100 KVA Transformer)
16Transportation and Loading of S/Stn. complete and allied materials on truck at Divisional Store and same material unloading at road head of site of work and Manual Carriage Of DTR and allied Material For Average Distance From Road To Site Of Work .(Required as per site).
17Supply Part of 11 KV HT Line
18Prov. Steel Tubular Poles (9m, Working Load > 227kgf/m²) with Steel cap & Base Plate
19Prov. Steel Tubular Poles 11m, Long with Steel cap & Base Plate (Supply by HPSEBL 3 Each)
20Prov. RCC Muff
21Prov. concrete filling in RCC muff
22Prov. (AAAC 7/3.81 mm 80 mm²) mm Conductor
23Run Through Str. ( ∆) Formation on Singlr Pole Str.
24Prov. Cross Arm (Channel Iron (100x50x6) Length 1270 mm for single pole
25Prov. Angle Iron (50x50x6mm) Leggth 750 mmx 2*2 nos structure
26Prov. Pole Top Bracket (MSCI) (100X50X6 mm) Length 100 mm
27Prov.11kv Pin Insulator with pin complete in all respect
28Dead end Structure:
29Prov.Belt set -MS Angle Iron 50x50x6,Length 1800mm x2No.
30Prov.X-Bracing set -MS Angle iron 50x50x6,length 2125mmx2no
31Prov.X-Arm (Horizontal )Ms Channel (100x50x6,Length 2340x2mm2no formation
32Prov.Discs insulator sets on Dead End structures (comprising 1 No. Disc: ^^(Disc Polymeric,TC, 90 KN ) including Dead End Clamps etc.) x (3 No. conductors) x (2 No. sides)complete for double pole str in all respect. (Supply By HPSEBL 18 Set)
33Prov.11kv Pin Insulator with pin complete in all respect (Supply by HPSEBL 9 No.)
34HT Stay /guy Arrengement
35Prov. Stay set complete
36Prov. Stay Wire HT (10.0 kg Per Stay Set)
37Earthing
38Prov.11kv Earthing set complete in all respect.
39Prov.G.I.Wire No. 8 SWG in mtr.
40Prov.Eye/Earth Hook
41Prov.M.S Channel Iron :50x50x6,length:2800mm for road crossing
42Prov.MS Half Clamp
43Prov.MS Full Clamp/stay
44Prov.11kv Danger Plate (250x200x1.6 mm) (Supply by HPSEBL 18 No.)
45Prov.Nuts and Bolts of Various Sizes
46Prov.Barbed Wire
47Prov. Aluminium Paint.
48Prov. Red Oxide
4911 kv Knee Bracing Set 2X AI 750x50x50x6mm
50MS Channel Iron: 100X50x6, Length 600
51Prov. GO AB Switch Unit (11kV, 400A, 25 KA) Tripple pole O/D type
52Prov. D.O Fuse Unit
53Prov. X-Arm: [Channel Iron (75x40x6 mm), Length : 2800 mm X 4 Nos] for supporting DO fuse unit & GO switch
54Prov. GO Switch Handle Supporting: [Channel Iron (75x40x6 mm), Length: 460 mm
55Supply Part of 11/0.4 KV, 100 KVA Transformer
56Prov. Distribution Transformer (Ordinary), 11/0.4 kV, 100 KVA
57Prov. Steel Tubular Poles (9 m, Working Load > 200 kgf/m²)
58Prov. RCC Muff
59Prov. concrete filling in RCC muff
60Prov. X-Arm: [Channel Iron (100x50x6 mm), Length : 2800 mm X 2 Nos] for incomer line
61Prov. MS Angle Iron (50X50x6 mm), Length : 2800 mm x 1 Nos for LA.
62Prov. X-Arm: [Channel Iron (75x40x6 mm), Length : 2800 mm X 4 Nos] for supporting DO fuse unit & GO switch
63Transformer Belting & Knee Bracing
64Prov. X-Arm [Channel Iron (100x50x6 mm), Length : 2800 mm x 2 Nos for Transformer Bed]
65Prov. X-Arm [Channel Iron (100x50x6 mm), Length : 460 mm x 2 Nos for supporting main channel of Transformer]
66Prov. MS Angle Iron (50X50x6 mm), Length : 2800 mm x 2 Nos
67Prov. MS Angle Iron (35X35x5 mm), Length : 460 mm x 2 Nos
68Prov. MS Angle Iron (50X50x6 mm), Length: 950 mm x(2 Nos for Bed Knee Bracing)
69Transformer L.T Distribution Box and GO Switch fixing Assembly
70Prov. MS Angle Iron (50X50x6 mm), Length : 2800 mm x 2 Nos
71Prov. MS Angle Iron (50X50x6 mm), Length : 450 mm x 1 No.
72Prov. GO Switch Handle supporting : [Channel Iron (75x40x6mm), Length: 460 mm
73Prov. GO AB Switch Unit (11kV, 400A, 100 KA) Tripple Pole O/d Type
74Prov. D.O Fuse Unit
75Prov. Surge Arrester, 9 kV Station Class (Porcelain Type)
76Prov. Discs insulator (comprising 1 No. Disc: ^^(Porcelain, BS, 12 kV, 90 kN) CD- 400mm
77Prov. Stay set complete
78Prov. Stay Wire (7/3.15 mm) (10.0 kg Per Stay Set)
79Prov. Pipe Earthing Set
80Prov. 6 SWG GI wire For Earthing
81LT Distribution Panel Box with MS Sheet of 1.6 mm ( 900x800x200 mm ) cubide Box complete with stand etc and Al Busbar (25x6mm)inside .painted /powder coated after primar coating MCCB 160 amp 3P 35kA , ICS =100 % ICU, Kit-Kit 200 Amp for 100 KVA DTR
82Prov. Half Clamp (M.S. Flat 50X6 mm)
83Prov. Full Clamp (M.S. Flat 50X6 mm)
84Prov. Nuts and Bolts of Various Sizes (Galvanised / Coated) [Preferably 16 mm Φ or more (with flat and spring washers)]
85Prov. Aluminium Thimble
86Prov. Copper Thimble 200 Amp
87Prov. Danger Plate (Supply by HPSEBL 1 No.)
88Prov. Barbed Wire
89Prov. LT Cable 3.5 X 120 mm² 1.1 kV XLPE Cable Unarmoured (Supply HPSEBL 50 Mtr.)
90Prov. Aluminium Paint.
91Prov. Red Oxide
92Chain Link fencing , Angle Iron ,Gate etc for transformerfencingComplete in all respect. Please Enable Macros to View BoQ information

AI Tender Summary

OUR REF NO 55275092
AUTHORITY Government Departments
TENDER VALUE 14.80 Lakhs
LAST DATE 06-05-2026
Authority
Authority Name Himachal Pradesh State Electricity Board
Work Description Tender for Tender For Prov.&Erection 11 Kv Ht Line To Proposed 11/0.4 Kv 100 Kva Dtr At Lower Haroli For Submersible Pump 40Bhp Motor Tubewell Connection Near Jal Shakti Vibhag Rest House At Haroli Under Esd Hpsebl Haroli.
Basic Detail
Tender No HED/11/2026-27
Bidding Type Tender
Location
City Haroli
State Himachal Pradesh
Key Dates
Publish Date 29 Apr 2026
Submission Date 06 May 2026
Open Date 06 May 2026
Finance
Tender Value 14.80 Lakhs
Tender Fee 590
EMD 14807
Exemption Not Available
Document List
5144974c-5159-4c58-8036-f7b6b771fbb0.html
additionaltermanedcondition.pdf
BOQ_200358.xls
Tendernotice_1.pdf
termandcondition.pdf

Unlock Full AI Tender Summary

Get instant access to the complete AI-generated analysis — scope, eligibility, timeline & more.

Instant Access Secure Free
Your details are secure and used only for document delivery.

Tender Timeline

Apr 29, 2026
11:30 IST

Tender Published

Tender notice published.

Completed
May 06, 2026
17:00 IST

Bid Submission Deadline

Online submission via eProcurement portal.

Completed
May 06, 2026

Bid Opening Date

Technical bids will be opened and evaluated.

Completed

Tender Documents

Download All (ZIP) ↓
html

5144974c-5159-4c58-8036-f7b6b771fbb0.html

pdf

additionaltermanedcondition.pdf

xls

BOQ_200358.xls

pdf

Tendernotice_1.pdf

pdf

termandcondition.pdf

Disclaimer

We takes all possible care for accurate & authentic tender information. However users are requested to refer Original source of Tender Notice / Tender Document published by Tender Issuing Agency before taking any call regarding this tender

TenderDetail
Loading tenders