| 1 | Excavation in foundations in ordinary soil (Loam clay or sand) including lift upto 1.5 m (5 fts.) and lead upto 30 mt. (100 fts.) & including filling, watering and ramming of excavated earth into the trenches or into the space between the building and the sides of foundation trenches or into the plinth and removal and disposal of surplus earth as directed by the Engineer-Incharges upto a distance of 30mt. (100 fts) from the foundation trenches.(DSR-2.8.1) |
| 2 | Providing and laying in cement concrete 1:4:8 (1 cement :4 coarse sand :8 graded Stone aggregate 40 mm nominal size) and curing complete,including cost of form- work, in foundation and floors.(DSR-4.1.8) |
| 3 | Providing and laying in position specified grade of reinforced cement concrete, excluding the cost of centering, shuttering, finishing and reinforcement - All work up to plinth level :. 1:1.5:3 (1 cement : 1.5 coarse sand (zone-lll) derived from natural sources : 3 graded stone aggregate 20 mm nominal size derived from natural sources) (DSR-5.1.2) |
| 4 | Reinforced cement concrete work in beams, suspended floors, roofs having slope up to 15° landings, balconies, shelves, chaijjas, lintels, bands, plain window sills, staircases and spiral stair cases above plinth level up to floor five level, excluding the cost of centering, shuttering, finishing and reinforcement with 1:1.5:3 (1 cement : 1.5 coarse sand(zone-lll) derived from natural sources : 3 graded stone aggregate 20 mm nominal size derived from natural sources). (DSR-5.3) |
| 5 | Reinforced cement concrete work in walls (any thickness), including attached pilasters, buttresses, plinth and string courses, fillets, columns, pillars, piers, abutments, posts and struts etc. above plinth level up to floor five level, excluding cost of centering, shuttering, finishing and reinforcement 1:1.5:3 (1 cement : 1.5 coarse sand(zone-lll) derived from natural sources : 3 graded stone aggregate 20 mm nominal size derived from natural sources)(DSR-5.2.2) |
| 6 | TMT Fe-500 or iron in plain work such as reinforced concrete or reinforced, brick work (when not included in over all rates ) wrought to required shape as necessary including bending for proper completion of the work and including supply of steel its wastage bend hooks and authorised over lapping shall be measured upto floor two level. (DSR-5.22.6) |
| 7 | Brick work with common burnt clay F.P.S. (non modular) bricks of class designation 7.5 in foundation and plinth in:Cement mortar 1:6 (1 cement : 6 coarse sand)(DSR-6.1.2) |
| 8 | Brick work with common burnt clay F.P.S. (non modular) bricks of class designation 7.5 in superstructure above plinth level up to floor V level in all shapes and sizes in:Cement mortar 1:6 (1 cement : 6 coarse sand)(DSR-6.4.2) |
| 9 | 15 mm cement plaster on rough side of single or half brick wall of mix: 1:4 (1 cement: 4 coarse sand)(DSR-13.5.1) |
| 10 | Making grooves 10 to 12mm wide x 8mm deep in plaster of the wall or in ceiling vertically or horizontally as required.(DSR-13.76) |
| 11 | Finishing walls with Premium Acrylic Smooth exterior paint with Silicone additives of required shade. New work (Two or more coats applied @ 1.43 ltr/ 10 sqm. over and including priming coat of exterior primer applied @ 2.20 kg/ 10 sqm).(DSR-13.47.1) |
| 12 | Providing and applying white cement based putty of average thickness 1 mm, of approved brand and manufacturer, over the plastered wall surface to prepare the surface even and smooth complete.(DSR-13.8) |
| 13 | Providing and fixing concertina coil fencing with punched tape concertina coil 600 mm dia 10 metre openable length ( total length 90 m), having 50 nos rounds per 6 metre length, upto 3 m height of wall with existing angle iron ‘Y’ shaped placed 2.4m or 3.00 m apart and with 9 horizontal R.B.T. reinforced barbed wire, stud tied with G.I. staples and G.I. clips to retain horizontal, including necessary bolts or G.I. barbed wire tied to angle iron, all complete as per direction of Engineer-in-charge, with reinforced barbed tape(R.B.T.) / Spring core (2.5 mm thick) wire of high tensile strength of 165 kg/ sq. mm with tape (0.52 mm thick) and weight 43.478 gm/ metre (cost of M.S. angle, C.C. blocks shall be paid separately)(DSR-16.53) |
| 14 | Steel work welded in built up sections/ framed work, including cutting, hoisting, fixing in position and applying a priming coat of approved steel primer using structural steel etc. as required. 10.25.2 In gratings, frames, guard bar, ladder, railings, brackets, gates and similar works. (Angle iron 40*40*5)(DSR-10.25.2) |
| 15 | Centering and shuttering including strutting, propping etc. and removal of form for all heights : Foundations, footings, bases of columns, etc. for mass concrete.(DSR-5.9.1) |
| 16 | Centering and shuttering including strutting, propping etc. and removal of form for all heights : Columns,Pillars, Piers, Abutments, Posts and Struts.(DSR-5.9.6) |
| 17 | Centering and shuttering including strutting, propping etc. and removal of form for all heights : Lintels, beams, plinth beams, girders, bressumers and cantilevers.(DSR-5.9.5) |
| 18 | Earth work in excavation by mechanical means (Hydraulic excavator)/ manual means over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 sqm on plan) including getting out and disposal of excavated earth lead upto 50 m and for all lift, as directed by Engineer-in-charge.All kinds of soil(DSR-2.6.1) |
| 19 | 1:4:8 (1 Cement : 4 coarse sand (zone-lll) derived from natural sources : 8 graded stone aggregate 40 mm nominal size derived from natural sources)(DSR-4.1.8) |
| 20 | Providing and laying in position specified grade of reinforced cement concrete, excluding the cost of centering, shuttering, finishing and reinforcement - All work up to plinth level :1:1.5:3 (1 cement : 1.5 coarse sand (zone-lll) derived from natural sources : 3 graded stone aggregate 20 mm nominal size derived from natural sources)(DSR-5.1.2) |
| 21 | Reinforced cement concrete work in walls (any thickness), including attached pilasters, buttresses, plinth and string courses, fillets, columns, pillars, piers, abutments, posts and struts etc. above plinth level up to floor five level, excluding cost of centering, shuttering, finishing and reinforcement :1:1.5:3 (1 cement : 1.5 coarse sand(zone-lll) derived fromnatural sources : 3 graded stone aggregate 20 mm nominalsize derived from natural sources)(DSR-DSR-5.2.2) |
| 22 | Steel work welded in built up sections/ framed work, including cutting, hoisting, fixing in position and applying a priming coat of approved steel primer using structural steel etc. as required.10.25.2 In gratings, frames, guard bar, ladder, railings, brackets, gates and similar works(DSR-DSR-10.25.2) |
| 23 | Steel reinforcement for R.C.C. work including straightening, cutting, bending, placing in position and binding all complete upto plinth level.Mild steel and Medium Tensile steel bars(DSR- DSR 5.22.1) |
| 24 | Applying priming coat:With ready mixed red oxide zinc chromate primer of approved brand and manufacture on steel galvanised iron/ steel works(DSR-13.50.3) |
| 25 | Painting with synthetic enamel paint of approved brand and manufacture of required colour to give an even shade : Two or more coats on new work over an under coat of suitable shade with ordinary paint of approved brand and manufacture(DSR-13.62.1) |
| 26 | Centering and shuttering including strutting, propping etc. and removal of form for5.9.1 Foundations, footings, bases of columns, etc. for mass concrete(DSR-(DSR-5.9.1)) |
| 27 | Centering and shuttering including strutting, propping etc. and removal of form for :Columns, Pillars, Piers, Abutments, Posts and Struts(DSR-(DSR-5.9.6)) Note - 1- Rates are inclusive of all taxes but excluding GST which shall be paid extra as applicable 2- Labour cess @ 1% will be deducted from contractor's bill at the time of payment Please Enable Macros to View BoQ information |