| 1 | Dismantling and removing R.C.C. slab & pier including stacking the useful materials for reuse and removing the debris within 50m lead etc. with all labour charges, T&P, B&O.C. Workers Welfare Cess etc. complete as directed by the Engineer-in-charge. |
| 2 | Earth work in excavation of foundation in hard soil or gravelly soil with all lead ,lifts and delifts including dressing and breaking clods to maximum 5cm to 7cm and laying in layers not exceeding 0.3m depth including cost of all labour ,materials & T&P etc.Complete as directed by the Engineer-in-charge.of Engineer-in-charge. |
| 3 | Filling in foundation and plinth with sand including watering and ramming with cost, conveyance, royalty etc. complete as per direction of the Engineer-in-Charge. |
| 4 | Cement concrete (1:3:6) with 4cm size hard granite metal including all leads, lifts & delifts including cost, conveyance, royalty & taxes etc. of all materials, all labour charges, T&P, watering & curing, B&O.C. Workers Welfare Cess etc. complete as directed by the Engineer-in-charge. |
| 5 | Cement concrete (1:2:4) with 12mm size hard broken granite chips including with all leads, lifts & delifts including cost, conveyance, royalty & taxes etc. of all materials, all labour charges, T&P, watering & curing, B&O.C. Workers Welfare Cess etc. complete as directed by the Engineer-in-charge. |
| 6 | Supplying, fitting and placing uncoated HYSD Bar reinforcement complete as per drawing and technical specification including cost, conveyance, taxes of all materials and cost of all labours etc. complete as per direction of Engineer-in-charge. |
| 7 | Rigid and smooth centering and shuttering for PCC walls including false works and dismantling them after casting including cost of materials for RCC foundation, Plinth band & footing base of column mass concrete etc. complete as per direction of Engineer-in-Charge. |
| 8 | Providing formwork for Concrete with F1 finish for upstream faces of dam,spillway ,glacis of barrages,unexposed surfaces of foundation .block joints etc.with steel shutters rigidly fixed and removal of forms and making good to the surfaces where necessary complete with all labour,materials and T & P etc.Complete as directed by the Engineer-in-charge. where necessary complete with all labour,materials and T & P etc. Complete as directed by the Engineer-in-charge. |
| 9 | RCC work of M-20 grade(1:1½:3) with 20mm and down grade hard broken granite stone chips including hoisting and laying with all leads, lifts & delifts including cost, conveyance, royalty & taxes etc. of all materials, all labour charges, T&P, watering & curing, B&O.C. Workers Welfare Cess etc. complete as directed by the Engineer-in-charge. (vide item No.04, P- 50 of A.R. 2006) Data for 15 Cum |
| 10 | Filling in foundation and plinth with excavatedearth including watering and ramming etc. complete as directed by the Engineer-in-charge. |
| 11 | Earth work in approved type of soil in borrow area by mechanical means loading into and transportation by transport vehicle and unloading the earth on properly prepared surface with in 5km lead including rough dressing, breaking clods to maximum 50 to 70mm size & and laying in layers not exceeding 0.23M in depth with all leads, lifts, sundries, T&P required for the work etc. complete as directed by the Engineer in charge. Please Enable Macros to View BoQ information |