| 1 | Part A- Cost of Supply Of Materials. |
| 2 | Supply of materials for 33kV, 1Core, 630sqmm Aluminium,XLPE Insulation UG cable with accessories. |
| 3 | Supply of 33kV, 1Core, 630sqmm Alumnium XLPE insulation UG cable as per the specification and direction of EIC. |
| 4 | Supply of Outdoor termination kits Heat Shrinkable type suitable for 33kV 1Core, 630 sqmm, HT UG cable for 1Core as per the specification and direction of EIC. |
| 5 | Supply of Indoor termination kits Heat shrinkable type suitable for 33kv,1Core,630sqmm,HT UG cable kits as per the specification and direction of EIC. |
| 6 | Supply of Channel [email protected]/MTR. (GI) for cable trench(For 3 lane-780 mtr.) as per the specification and direction of EIC. |
| 7 | Part A- Cost of Erection Of Materials. |
| 8 | Laying, Commissioning, Testing of 33kV, 3x1core, 630sqmm, aluminium, XLPE UG cable. |
| 9 | Laying,Commissioning & Testing of 33kv,1 Core ,3Runs,630sqmm,XLPE insulation (extruted type) UG cable in trefoil formation by open trench method as per direction of EIC. |
| 10 | Erection of Outdoor termination kits Heat Shrinkable type suitable for 33kv,1Core ,630sqmm, HT UG cable kits as per direction of EIC. |
| 11 | Erection of Indoor termination kits Heat Shrinkable type suitable for 33kv,1Core, 630sqmm,HT UG cable kits.as per direction of EIC. |
| 12 | Part A- Cost of Civil Works. |
| 13 | Civil works with supply of all materials like cement, MS tor rod, brick, coarse & fine aggregates and labour, T&P, ete for UG Cable Trench. |
| 14 | Earth work excavation of soil (2.5 mtr width x 2.5 mtr depth) |
| 15 | Back filling with excavated soil outside and above the trench |
| 16 | Supply and erection of RCC trench (2000mtrD), 250mm thick, 2110 mm wide wide (M-30 grade) - Cast-in-SITU |
| 17 | Supply of rod, bending, cutting and binding of RCC trench (0.898 Quint/Cum) - Cast-in-SITU |
| 18 | PCC (1:3:6) below trench (width 2110 mm, thickness 100mm throughout) |
| 19 | Supply and erection of GI Pipe of dia. 150mm, Class-B (8Mtr.) as per the direction of EIC. |
| 20 | Part B-COST OF MATERIALS FOR 33KV DP WITH ISOLATOR - 2 Nos |
| 21 | Supply & installation of WPB 160X152 (13mtr. Long, 30.44KG/Mtr.). Including excavation of pole pit in all king of soil with depth upto 1/6th of pole height. Complete in all respect as per the approved technical specification and direction of EIC. |
| 22 | Supply & installation of Top Channel 100x50x6mm, 9.56 KG/Mtr. Each channel length 4.3 mtr.,2nos. Channel required = (2x9.56x4.3). Complete in all respect as per the approved technical specification and direction of EIC. |
| 23 | Supply & installation of Fish plate 50x6mm, 2.36kg/ mtr ,each 0.280mtr length,6nos. Required= (6x2.36x0.280). Complete in all respect as per the approved technical specification and direction of EIC. |
| 24 | Supply & installation of Insulator support channel 75x40x4.8mm,7.14kg/mtr,each channel length 4.3mtr,1 nos channel required=(1x7.14x4.3). Complete in all respect as per the approved technical specification and direction of EIC. |
| 25 | Supply & installation of Isolator support channel 75x40x4.8mm,7.14kg/mtr.,each channel length 4.3mtr.,2nos channel required=(2x7.14x4.3). Complete in all respect as per the approved technical specification and direction of EIC. |
| 26 | Supply & installation of Double pole belting channel 75x40x4.8mm,7.14kg/mtr,each channel length 4.3mtr,4nos channel required=(4x7.14x4.3). Complete in all respect as per the approved technical specification and direction of EIC. |
| 27 | Supply & installation of 50x50x6mm GI Bracing Angle 4.5kg/mtr,each angle length 4.927mtr,4nos angle required=(4x4.5x4.927). Complete in all respect as per the approved technical specification and direction of EIC. |
| 28 | Supply & installation of Isolator operating down pipe support channel 75x40x4.8mm, 7.14kg/mtr.,each channel length 0.8mtr.,1nos. Channel required= (1x7.14x0.8). Complete in all respect as per the approved technical specification and direction of EIC. |
| 29 | Supply & installation of Down pipe Digonal support Angle,4.5kg/mtr.,each angle length 0.388mtr.,1no angle required=(1x4.5x0.388). Complete in all respect as per the approved technical specification and direction of EIC. |
| 30 | Supply & installation of Down pipe base support Angle,4.5kg/mtr.,each angle length 0.34mtr.,1nos angle required=(1x4.5x0.34). Complete in all respect as per the approved technical specification and direction of EIC. |
| 31 | Supply & installation of Isolator support side channel 100x50x5mm,9.56kg/mtr.,each channel length 0.5mtr,2nos channel required=(2x9.56x0.5). Complete in all respect as per the approved technical specification and direction of EIC. |
| 32 | Supply & installation of Danger plate 2 nos.Complete in all respect as per the approved technical specification and direction of EIC. |
| 33 | Supply & installation of Black clamp for danger plate 25x3mm flat 0.59kg/mtr.Flat of 0.51mtr. Length 2nos.=(2x0.59x0.51). Complete in all respect as per the approved technical specification and direction of EIC. |
| 34 | Supply & installation of HT stay clamp 50x8mm,flat 3.14kg/mtr.,0.511mtr.,length 2nos. Qut. Required(1 pair). Complete in all respect as per the approved technical specification and direction of EIC. |
| 35 | Supply & installation of HT Stay set (complete). Complete in all respect as per the approved technical specification and direction of EIC. |
| 36 | Supply & installation of HT Stay insulator Type-C(2 NO.). Complete in all respect as per the approved technical specification and direction of EIC. |
| 37 | Supply & installation of 7/8 SWG Stay wire 15kg/stay. Complete in all respect as per the approved technical specification and direction of EIC. |
| 38 | Supply & installation of GI pipe earthing 40mm ,3mtr.Long. Complete in all respect as per the approved technical specification and direction of EIC. |
| 39 | Supply & installation of 50x6mm GI Flat for earthing 2.36kg/mtr.(15mtr.for LA,4mtr. For isolator body ,2.5mtr for mesh formation and 2.5mtr for rising)=24x2.36. Complete in all respect as per the approved technical specification and direction of EIC. |
| 40 | Supply & installation of GI barbed wire anticlimbing device 3kg.per support. Complete in all respect as per the approved technical specification and direction of EIC. |
| 41 | Supply & installation of Black clamp for anticlimbing device 25x3mm,flat 0.59kg/mtr.,flat of 0.510mtr. Length 8nos.=(8x0.59x0.510). Complete in all respect as per the approved technical specification and direction of EIC. |
| 42 | SITC of Lighting arrester(30kv,10ka) (Station class-2). Complete in all respect as per the approved technical specification and direction of EIC. |
| 43 | Supply & installation of 33kv 630 AMP Double break (Turn & twist center rotating) isolator without earth switch with PI(Polymer). Complete in all respect as per the approved technical specification and direction of EIC. |
| 44 | Supply & installation of 33kv pin insulator polymer. Complete in all respect as per the approved technical specification and direction of EIC. |
| 45 | Supply & installation of H W fitting(B&S) 90kn,4 Bolt. Complete in all respect as per the approved technical specification and direction of EIC. |
| 46 | Supply & installation of Disc insulator (B&S) 90kn Polymer. Complete in all respect as per the approved technical specification and direction of EIC. |
| 47 | Supply & installation of PG Clamp for 148sq.mm. AAA conductor. Complete in all respect as per the approved technical specification and direction of EIC. |
| 48 | Supply and fixing of GI Nut,Bolt & Washer of different sizes (22.15kg each DP with isolator). Complete in all respect as per the approved technical specification and direction of EIC. |
| 49 | Supply and painting of Black paint as required and direction of EIC. |
| 50 | Supply and painting of Yellow Colour paint for Background) as required and direction of EIC. |
| 51 | Part B- Cost of Civil Works. |
| 52 | Fixing of 33 KV line Complete stay set including 1) Turn Buckle Assembly 2) Stay Rod & Stay plate 3) Stay wire, 5) Stay clamp with & Nuts & Bolts,including excvation,supply of 0.5Cum cement concrete foundation 1:2:4 size (500mmx500xmmx800mm) using 20mm BHG metal with all labour and material (Excavation of earth will be done of size 500x500x1500mm).Complete in all respect as per TPCODL Drawing & Standard. |
| 53 | Concreating ratio 1:1:5:3 (500mmx500mmx2200mm)= 0.55Cu.mtr.Complete in all respect as per the direction of EIC. |
| 54 | Couping ratio 1:1:5:3 with dimension (500mmx500mmx450mm)= 0.1125Cu.mtr.Complete in all respect as per the direction of EIC. |
| 55 | Installation of Earth pit,Charcoal,Salt etc, including construction of earthing chamber size(2'x2') and RCC slab cover.Complete in all respect as per the direction of EIC. |
| 56 | Part C-COST OF MATERIALS FOR 33KV DP WITHOUT ISOLATOR - 1Nos |
| 57 | Supply & installation of WPB 160X152 (13mtr. Long,30.44KG/Mtr.) Including excavation of pole pit in all king of soil with depth upto 1/6th of pole height. Complete in all respect as per the approved technical specification and direction of EIC. |
| 58 | Supply & installation of Top Channel 100x50x6mm,9.56 KG/Mtr. Each channel length 3.25 mtr.,2nos. Channel required=(2x9.56x3.25). Complete in all respect as per the approved technical specification and direction of EIC. |
| 59 | Supply & installation of Fish plate 50x6mm,2.36kg/mtr,each 0.280mtr length,6nos. Required=(6x2.36x0.280). Complete in all respect as per the approved technical specification and direction of EIC. |
| 60 | Supply & installation of Double pole belting channel 75x40x4.8mm,7.14kg/mtr,each channel length 1.96mtr,4nos channel required=(4x7.14x1.96). Complete in all respect as per the approved technical specification and direction of EIC. |
| 61 | Supply & installation of 50x50x6mm GI Bracing Angle 4.5kg/mtr,each angle length 3.432mtr,4nos angle required=(4x4.5x3.432). Complete in all respect as per the approved technical specification and direction of EIC. |
| 62 | Supply & installation of Danger plate 2 nos.. Complete in all respect as per the approved technical specification and direction of EIC. |
| 63 | Supply & installation of Black clamp for danger plate 25x3mm flat 0.59kg/mtr.Flat of 0.51mtr. Length 2nos.=(2x0.59x0.51). Complete in all respect as per the approved technical specification and direction of EIC. |
| 64 | Supply & installation of HT stay clamp 50x8mm,flat 3.14kg/mtr.,0.511mtr.,length 2nos. Qut. Required(1 pair). Complete in all respect as per the approved technical specification and direction of EIC. |
| 65 | Supply & installation of HT Stay set(complete). Complete in all respect as per the approved technical specification and direction of EIC. |
| 66 | Supply & installation of HT Stay insulator Type-C(2 NO.). Complete in all respect as per the approved technical specification and direction of EIC. |
| 67 | Supply & installation of 7/8 SWG Stay wire 15kg/stay. Complete in all respect as per the approved technical specification and direction of EIC. |
| 68 | Supply & installation of GI pipe earthing 40mm ,3mtr.Long. Complete in all respect as per the approved technical specification and direction of EIC. |
| 69 | Supply & installation of 50x6mm GI Flat for earthing 2.36kg/mtr.(2.5mtr.for Mess formation and 2.5mtr for rising)=5x2.36. Complete in all respect as per the approved technical specification and direction of EIC. |
| 70 | Supply & installation of GI barbed wire anticlimbing device 3kg.per support. Complete in all respect as per the approved technical specification and direction of EIC. |
| 71 | Supply & installation of Black clamp for anticlimbing device 25x3mm,flat 0.59kg/mtr.,flat of 0.510mtr. Length 8nos.=(8x0.59x0.510). Complete in all respect as per the approved technical specification and direction of EIC. |
| 72 | Supply & installation of 33kv pin insulator polymer. Complete in all respect as per the approved technical specification and direction of EIC. |
| 73 | Supply & installation of H W fitting(B&S) 90kn,4 Bolt. Complete in all respect as per the approved technical specification and direction of EIC. |
| 74 | Supply & installation of Disc insulator (B&S) 90kn Polymer. Complete in all respect as per the approved technical specification and direction of EIC. |
| 75 | Supply & installation of PG Clamp for 148sq.mm. AAA conductor. Complete in all respect as per the approved technical specification and direction of EIC. |
| 76 | Supply & fixing of GI Nut,Bolt & Washer of different sizes (12.261kg each DP without isolator). Complete in all respect as per the approved technical specification and direction of EIC. |
| 77 | Supply and painting of Black paint as required and direction of EIC. |
| 78 | Supply and painting of Yellow Colour paint for Background) as required and direction of EIC. |
| 79 | Part C- Cost of Civil Works. |
| 80 | Fixing of 33 KV line Complete stay set including 1) Turn Buckle Assembly 2) Stay Rod & Stay plate 3) Stay wire, 5) Stay clamp with & Nuts & Bolts, including excvation,supply of 0.5Cum cement concrete foundation 1:2:4 size (500mmx500xmmx800mm) using 20mm BHG metal with all labour and material (Excavation of earth will be done of size 500x500x1500mm).Complete in all respect as per TPCODL Drawing & Standard. |
| 81 | Concreating ratio 1:1:5:3 (500mmx500mmx2200mm)= 0.55Cu.mtr.Complete in all respect as per the direction of EIC. |
| 82 | Couping ratio 1:1:5:3 with dimension (500mmx500mmx450mm)= 0.1125Cu.mtr.Complete in all respect as per the direction of EIC. |
| 83 | Installation of Earth pit,Charcoal,Salt etc, including construction of earthing chamber size(2'x2') and RCC slab cover.Complete in all respect as per the direction of EIC. |
| 84 | Part D- Cost of Supply Of Materials. |
| 85 | Supply of materials for 11kV, 3Core, 400sqmm Aluminium,XLPE Insulation armoured UG cable with accessories. |
| 86 | Supply of 11kV, 3Core, 400sqmm Alumnium XLPE insulation armoured UG cable as per the specification and direction of EIC. |
| 87 | Supply of Outdoor termination kits Heat Shrinkable type suitable for 11kV 3Core,400 sqmm, HT UG cable for 3Core as per the specification and direction of EIC. |
| 88 | Supply of Straight through jointing kits Heat Shrinkable type suitable for 11kv,3core,400sqmm, Aluminium UG cable for 3 core as per the specification and direction of EIC. |
| 89 | Supply of Channel 100x50x6mm @9.56KG/MTR. (GI) for cable trench (For 2 lane-500 mtr.) as per the specification and direction of EIC. |
| 90 | Part D- Cost of Erection Of Materials. |
| 91 | Laying, Commissioning, Testing of 11kV, 3core, 400sqmm, aluminium, XLPE insulation armoured UG cable by open trench method. |
| 92 | Laying,Commissioning & Testing of 11kv,3 Core ,400sqmm,Aluminium XLPE insulation armoured (extruded type) UG cable by open trench method as per direction of EIC. |
| 93 | Erection of Outdoor termination kits Heat Shrinkable type suitable for 11kv,3Core ,400sqmm, Aluminium UG cable kits for 3 core as per direction of EIC. |
| 94 | Erection of Straight through jointing kits Heat Shrinkable type suitable for 11kv,3Core,400sqmm, Aluminium UG cable kits for 3 core as per direction of EIC. |
| 95 | Part D- Cost of Civil Works. |
| 96 | Civil works with supply of all materials like cement, MS tor rod, brick, coarse & fine aggregates and labour, T&P, ete for UG Cable Trench. |
| 97 | Earth work excavation of soil (2.5 mtr width x 2.5 mtr depth) |
| 98 | Back filling with excavated soil outside and above the trench |
| 99 | Supply and erection of RCC trench (2000mtrD), 250mm thick, 2110 mm wide wide (M-30 grade) - Cast-in-SITU |
| 100 | Supply of rod, bending, cutting and binding of RCC trench (0.898 Quint/Cum) - Cast-in-SITU |
| 101 | PCC (1:3:6) below trench (width 2110 mm, thickness 100mm throughout) |
| 102 | Supply and erection of GI Pipe of dia. 150mm, Class-B (8Mtr.) as per the direction of EIC. Please Enable Macros to View BoQ information |