| 1 | Supply of Decentralized material as per UPCL Norms. |
| 2 | Supply of MS NUT & BOLT OFF SIZE |
| 3 | Supply of X ARM CLAMP FOR PCC POLE WITH N/B |
| 4 | Supply of X ARM CLAMP FOR ST POLE SP-55 WITH N/B |
| 5 | Supply of F Clamp as per UPCL Specification. |
| 6 | Supply of LT CLAMP FOR PCC POLE WITH N&B |
| 7 | Supply of MS Stay Clamp for Sp-33 Nut & Bolts ( size 65x16mm) for suspension clamps assemble without cracks & burrs Painted by primers. |
| 8 | Supply of LT Clamp with N&B ST Pole SP-33 |
| 9 | Supply of Suspension Clamps I Hook with nut & bolts as per drawing and UPCL Specification. |
| 10 | Supply of Dead End Clamp I Hook with nut & bolts as per drawing and UPCL Specification. |
| 11 | Supply of SHACKLE INSULATOR 100X115 mm WITH N&B |
| 12 | Supply of Shear head type Insulated piercing connector body molded from high quality mechanical climate and UV resistant glass reinforced polyamide, hot dipped galvanized bolts & contact teeth ABC size 95sq.mm to25 sq.mm jumpering for Line to line DB taping ( Tyco/ RPG/3M. make) as per UPCL Specification. |
| 13 | Supply L.T. bare Neutral Connector PG clamp made of Al 95x25 sq.mm. double bolt for line to line jumpering as per UPCL specifciation. |
| 14 | Supply of SMC three phase L.T.Distribution Box with inbuilt pannel lock, AI bus bar RYB 25x6 mm AI bus bar Nos 40X6mm For connection LT Consumer (sintex make or other ISI mark reputeted company with pannel lock with key as per drawing attached |
| 15 | Supply of AL Crimping Type Lugs 25 Sqmm as per specification of UPCl |
| 16 | Supply of AL Crimping Type Lugs 70Sqmm as per specification of UPCl |
| 17 | Supply LT bare neutral Connector PG clamp made of AL 25x50sqmm double bolt for line to line jumpering as per UPCL Specification |
| 18 | Supply of MS Half Clamp for LT Distribution Box-PCC Pole as per UPCL Specification |
| 19 | Following work as per UPCL norms & site requirement. |
| 20 | Eraction of M.S Earthing rod 20-2500 mm for earthing of supports as per RESPO drawing no RES-12 including driving earth rod 2.5mtr Deep Below ground level connected to support with G.I earthing with Nut & bolts work complete. |
| 21 | Fabrication of Steel after cutting in required sizes with drilling of holes upto good finish for top channel, bracing and special type bracket etc. as per RESSPO schedule and local approved drawing. |
| 22 | Excavation for stay Pit of size 0.6x0.6x1.2mtr in all type of soil including proper dressing of sides and ramming of bottom including getting out he exacavated soil and disposal of surplus excavated soil. |
| 23 | Charges of Erection of LT Stay set 16x1800mm. pit size 0.6x0.9x1.2 Mtr. as per specifications including 7/16SWG stay wire, binding, nozzling of stay with bcking filling of pit with CC 1:4:8 in bottom to pit in size 0.60 complete work stay set will be provided by UPCL.as per RESPO specification & direction of Engineer in charge |
| 24 | Grouting of Stay set in size 0.6x0.6x0.3 in CC ratio 1:48 ( 1 cement : 4 graded stone 20mm nominal size 8 coarse sand) block including cost of cement,sand and stone ballast |
| 25 | Excavation for pole pit of size 0.9X0.6X1/6 of full length of pole for erection of pole in all type of soil including proper dressing of sides and ramming of bottom including getting out the excavated soil and disposal of surplus excavated soil as directed complete work. |
| 26 | Charges of Erection of P.C.C. Pole 8.5 Mtr. Long ( 180 kg. W/L )for reducing span of LT, ABC line including digging of pits 0.6x0.9x2.15 Mtr.& with fixing of all accessories & back filling with soil & boulder earthing complete work as per RESPO specification & as per direction of Engineer in charge. |
| 27 | Erection & Grouting of STP SP-33 Single Pole including digging of pit size 0.6X0.6X1.8 M , grouting, stone pad and making kiciking block in E&B ,fixing of all accessories upto energisation.. |
| 28 | Erection & Grouting of STP SP-55 Single Pole including digging of pit size 0.6X0.6X1.8 M , grouting, stone pad and making kiciking block in E&B ,fixing of all accessories upto energisation.. |
| 29 | Erection & Grouting of STP SP-33 double Pole including digging of pit size 0.6X0.6X1.8 M , grouting, stone pad and making kiciking block in E&B ,fixing of all accessories upto energisation.. |
| 30 | Erection & Grouting of STP SP-55 double Pole including digging of pit size 0.6X0.6X1.8 M , grouting, stone pad and making kiciking block in E&B ,fixing of all accessories upto energisation.. |
| 31 | Grouting of Pole including digging of pit size 0.6X0.6X1.8 M , grouting, stone pad and making kiciking block in E&B ,fixing of all accessories upto energisation. |
| 32 | Muffing of poles size 0.45cmX0.60cm radious with CC 1:3:6 (1cement:3coarse sand:6 graded stone 10mm nominal size) block size 45cm height from ground level including cost of cement, stoneand sand etc. |
| 33 | Painting of poles STP SP 33 with angle and channel and all steel part by one coat of Red Oxide Primer and two coats of Aluminum Paint and two strip of fluorescent alternate Red and White paint 30 Cm wide upto 1.5 Mtrs. from ground level. |
| 34 | laying, Sagging of 2P 3W LT Line of ACSR Weasel conductor on existing pole with proper fitting of & hosting of with proper sagging with earth wire included T&P 1 Phase 2 Wire |
| 35 | T-Off Connection Complete 11 KV Line as per Direction of Engineer Incharge |
| 36 | Cartage of SP33 Pole 8.5 mtr long from store center to nearest road side with loading unloading at both points. Loading unloading plus carriage per pole 21-50km |
| 37 | Cartage of SP33 Pole 8.5 mtr long from store center to nearest road side with loading unloading at both points. Loading unloading plus carriage per pole 21-50km |
| 38 | Cartage of SP-55 from store centre to nearest road site with loading, unloading at both points. (Loading, unloading plus carriage per pole) (21 to 50 km). |
| 39 | Cartage of Petty Material by vehicle from store centre to nearest road site including loading and unloading at both ends. (21 to 50 km). |
| 40 | Charges of Head Load Cartage (PCC Pole 8.5 Mtr Long) from Road site To work Site as per RESP Specification of Engineer incharge distance 01-03 KM |
| 41 | Head load Cartage STP SP-33 of the following poles from road side to construction site (rates are per Pole / Km. including loading/unloading at both points) (0 to 1 km). |
| 42 | Charges of Head Load Cartage STP SP-55 Pole from Road site To work Site as per RESP Specification of Engineer incharge distance 01-03 KM |
| 43 | Alignment of Tilted LT pole at site before stringing AB cable/conductor as per direction of Engineer Incharge |
| 44 | Resaging of Loose 11 KV Line |
| 45 | Charges of Installation & Fixing of SMC three phase /Single Phase L.T.Distribution Box with inbuilt pannel lock, AI bus bar RYB 25x6 mm AI bus bar size including all complete work as per drawing, upcl specification and direction of Engineer-In-Charge. |
| 46 | Painting of poles STP SP 55 with angle and channel and all steel part by one coat of Red Oxide Primer and two coats of Aluminum Paint and two strip of fluorescent alternate Red and White paint 30 Cm wide upto 1.5 Mtrs. from ground level. |
| 47 | Looping & Chooping of Tree branches |
| 48 | Supply of Fixing of danger plate Please Enable Macros to View BoQ information |