| 1 | Transporting LT ABC by hired vehicle to a distance up to 5 km and carring up to 2 drum including loading and un loading using crane |
| 2 | Stringing of 1.1 kV Aerial bunched cable of size 3 x 70+ 1 x 16+1x 50 sqmm with bare/insulated Messenger through existing poles |
| 3 | Dismantling one damaged LT PSC/RCC pole after disconnecting stays, strut etc. attached thereon and stacking the same. |
| 4 | Erection of suspension clamp for LT ABC of any size |
| 5 | Erection of Anchor clamp / dead end clamp for LT ABC of any size |
| 6 | Installing One No. Insulation piercing connector of size Main :16 to 95 ,Tap:1.5 to 16 Sq.mm |
| 7 | Installation of Insulation piercing connector for main to service line main :16-95 sqmm, Tap 16-95 sqmm |
| 8 | Providing End Caps |
| 9 | Providing one Earth using GI earth pipe of size 38.1mm dia, 2.5m length including digging separate pit (0.45x0.45x2.5m) at a minimum distance of 1.5m away from the pole/structure and maintaining standard distance between different earth pipes in ordinary soil & backfilling. |
| 10 | Fitting one No. Section fuse on LT line with dropping cables, crimping sockets, connecting with bolt & nut etc. |
| 11 | Providing one Coil Earth using No.8 GI-earth wire (50mm dia, 115 turns) including digging separate pit (0.45x0.45x1.5m) at standard distance away from the pole/structure in ordinary soil & backfilling. |
| 12 | Dismantling (without damage) one km LT single phase 2 wire OH line conductor by dismantling cross arms, insulators and stacking the conductors in rolls properly. |
| 13 | Disconnecting and lowering down the single phase WP service connection with guy wire from the OH line and reconnecting the same after completing the line work. |
| 14 | Transporting poles by hired vehicle to a distance upto 5km and carrying upto 4 numbers of poles excluding loading& unloading charges. |
| 15 | Providing Stay for LT poles including digging & back filling pit in ordinary soil. |
| 16 | Renewal of existing damaged/broken old LT stay in existing stay rod. |
| 17 | Erecting one LT PSC Pole in position including digging & back filling pit in ordinary soil. |
| 18 | Labour charges for loading LT PSC pole from the stacking place and unloading the same at work site (transportation by any vehicle). |
| 19 | Renewal of existing damaged/old LT PSC/RCC (single phase line) pole with new PSC pole in place including excavation of pole pit, erection of new pole, backfilling pit and refitting of all items except street light fitting etc. and conveyance of all materials except pole. |
| 20 | Insertion of one LT PSC pole in existing three phase OH line including digging & back filling pit in ordinary soil, fitting cross arm, insulator, binding etc. excluding transportation of poles. Please Enable Macros to View BoQ information |