| 1 | Earthwork in excavation, loading, unloading and carriage by mechanical means of all kinds of soil including ordinary soil, hard soil , stony earth, gravel and moorum etc interspread with boulders up to1/2 cum size for base stripping including dressing and leveling the bed to design section and disposal of unutilized excavated soil away from work site in the specified spoil yard with all leads, lifts and delifts, including dewatering if any shoring, shuttering and propping of bullah piles trimming of slopes and bed with all cost of all machineries and all other taxes excluding GST and cess etc complete with all T&P and supervision charges etc as per the approved drawing, design and specification and direction of the Engineer in charge. |
| 2 | Watering and compacting the earth work under OMC condition by sheep foot roller and dozer in layers not exceeding 22.5 cm in depth to 95 % proctor density including cost of quality control tests, mobilisation & demobilisation, supplying, operation, maintenance of all machineries, equipments, materials and labours, hire and running charges of materials excluding GST inclusive supervision charges, cess required for the work etc. complele as per approved design, drawing and specification and the direction of the Engineer in charge.(Measurement is to be taken on the finished level section & payment will be made after compaction ). |
| 3 | Filling foundation and plinth with sand including watering and ramming with all labour, T&P etc complete to the required level including cost, carriage, royalty, DMF,EMF,additional charges & cess, taxes of all materials excluding GST, etc complete as per the approved drawing, design, specification and direction of the Engineer-in-Charge. |
| 4 | Cement concrete (1:3:6) with crusher broken hard granite 40mm down graded aggregates of approved quality free from weathered skin surface mixing by concrete mixer and placing in position including hoisting and laying with all leads, lifts and delifts, dewatering, mixing and vibrating by mechanical means, loading & unloading, curing with cost, conveyance, all labours, T&P, Royalty, DMF,EMF,additional charges, cess, but excluding GST as per approved drawing, design and specification and direction of the Engineer in charge. |
| 5 | Providing rigid smooth centering shuttering for RCC works including flase works and dismantling them after casting and removal of forms and making good to the surface where necessary etc. complete with all labour, materials, supervision charges, cost, conveyance and T&P, cess & taxes of all materials excluding GST, etc. complete as per approved design, drawing, specification and directed by the Engineer-in-charge. |
| 6 | Cement concrete (1:2:4) with crusher broken hard granite chips 12mm aggregates of approved quality free from weathered skin surface mixing by concrete mixer and placing in position including hoisting and laying with all leads, lifts and delifts, dewatering, mixing and vibrating by mechanical means, loading & unloading, curing with cost, conveyance, all labours, T&P, Royalty, DMF,EMF,additional charges, cess, but excluding GST as per approved drawing, design and specification and direction of the Engineer in charge. |
| 7 | Providing , laying and fixing in position of RCC hume pipe of 2.5m long & 1200 mm dia spun pipes NP3 class conforming to ISI standard with collar joints filled in cement mortar (1:3) with necessary twisted and coal tarred hempyarn including caulking and finishing the same, as per approved drawing including all cost, conveyance , cess and all other taxes of all materials required for the work including cost & conveyance of spun pipe including all labour charges for loading, unloading, curing and laying in position, T&P with all leads, lifts and delifts of all materials dewatering if any including making the coffer dam if required excluding GST as per the specification and direction of Engineer-in-Charge. |
| 8 | Supplying, fitting including straightening, cutting, bending, shirting, binding the M.S. or HYSD reinforcement bars for R.C.C. work and tying the grills and placing in position including cost, conveyance of M.S. or HYSD reinforcement bars and binding wires of 18 to 20 gauges, loading, unloading incuding cost, carriage, labour, cess and taxes and all materials excluding GST etc complete as per approved design, drawing, specification and the direction of the Engineer-in-charge. |
| 9 | Rough stone dry packing in aprons and revetments to designed thickness and slope using 15cm to 30cm size hard broken granite stone of approved quality from approved quarry free from weathered skin and any other deleterious materials including filling the interstices with small stones, spalls etc and wedging with hammer and placing the surface to proper line and level, fixing key stones including dewatering, if any with all cost, labour, conveyance and all leads and lifts, royalties, DMF,EMF,additional charges, cess, taxes of all materials, T&P but excluding GST etc complete in all respect as per approved drawing, design, specification and direction of the Engineer- in- charge. |
| 10 | Providing & making Gabion structure with Mechanically Woven Double Twisted Hexagonal Shaped Wire mesh Gabion Boxes as per IS16014:2012, MORT&HClause2500, of required size, Mesh Type10X12 (D=100mm with tolerance of +2%) Zinc coated, PVC, Mesh wire diameter 2.7mm, mechanically edged /Selvedge 3.40mm with partitionsate very 1minterval and shall have minimum 10numbers of openings per meter of mesh perpendicular to twist, tying with lacing wire of diameter 2.2mm, supplied @3% by weight of Gabion boxes, filled with boulders with least dimension of 200mm, as per drawing, with all leads, lifts and delifts, cost, conveyance including cost, maintenance of haul roads, re-handling charges involving royality and taxes of all metierials excluding GST etc. complete as per the direction of the Engineer-in Charge. |
| 11 | Fine dressing of earth work in slopes including filling of rain cuts and slips with selected earth duly compacted and trimmed to the required profile and turfing the surface with best compacted dub grass sods 8cm to 10cm thick including collection & supplying the same and conveyance charges, , Cess and taxes of all materials excluding GST with all leads, lifts and delfts by mechanical means including laying and trimming to form a level and compact surface in line with the slopes and grade of the canal section or earth embankment section of river including watering until the green growth of grass including mobilization and demobilization etc complete as per design, drawing and specification and direction of the Engineer-in-Charge. (Measurement will be taken after full survival of turf). |
| 12 | Providing weep holes in R.C.C abutment, flanks, out walls and flanks walls etc with 75 mm dia AC pipe extending through the full width of the structure with slope of 1 V:20 H towards drawing face with non- return flap valves at wall face with all cost, conveyance, labour T&P, royality, EMF &DMF and taxes of all materials excluding GST Complete with all T&P and supervision charges etc as per the approved drawing, design & specification & direction of the Engineer-in-charge. Please Enable Macros to View BoQ information |