Tender For Construction Of Canal From Km 2.650 To 2.800 & 3.150 To 3.300 And Balance Pucca Work Of Achharaud Minor. Tender Cost-19.69 Lacs (Excluding Gst) (Lot-04), Hamirpur-Uttar Pradesh
TDR : 55239022
Tender Notice
BOQ
13 Days Left
Hamirpur
Uttar Pradesh
Tender For Construction Of Canal From Km 2.650 To 2.800 & 3.150 To 3.300 And Balance Pucca Work Of Achharaud Minor. Tender Cost-19.69 Lacs (Excluding Gst) (Lot-04)
Name of Work:- Construction of Canal from km 2.650 to 2.800 & 3.150 to 3.300 and Balance pucca work of Achharaud minor. TENDER COST-19.69 Lacs (Excluding GST) (Lot-04)
Sl. No.
Item Description
1
The quantities given here under are tentative. They can vary on either side upto any extant,the contractor shall have no claim on account of changes and shall be paid of the quantities as physically met at site reach of work for complete work.
2
E/W excavation in foundation M.K.R. soil including initial lead and lift as per proper completion of work.
3
Earth work in filling in embankment including mechanical compaction dressing and watering with all leads and lifts and T&P etc. for proper compaction of work including all tax like income tax labour cess etc. But excluding G.S.T.
4
Excavation in all type of strata excluding hard granite rock including compaction, dressing,watering and disposal of excavated material as diredcted by engineer-In-Charge including all leads, lifts and T&P etc for proper completion of work including all Tax like income tax labour cess etc. But excluding G.S.T.
5
Supplying & Laying coarse sand in foundation with all cost of material, labour, T&P etc required for completion of work.
6
Laying C.C M10 A40 in foundation with all cost of sand cement and stone, balllast T&P etc reguard for completion of work
7
Supplying & fixing hume pipe 600 mm dia pipe including cost of material, labour, T&P etc with all leads & lifts for proper completion of Job.
8
R.C.R. Stone masonry 1:4 cm with all cost of labour cement, sand, stone T&P etc required for completion of work.
9
Joint fixing & laying C.C. 1:2:4 in top of stone masonry with all cost of sand, cement & stone ballast T&P etc required for completion of work.
10
Cement pointing 1:2 on stone masonry all cost of labour material T&P etc required for completion of work.
11
Centering & Shuttering for R.C.C. work with all cost of labour material T&P etc required for completion of work.
12
Dry stone pitching with all cost of labour material T&P etc. required for completion of work. Please Enable Macros to View BoQ information
We takes all possible care for accurate & authentic tender information, however Users
are requested to refer Original source of Tender Notice / Tender Document published by
Tender Issuing Agency before taking any call regarding this tender.