| 1 | S/F one set 25 HP C/F pump set, Repairing of 25 HP C/F Motor Pump Set,S/F Motor control panel, ,S/F of 7.5HP VT pump set ,Repairing of 7.5 VT Pump Set ,S/F of 3 T Chain pully, Power wiring other allied works at Kharka Clear water supply scheme |
| 2 | Mechanical & Electrical Work at WTP |
| 3 | Supplying all labour tools and tackles for complete dismantling and opening of 25 HP 3 phase inducting motors Make Kirloskar, cutting burnt wire and rewinding supper enameled copper wire, insulating paper, tape bamboo stick etc. Heating Varnishing and testing on full load at site including transportation charge after deducting the cost of scrap materials (burnt wire Wt. 18 Kg approx.) for both set |
| 4 | Cost for supplying labour, tools and tackles for repairing of C/F pump of 25HP pump sets with opening and refitting after repairing with S/F of new rotating unit complete having C.I impeller, shaft, neck ring, bearing, bearing housing etc. all complete with transportation charge. |
| 5 | Supply, installation, testing and commissioning of horizontal casing centrifugal pump sets with aliedequipment.Horizontal Split Casing Centrifugal Pump [make: Kirloskar/Jyoti/ Worthington/ Mather & Platt] , capable of discharging required flow against required Head-as below. mounted on common base plate and coupled with TEFC, squirrel cage induction motor, rating of motor 15% more BHP than that of pump, operating on 1500 rpm, 415V, 50Hz [make: Kirloskar/ABB/ Jyoti/Crompton Greaves/BHEL] pressure gauge, required size of Motorised sluice valve and non-return valve, standard fittings etc. including construction of MS Suction and delivery header, jointing it with Suction and Delivery line by providing required MS/CI pipes, flanges, reducer and specials, nuts bolts, packings etc. all complete as per the requirement, standards and instruction of E/I.(Contrator will again have to check the design of motor,pump & get it approved by the Deptt.)Discharge 34 m^3/hr Head 84M ,25HP |
| 6 | S/F of coupling unit suitable for 25HP pump set at site |
| 7 | Motor control panel having FASD Starter-2 nos supplying and fitting suitable for 25HP C/F Two Pump sets. |
| 8 | S/F 200 Amps Busbar Make-L&T /Hevells or reputed brand. |
| 9 | Cost for S/F of change over switch 200 amp of L&T, Havell’s make ISI mark .. |
| 10 | Power wiring with required 35 Sq mm 3core 1.1KV, Grade unarmoured copper cables XLPE/PVC insulated unarmoured cable from Power distribution Panel (MCP) to motors, including laying on wall or on floor as where required jointing and making proper terminations, etc. all complete. |
| 11 | Mechanical & Electrical Work at Intake well . |
| 12 | Supply, installation, testing and commissioning of vertical turbine pump sets with allied equipment as Under Vertical Turbine Pump [ Make : Kirloskar/ joyti/Worthington/ Mather & Platt]as per IS. 1710/1972, SIS of VT pumpset capable of discharging Discharging – 36M^3/HR against the total head of 20 M coupled with squirrel cage induction motor, having 20% more BHP than that of pump, opereting on 1500 rpm, 415V, 50Hz, [Make; Kirloskar/ BHEL/ ABB/ Joyti/ Crompton greeves] all complete suitable discharge head, base plate & accessories such as suitable MS Column pipe flange type 60 ft spider bearing , line shaft rubber cut less bush spider with stainer ,motorised sluice valve ratio PN - 1.6 NR valve , pressure gauge including cost of construction PCC foundation with cement sand , stone chips foundation bolt nut, spring washer , plaster punning of foundation and making delivery pipe with piping works required for the job and etc all complete job , testing of pump set on full load at site.(cost of Pump,Motor etc) (Contractor will again have to check the Design of pump & motor and get it approved by the Deppt.)Discharging – 36M^3/HR and Head – 20M ,7.5HP |
| 13 | Cost of dismantling the motor and taking out bowl assembly from the intake well by supplying all labour, tools and tackles etc at site. |
| 14 | Cost towards dismantling, checking and repairing and rewinding of 7.5 H.P VT Jyoti Limited squirrel cage induction motor with all labour, tools & tackles including fitting new taper roller thrust bearing-7310 SKF make – 1 no. and rewinding material such as supper enameled copper wire of proper gauge and weight, heating, varnishing and refitting etc at site. (Weight 4.4 kg approx)including loading unloading and transportation charge. |
| 15 | Cost for complete opening dismantling and refitting after repairing of 7.5 HP VT ball assembly with S/F top and bottom ,Including changing of ,Coupling ,Mounting Coupling, Suitable Bearing, wearing ring – 5 Nos. G.M. impeller as per sample – 5 Nos. including remetalling turning & polishing and making same size of ball assembly housing etc. all complete with all labour and materials as required on site. |
| 16 | Cost for S/F of heavy duty M.S. column pipe size 3” dia x 10’ long with one side long socketed. |
| 17 | Supplying and fitting Foot valve 3” dia and its washer. |
| 18 | Power Wiring 100 Sq mm 3.5 core 1.1 KV grade armoured alumminium cables XLPE/PVC inculated armoured cable from WTP Transformar to MCP at Raw water pump house. laying , jointing and making proper terminations ,etc. all complete. |
| 19 | COST of 3T triple type chain pully block suitable as below with 6m lift complete with laoad chain and hand chain suitable for avove lift, tested 50% over load as per IS 3832 carry ISI etc. all complete job as per the site requirement.. |
| 20 | COST of 3T triple type chain pully block suitable as below with 6m lift complete with laoad chain and hand chain suitable for avove lift, tested 50% over load as per IS 3832 carry ISI etc. all complete job as per the site requirement. |
| 21 | Repairing of 25 HP C/F and 7.5 VT Pump Set and other allied works at Kharka Clear water supply scheme |
| 22 | Mechanical & Electrical Work at WTP |
| 23 | Supplying all labour tools and tackles for complete dismantling and opening of 25 HP 3 phase inducting motors Make Kirloskar, cutting burnt wire and rewinding supper enameled copper wire, insulating paper, tape bamboo stick etc. Heating Varnishing and testing on full load at site including transportation charge after deducting the cost of scrap materials (burnt wire Wt. 18 Kg approx.) for both set |
| 24 | Cost for supplying labour, tools and tackles for repairing of C/F pump of 25HP pump sets with opening and refitting after repairing with S/F of new rotating unit complete having C.I impeller, shaft, neck ring, bearing, bearing housing etc. all complete with transportation charge. |
| 25 | S/F of coupling unit suitable for 25HP pump set at site |
| 26 | S/F 200 Amps Busbar Make-L&T /Hevells or reputed brand. |
| 27 | Cost for S/F of change over switch 200 amp of L&T, Havell’s make ISI mark . |
| 28 | Mechanical & Electrical Work at Intake well |
| 29 | Cost of dismantling the motor and taking out bowl assembly from the intake well by supplying all labour, tools and tackles etc at site. |
| 30 | Cost towards dismantling, checking and repairing and rewinding of 7.5 H.P VT Jyoti Limited squirrel cage induction motor with all labour, tools & tackles including fitting new taper roller thrust bearing-7310 SKF make – 1 no. and rewinding material such as supper enameled copper wire of proper gauge and weight, heating, varnishing and refitting etc at site. (Weight 4.4 kg approx)including loading unloading and transportation charge. |
| 31 | Cost for complete opening dismantling and refitting after repairing of 7.5 HP VT ball assembly with S/F top and bottom ,Including changing of ,Coupling ,Mounting Coupling, Suitable Bearing, wearing ring – 5 Nos. G.M. impeller as per sample – 5 Nos. including remetalling turning & polishing and making same size of ball assembly housing etc. all complete with all labour and materials as required on site. |
| 32 | Cost for S/F of heavy duty M.S. column pipe size 3” dia x 10’ long with one side long socketed. |
| 33 | Supplying and fitting Foot valve 3” dia and its washer. Please Enable Macros to View BoQ information |