| 1 | Repairing of 150 HP, 550V, DOL Starter at Madhaipur Colliery . (Inclusive of EPF/CMPF) |
| 2 | Repairing of Isolator with pro Moving contact |
| 3 | Bush Insulator terminal with brass stud |
| 4 | Amp Metre with CT ratio 200/5 A flush type |
| 5 | Thermal over load L&T make complete Set |
| 6 | CT 200/5 A |
| 7 | ML12 Magnatic Contractor Unit 550V |
| 8 | 70 SQMM Copper Flexible Cable with Socket |
| 9 | Push Switch |
| 10 | ELR Relay with Matching CBCT |
| 11 | Bakelite contactor 12 Way |
| 12 | BCH make Timer range 0-60 Sec,550V |
| 13 | Supply of Indication Lamp |
| 14 | 2.5 SQMM PVC Flexible Cu wire for wiring |
| 15 | Single Phase Preventer |
| 16 | Body Bolt,Nut and Painting |
| 17 | Labour Charge |
| 18 | Profit @ 10% |
| 19 | Repairing of 150 HP, 550V, DOL Starter at Madhaipur Colliery. (Inclusive of EPF/CMPF) |
| 20 | Dismantaling of Isolator |
| 21 | Main Terminal Insulator |
| 22 | Isolator |
| 23 | Overload Assembly |
| 24 | Earth Leakge relay |
| 25 | Timer |
| 26 | CBT with Board |
| 27 | Current Transformer |
| 28 | Main Connection Cable |
| 29 | Heavy Duty Copper Socket |
| 30 | Amps Meter |
| 31 | Push Switch |
| 32 | Lamp with Holder |
| 33 | Fuse Base Carrier |
| 34 | Complete Wiring |
| 35 | Insulation and Material |
| 36 | Cleaning and Painting |
| 37 | Contractor Unit |
| 38 | Profit @ 10% |
| 39 | Labour Charge |
| 40 | Transporting |
| 41 | Rewinding and Repairing of 250 KVA, 11KV/550V Lighting Transformer at Madhaipur Colliery. (Inclusive of EPF/CMPF) |
| 42 | Dismantling of Core & Winding from Transformer |
| 43 | Cost of new electrolytr grade DPC Copper |
| 44 | Cleanning of Copper Strips of Secondary Coil |
| 45 | Cost of HT grade Insulating materials |
| 46 | Cost of Wooden forma for formation |
| 47 | Supply & fixing of new Tap-Changer Swicth |
| 48 | Cost of Terminal bushing with Insulator |
| 49 | Supply & Fitting of new gasket,missing |
| 50 | De-Carbonizing, cleaning & painting etc |
| 51 | De-hydration & filtration of Transformer |
| 52 | Labour Charges for complete repairing |
| 53 | Cost of Testing the above Transformer |
| 54 | Cost of new Transformer tank |
| 55 | O.H. & Profit @ 10% |
| 56 | Transpotartion Charge |
| 57 | Less Scarp Value |
| 58 | Complete Rewinding and Repairing of 250KVA,11KV/440V Lighting Transformer of Manderboni Colliery. (Inclusive of EPF/CMPF) |
| 59 | Dismantling of Core & Winding from Transformer |
| 60 | Cost of new electrolytr grade DPC Copper |
| 61 | Cleanning of Copper Strips of Secondary Coil |
| 62 | Cost of HT grade Insulating materials |
| 63 | Cost of Wooden forma for formation |
| 64 | Supply & fixing of new Tap-Changer Swicth |
| 65 | Cost of Terminal bushing with Insulator |
| 66 | Supply & Fitting of new gasket,missing |
| 67 | De-Carbonizing, cleaning & painting etc |
| 68 | De-hydration & filtration of Transformer |
| 69 | Labour Charges for complete repairing |
| 70 | Cost of Testing the above Transformer |
| 71 | Cost of new Transformer tank |
| 72 | O.H. & Profit @ 10% |
| 73 | Transpotartion Charge |
| 74 | Less Scarp Value |
| 75 | Rewinding & Repairing of 50KVA,3.3KV/440V Lighting Transformer at Sonabandhi village of Manderboni Colliery. (Inclusive of EPF/CMPF) |
| 76 | Cost of copper wire with DPC |
| 77 | Cost of Insulating Materials (Primary & Secondary) |
| 78 | Cost of Cork sheet. 4mm |
| 79 | Cost of Connection stud with insulator |
| 80 | Cost of wooden forma for making coils |
| 81 | Cost of De-carbonizing core & tank clean |
| 82 | Cost of thinner and varnish |
| 83 | Cost of cooling tubes welding & grinding |
| 84 | Re-winding charge |
| 85 | Less Scrape Value |
| 86 | Profit @ 10% |
| 87 | Repairing of 150 HP, 550V, 1440 RPM, Electrical Induction Motor at Manderboni Colliery. (Inclusive of EPF/CMPF) |
| 88 | Dismantling of motor and withdrawing of coils from the motor slot & cleaning decarbonizing of stator & rotor |
| 89 | Supply of class F varnish & thinner |
| 90 | Flexible glass cable for terminal connection & jumpering |
| 91 | Assembling of motor |
| 92 | Drying/Heat treatment of motor at required |
| 93 | Fabrication Fan cover with material |
| 94 | Rotor Bar brazing & Grinding using Rupotom Rod |
| 95 | Both side Rotor Shaft fixing & Machning as per |
| 96 | Fabrication Fan with material |
| 97 | Testing of Motor |
| 98 | Profit @ 10% |
| 99 | Total impact of GST for the purpose of CTC Please Enable Macros to View BoQ information |