| 1 | Providing one Coil Earth using No8 GI earth wire (50 mm dia,115 turns) including digging separate pit (0.45x0.45x1.5m) at standard distance away from the pole/structure in ordinary soil & backfilling |
| 2 | Providing one Earth using GI earth pipe of size 38.1mm dia2.5m length including digging separate pit (0.45 x 0.45 x 2.5 m) at a standard distance of 1.5 m away from the pole/structure in ordinary soil and backfilling the pit with 15 cm alternate layer of charcoal,salt and sand upto 90 cm from the bottom including the cost of 20 kg salt,25 kg charcoal |
| 3 | Providing one Driven Earth using GI earth pipe of size 38.1mm dia2.5m length including digging separate pit at a minimum distance of 1.5 m away from the pole/structure and maintaining standard distance between different earth pipes in loose soil |
| 4 | Providing one Earth using GI earth pipe of size 38.1mm dia2.5m length including digging separate pit (0.45 x 0.45 x 2.5 m) at a minimum distance of 1.5 m away from the pole/structure and maintaining standard distance between different earth pipes in ordinary soil and backfilling |
| 5 | Fitting one Additional 2.4m/3m Channel cross arm (100x50x6mm), in existing 11KV DP incl. conveyance of materials. |
| 6 | Transporting poles by hired vehicle to a distance up to 5km and carrying up to 4 poles excluding loading & unloading |
| 7 | Transporting LT ABC by hired vehicle to a distance up to 5km and carrying up to 2 drum including loading & unloading using crane |
| 8 | Fitting and erecting one HT DP using PSC pole in position incl. fitting 2 channel cross arms, digging & back filling pit, drawing sufficient length of GI earthing leads through all cross arms to ground for earthing (excluding provision of earthing) |
| 9 | Labour charges for loading HT A type pole from the stacking place and unloading the same at work site (transport by vehicle). |
| 10 | Fitting and erecting one HT A type pole in position incl. fitting cross arm,digging & back filling pit in ordinary soil(as per standards) , drawing sufficient length of GI earthing leads from F clamp through V cross arm to ground for earthing (excluding provision of earthing) |
| 11 | Fitting and erecting one HT PSC type pole in position incl. fitting cross arm, digging & back filling pit in ordinary soil(as per standards) , drawing sufficient length of GI earthing leads from F clamp through V cross arm to ground for earthing (excluding provision of earthing),drawing earth leads |
| 12 | Providing concrete muffing (0.45x0.45x1.5m) ( 0.5m above GL and 1m below GL).Excavation 0.45x0.45x1m concrete (1:3:6 20mm) 0.45x0.45x1.5m.Plastering (1:3) 12mm 0.45mx0.45mx 5 sides |
| 13 | Fitting and erecting one HT Double pole structure using A type pole in position incl. fitting 2 No channel cross arm,digging & back filling pit in ordinary soil, drawing sufficient length of GI earthing leads through all cross arms to the ground for earthing (excluding provision of earthing |
| 14 | Labour charges for loading HT PSC pole from the stacking place and unloading the same at work site (transport by vehicle). |
| 15 | Fitting and providing one HT stay for 11KV pole incl. digging and back filling pit in ordinary soil |
| 16 | Fitting one set AB switch on existing DP giving connection and drawing sufficient length of GI earthing leads to the grounf for earthing excluding provision for earthing |
| 17 | Drilling hole of various sizes on existing Channel/Cross arm |
| 18 | Additional rate for excavation of Pit for A type pole in Laterite |
| 19 | Fitting and providing one HT Fly stay for 11KV Pole using HT PSC pole incl. digging and back filling pit in ordinary soil drawing sufficient length of GI earth leads to the ground for earthing (excluding provision for earthing) |
| 20 | Fitting and providing one strut using HT PSC pole incl. digging and back filling pit in ordinary soil |
| 21 | Disconnecting and lowering down the Single phase WP service connection with guy wire from the OH line incl. reconnecting the same after completing the line work |
| 22 | Disconnecting and lowering down the three phase WP service connection with guy wire from the OH line incl. reconnecting the same after completing the line work |
| 23 | Additional rate refitting/redoing shackle Set including reshackling one span while renewing any type of LT pole |
| 24 | Additional rate for providing one disc set,PG clamp etc complete on any type of HT pole for making cut point |
| 25 | Dismantling one damaged 11 kV PSC/RCC pole after disconnecting stays, strut, etc. attached thereon and stacking the same |
| 26 | Dismantling ( without damage) one 11 kV PSC/RCC pole after disconnecting stays, strut, etc. attached thereon and stacking the same |
| 27 | Dismantling one ordinary street light /CFL/LED fitting from the existing pole and refitting the same on newly erected pole including disconnecting and reconnecting wires |
| 28 | Dismantling ( without damage) one LT PSC/RCC pole after disconnecting stays, strut, etc. and stacking the same |
| 29 | Dismantling one damaged LT PSC/RCC pole after disconnecting stays,strut etc and stacking the same |
| 30 | Cutting trees having girth beyond 30cm but upto and including 60cm (felling treesincluding cutting of trunks and branches) and removing the root completely and stacking etc. 1 No. |
| 31 | Dismantling (without damage) one Channel cross arm from existing DP structure and bringing back to section store. |
| 32 | Fitting one no additional section Fuse unit and giving connection from Transformer to fuse and Distribution to LT OH line |
| 33 | Excavation of cable trench of appropriate size (normally 1.2 m deep and 0.35m/0.5 m wide for single/double run) in all classes of soil including breaking clods,watering,ramming and sectioning of soil bank etc and backfilling the soil after cable laying and consolidating the soil in layers of 75 cm (excluding laying of cable) |
| 34 | Additional rate for excavation of cable trench of appropriate size (normally 1.2m deep and 0.35m /0.5m wide for single/double run) in exceptionally hard conditions (like in ordinary rock).* (As per the PWD Standard Databook ,'ordinary rock' is defined as anymaterial which can be quarried or split with crowbars or wedges)) |
| 35 | Laying HT XLPE UG cable of sizes beyond 3 x 185 sq mm and upto and including 3 x 300 sqmm including conveying cable from Sub regional store/stacking placeto work site and laying it carefully using cable rollers,taking through stone ware/Gipipes at road crossing/culverts/bridges etc whereever necessary, providing identification tags at 5m intervals,filling the space around the cable with riddled soil and covering the top with bricks,providing cable route markers at 100 m intervals,inclusive of cost of all materials( other than cost of GI/HDPE pipe & UG cable labour and transportation including crane charges excluding excavation and backfilling |
| 36 | Stringing of one km 3 PH 11 kV line with XLPE insulated ACSR Racoon or equivalent ( 3 conductors) after fitting insulators,binding conductors to pin insulators using suitable tie and anchoring with wedge type anchoring clamps including cutting and removing tree branches wherever necessary excluding cut point works |
| 37 | Providing bridging at Cut points for 3 PH11kV line with XLPE Insulated ACSR Raccoon or equalant (1 conductors) using IPC and respective conductors |
| 38 | Mounting and connecting HT XLPE UG cable ends of all sizes upto and including 3 x 300 sq mm with special type cable clamps, bolts nuts,terminal protectors etc including cost of extra materials if needed and giving necessary jumper connections |
| 39 | Doing straight joint on HT XLPE UG cables of sizes beyond 3 x 185 sq mm and upto and including 3 x 300 sq mm using the cable jointing kit supplied departmentally as per specification after providing proper traffic signalling and caution board fencing etc wherever necessary including charges for cable jointer and other sundries etc as per the direction of departmental officers at site. |
| 40 | Doing one cable end termination on HT XLPE UG cables of sizes beyond 3 x 185 sq mm and upto and including 3 x 300 sq mm using the cable jointing kit supplied departmentally after making fencing , caution board and all other safety measures including charges for cable jointer etc complete as per the direction of departmental officers. |
| 41 | Pole numbering using printed Aluminiumsheets of 22 SWG having size 20 x 12 cm or Painting the surface of line supports where numbers are to be inscribed, Pole numbers shall be painted in circular / rectangular background, using approved quality anti algal yellow paint in two coat after scraping and cleaning the surface at a height of 2.5 metre above ground level. The number and lettersshould be in black synthetic enamel paint.The size of the number should be at least2cm in height x 1.5cm in width. including cost of paint |
| 42 | Transferring LT 3 phase 4/5 wire OH line to newly erected HT/LT pole including dismantling existing cross arm and insulators refitting the same on the new pole,binding ete complete |
| 43 | Transferring LT single phase 2/3 wire OH line to newly erected HT/LT pole including dismantling existing cross arm and insulators refitting the same on the new pole,binding ete complete |
| 44 | Fitting 6 channel cross arms, AB switch,DO fuse,Station class LA,HT & LT connections upto OH lines etc on existing DP structure,Fixing distribution box/provision for one set (3 No) of LT fuses,drawing sufficient lemgth of GI earthing leadsto the groubd for earthing excluding provision for earthing and mounting of transformer on poles |
| 45 | Erecting one 100 kVA Transformer to existing DP and giving connections including loading from TMR/SRS/other stacking places & unloading at site but excluding cost for transporting transformer |
| 46 | Dismantling transformer station withtransformer erected in DP structure bydismantling HT Double Pole Structure using PSC pole after disconnecting stay wires, 10 channel cross arms,AB switch, DO fuse, LA, GI earthing leads, DTR meter with box with metering equipment, CTs, Distribution Box, statutory display boards etc. but excluding the rate of dismantling transformer, earthing, staysets & fencing. |
| 47 | Additional rate for excavation of one Pit for HT pole/ HT stay in hard laterite |
| 48 | Additional rate for excavation of one Pit for HT pole/ HT stay in soft rock |
| 49 | Additional rate for excavation of Pit for A type pole in hard Laterite |
| 50 | Additional rate for excavation of Pit for A type pole in soft rock |
| 51 | Additional rate for excavation of one Pit for HT pole/ HT stay in laterite Please Enable Macros to View BoQ information |