| 1 | Providing Service for Operation & Maintenance of Shahapur raw water pumphouse |
| 2 | Operation & Maintenance of shahapur raw water pumphouse including manpower as per Annexure A, minor spares, and consumables (excluding power) for 1 Month. |
| 3 | Providing Service for Operation & Maintenance of 13 MLD WTP |
| 4 | Operation & Maintenance of 13 MLD WTP including manpower as per Annexure A, minor spares, and consumables (excluding power) for 1 Month. |
| 5 | Shahapur Jackwell Raw water PumpHouse |
| 6 | Pump set -1 and 4Make- JYOTI Flow - 4800 LPMHead-125mMotor capacity - 200 HP |
| 7 | DISMANTLING & MOBILIZATION |
| 8 | Dismantling at site, shifting to workshop & return |
| 9 | Lifting/lowering with column pipes & equipment |
| 10 | MECHANICAL REPAIRS & OVERHAULING |
| 11 | Complete overhauling (opening, cleaning, refitting) |
| 12 | Repairing of pump shaft (SS welding & lathe work) |
| 13 | Replacement of line/head/bowl shaft (SS-410) |
| 14 | Supply and fitment of new GM Wearing Rings |
| 15 | Facing/treatment of bowl stages and impellers |
| 16 | Replacement of Mechanical Seals / Water seals |
| 17 | Replacement of GM bushes or rubber liner bushes |
| 18 | ELECTRICAL & MOTOR WORKS |
| 19 | Motor rewinding with copper wire & varnishing |
| 20 | Replacement of motor bearings (DE & NDE) |
| 21 | Replacement of 3-core submersible cable |
| 22 | Servicing of electrical control panel |
| 23 | TESTING & COMMISSIONING |
| 24 | Dynamic balancing of impellers & rotor assembly |
| 25 | Final full load performance testing at site |
| 26 | Anti-corrosive painting of pump & motor |
| 27 | Shahapur Jackwell Raw water PumpHouse |
| 28 | TESTING & COMMISSIONING |
| 29 | Pump set -2 & 3Make- JYOTI Flow - 4800 LPMHead-127mmotor capacity - 215 HP |
| 30 | DISMANTLING & MOBILIZATION |
| 31 | Dismantling at site, shifting to workshop & return |
| 32 | Lifting/lowering with column pipes & equipment |
| 33 | MECHANICAL REPAIRS & OVERHAULING |
| 34 | Complete overhauling (opening, cleaning, refitting) |
| 35 | Repairing of pump shaft (SS welding & lathe work) |
| 36 | Replacement of line/head/bowl shaft (SS-410) |
| 37 | Supply and fitment of new GM Wearing Rings |
| 38 | Facing/treatment of bowl stages and impellers |
| 39 | Replacement of Mechanical Seals / Water seals |
| 40 | Replacement of GM bushes or rubber liner bushes |
| 41 | ELECTRICAL & MOTOR WORKS |
| 42 | Motor rewinding with copper wire & varnishing |
| 43 | Replacement of motor bearings (DE & NDE) |
| 44 | Replacement of 3-core submersible cable |
| 45 | Servicing of electrical control panel |
| 46 | TESTING & COMMISSIONING |
| 47 | Dynamic balancing of impellers & rotor assembly |
| 48 | Final full load performance testing at site |
| 49 | Anti-corrosive painting of pump & motor |
| 50 | Jakatwadi WTP Pure water PumpHouse |
| 51 | Pump set -1,2,3Make- JYOTI Flow - 4800 LPMHead- 75 mmotor capacity - 120 HP |
| 52 | DISMANTLING & MOBILIZATION |
| 53 | Dismantling at site, shifting to workshop & return |
| 54 | Lifting/lowering with column pipes & equipment |
| 55 | MECHANICAL REPAIRS & OVERHAULING |
| 56 | Complete overhauling (opening, cleaning, refitting) |
| 57 | Repairing of pump shaft (SS welding & lathe work) |
| 58 | Replacement of line/head/bowl shaft (SS-410) |
| 59 | Supply and fitment of new GM Wearing Rings |
| 60 | Facing/treatment of bowl stages and impellers |
| 61 | Replacement of Mechanical Seals / Water seals |
| 62 | Replacement of GM bushes or rubber liner bushes |
| 63 | ELECTRICAL & MOTOR WORKS |
| 64 | Motor rewinding with copper wire & varnishing |
| 65 | Replacement of motor bearings (DE & NDE) |
| 66 | Replacement of 3-core submersible cable |
| 67 | Servicing of electrical control panel |
| 68 | TESTING & COMMISSIONING |
| 69 | Dynamic balancing of impellers & rotor assembly |
| 70 | Final full load performance testing at site |
| 71 | Anti-corrosive painting of pump & motor Please Enable Macros to View BoQ information |