| 1 | Dismantling (without damage) one km LT additional conductor line by dismantling cross arms, insulators and stacking the conductors in rolls properly. |
| 2 | Dismantling (without damage) one km 11kV line (three conductors) including dismantling cross arm, insulators, disc, disconnecting jumper connection, rolling the conductor and stacking the materials. |
| 3 | Dismantling (without damage) one km LT three phase 4 wire OH line conductor by dismantling cross arms, insulators and stacking the conductors in rolls properly. |
| 4 | Dismantling (without damage) one 11kV A type pole after disconnecting stays, strut etc. attached thereon and stacking the same. |
| 5 | Dismantling one damaged 11kV PSC/RCC pole after disconnecting stays, strut etc. attached thereon and stacking the same. |
| 6 | Dismantling one damaged LT PSC/RCC pole after disconnecting stays, strut etc. attached thereon and stacking the same. |
| 7 | Dismantling (without damage) one LT PSC/RCC pole after disconnecting stays, strut etc. attached thereon and stacking the same. |
| 8 | Dismantling (without damage) one LT PSC/RCC Strut pole including removal of clamps and stacking. |
| 9 | Dismantling (without damage) one km LT single phase 2 wire OH line conductor by dismantling cross arms, insulators and stacking the conductors in rolls properly. |
| 10 | Dismantling one section fuse from structure and bringing back to section |
| 11 | Labour charges for loading HT PSC pole from the stacking place and unloading the same at work site (transportation by any vehicle). |
| 12 | Labour charges for loading HT A type pole from the stacking place and unloading the same at work site (transportation by any vehicle). |
| 13 | Labour charges for loading LT PSC pole from the stacking place and unloading the same at work site (transportation by any vehicle). |
| 14 | Transporting poles by hired vehicle to a distance upto 5km and carrying upto 4 numbers of poles excluding loading& unloading charges. |
| 15 | Fitting and erecting one HT A type Single Pole in position, including fitting cross arm, digging and back filling pit in ordinary soil (as per standards), drawing sufficient length of GI earthing leads from F clamp through V cross arm to the ground for earthing (excluding provision of earthing). |
| 16 | Insertion of one HT A type pole in existing OH line including digging & backfilling pit in ordinary soil, fitting cross arm, insulators, binding etc., drawing sufficient length of GI earth leads to the ground for earthing (excluding provision of earthing). |
| 17 | Insertion of one HT PSC pole in existing HT/LT line including digging & back filling of pit in ordinary soil, fitting cross arm, insulator, binding etc. , drawing sufficient length of GI earth leads to the ground for earthing (excluding provision of earthing). |
| 18 | Fitting and providing one HT Stay for 11kV pole, including digging and back filling pit in ordinary soil. |
| 19 | Fitting one Additional 2.4m Channel cross arm in existing single pole including conveyance of materials. |
| 20 | Drilling hole of various sizes on existing Channel/Cross Arm. |
| 21 | Additional rate for refitting/redoing one Disc set while renewing any type of 11kV cut pole. |
| 22 | Stringing of one km 11kV line with ACSR Raccoon (3 conductors) after fitting insulators and giving jumper connections including cutting and removing tree branches wherever necessary excluding cut point works. |
| 23 | Erecting one LT PSC Pole in position including digging & back filling pit in ordinary soil. |
| 24 | Insertion of one LT PSC pole in existing single phase OH line including digging & back filling pit in ordinary soil, fitting cross arm, insulator, binding etc. excluding transportation of poles. |
| 25 | Insertion of one LT PSC pole in existing three phase OH line including digging & back filling pit in ordinary soil, fitting cross arm, insulator, binding etc. excluding transportation of poles. |
| 26 | Providing Strut using LT PSC pole including digging and back filling pit in ordinary soil. |
| 27 | Providing WP support with PSC pole including digging & back filling pit in ordinary soil. excluding transportation of poles. |
| 28 | Providing Stay for LT poles including digging & back filling pit in ordinary soil. |
| 29 | Additional rate for refitting/redoing one Shackle Set, including reshacling one span, while renewing any type of LT pole. |
| 30 | Transferring LT single phase 2/3 wire OH line to newly erected HT/LT pole including dismantling existing cross arm and insulators, refitting the same on the new pole, binding etc. complete. |
| 31 | Transferring LT three phase 4/5 wire OH line to newly erected HT/LT pole including dismantling existing cross arm and insulators, refitting the same on the new pole, binding etc. complete. |
| 32 | Stringing, shackling, fitting cross arms, insulators and binding, giving jumper connection etc. using ACSR Rabbit for Phase and Neutral, for one km LT single phase 2 wire line including cutting and removing tree branches wherever necessary and conveyance of all materials (except poles) from stacking place. |
| 33 | Stringing, shackling, fitting cross arms, insulators and binding, giving jumper connection etc. using ACSR Rabbit for Phase and ACSR Weasel for Neutral, for one km LT three phase 4 wire line including cutting and removing tree branches wherever necessary and conveyance of all materials (except poles) from stacking place. |
| 34 | Stringing, shackling, fitting cross arms, insulators and binding, giving jumper connection etc. using ACSR Rabbit for Phase and ACSR Weasel for Neutral & Street Main, for one km LT 3ph 5 wire line including cutting and removing tree branches wherever necessary and conveyance of all materials (except poles) from stacking place. |
| 35 | Fitting one No. Section fuse on LT line with dropping cables, crimping sockets, connecting with bolt & nut etc. |
| 36 | Disconnecting and lowering down the single phase WP service connection with guy wire from the OH line and reconnecting the same after completing the line work. |
| 37 | Disconnecting and lowering down the three phase WP service connection with guy wire from the OH line and reconnecting the same after completing the line work. |
| 38 | Dismantling one ordinary street light/CFL/LED fitting from existing pole and refitting the same on newly erected pole including disconnecting and reconnecting wires. |
| 39 | Providing one Coil Earth using No.8 GI- earth wire (50mm dia, 115 turns) including digging separate pit (0.45x0.45x1.5m) at standard distance away from the pole/structure in ordinary soil & backfilling. |
| 40 | Providing concrete muffing of size 0.45x0. 45x1.5m (0.5m above GL and 1m below GL). Excavation 0.45x0.45x1m, concrete (1:3:6, 20mm) 0.45x0.45x1.5m, Plastering (1:3) 12mm 0.45x0.45mx5sides. |
| 41 | Pole numbering using printed Aluminium sheets of 22 SWG having size 20 x 12 cm or Painting the surface of line supports where numbers are to be inscribed, Pole numbers shall be painted in circular / rectangular background, using approved quality anti algal yellow paint in two coat after scraping and cleaning the surface at a height of 2.5 metre above ground level. The number and letters should be in black synthetic enamel paint. The size of the number should be at least 2cm in height x 1.5cm in width. including cost of paint. |
| 42 | Providing/Inserting 2 line spacer on the existing LT OH line. |
| 43 | Providing/Inserting 3 line spacer on the existing LT OH line. Please Enable Macros to View BoQ information |