| 1 | Creation of 250KVA Sub Station alongwith LT Line at Sale Tax Complex Lakhanpur for Shri Amar Nath Yatra 2026-27 in respect of Sub Division Kathua of Electric Division, JPDCL Kathua |
| 2 | 250 KVA, 11/0.433-0.250KV;50 Hz, Al wound Distribution Transformer of latest Energy efficiency level-2 ( new), IS1180 part -1, 2014 as per latest upto date amendment with externally fitted MCCB with cable box and 4x4 mtrs. Suitable cable of ratings.(Aluminium Wound upto 200 KVA, Copper Wound for 250 KVA or Higher KVA rattings.) |
| 3 | Gapless Surge Arrestor,9 KV ,10 KA ,LA with polymer housing, Stn. Type |
| 4 | 11KV GO, AB Switch 3-Phase, 3-Pole, 200 Amp, Vertical Type |
| 5 | 11 KV Horn Gap Fuse Set 3 Phase 200A |
| 6 | 185 mm² (2 Ckt) Cable,1.1KV Grade, PVC Insulated Stranded Conductor FRLS type. |
| 7 | 9 Mtr. Long pole (PCC WL -300 KG) |
| 8 | 11KV Polymeric composite Disc Insulator 12KV,min failing load 45KN, Lighting Impulse 75KV Positive and 80KV Negative, creepage distance 320mm |
| 9 | GI Channel/Angle/Flat of sizes including clamps. |
| 10 | Galvanized Nuts and Bolts. |
| 11 | Earthing of substation -Excavation of earth pit of dia 650 mm & depth 3000 mm, installation of Earthing pipe of 40 mm Nominal bore & 4mm wall thickness & length 2.5 mtr long as Per IS 1239.GI Strip for neutral earthing of size 25 mm x 3 mm for connection of transformer body,G.O Set & lightening arrestor as per IS 2629/85, GI nuts & bolts,refilled with earth enhancement materials and earth Chamber made of brick masonary with RCC slab cover. |
| 12 | 11KV Polymeric composite Pin Insulator 12KV, 5kN, Lightening Impulse 75KV Positive and 80KV Negative, creepage distance 320mm |
| 13 | Galvanized Stay Set with 50x8mm stay clamp, guy insulator(2Nos.), anchor plate (200x 200 x 6 mm), nut-bolts, 2 Nos turn-buckles, 1.8m long, 16 mm diameter solid GS stay rod & 7/3.15 mm dia GI stranded wire complete |
| 14 | Wedge connectors /PG clamps |
| 15 | Danger plate with clamps |
| 16 | Anti Climbing devices with clamps |
| 17 | 3 Ph 4 Wire Trivector meter with CT (Prodigy Meter) |
| 18 | Cement bottoming 1:2:4 mix as per REC standerds .5 Cum/pole |
| 19 | Laying of LT line on 8 Mtrs. PCC poles with ACSR Weasel Conductor 3 Phase 4 wire in respect of Sub Division Kathua of Electric Division, JPDCL Kathua |
| 20 | 8 Mtr. Long Pole(WL-200 Kg ) |
| 21 | GI U-Clamp for Shackle insulators |
| 22 | 16 KN Shackle insulators |
| 23 | 30 mm² ACSR Weasel Conductor |
| 24 | Galvanized Nuts and Bolts |
| 25 | Danger Plates with Clamp |
| 26 | Earthing Complete by GI Pipe 40mm or GI rod 20 mm 2.5 Mtr long through GI Strip |
| 27 | Galvanised Stay Set with 50x8mm stay clamp, guy insulator(2Nos.), anchor plate (200x 200 x 6 mm), nut-bolts, 2 Nos turn-buckles, 1.8m long, 16 mm diameter solid GS stay rod & 7/3.15 mm dia GI stranded wire complete |
| 28 | 400 Ampere Change Over Switch 3-Phase 4-Pole Please Enable Macros to View BoQ information |