| 1 | Transportation, Erection & Dismantling of Rig Machine |
| 2 | Transportation of Tubewell Assembly |
| 3 | Transportation, Erection & Dismantling of 350/600 PSI COMPRESSOR |
| 4 | Transportation, Erection & Dismantling of 3 Cusec O.P Unit |
| 5 | Drilling of 600 mm. dia bore from G.L. to 70 m BGL. |
| 6 | Drilling of 500 mm.dia bore from 70 M bgl to 100 m BGL. |
| 7 | Drilling of 500 mm.dia bore from 100 M bgl to 200 m BGL. |
| 8 | Drilling of 500 mm.dia bore from 200 M bgl to 300 m BGL. |
| 9 | Drilling of 500 mm.dia bore from 300 M bgl to 350 m BGL. |
| 10 | 300 mm dia MS ERW pipe from G.L. to 60 m BGL |
| 11 | 200 mm.dia M.S ERW plain/ slotted pipe from 60 m BGL to 100 m BGL |
| 12 | 200 mm.dia M.S ERW plain/ slotted pipe from 100 m BGL to 200 m BGL |
| 13 | 200 mm.dia M.S ERW plain/ slotted pipe from 200 m BGL to 300 m BGL |
| 14 | 300 mm.dia size |
| 15 | 200 mm.dia size |
| 16 | Supply of 1.6 mm to 4.8 mm size pea gravel duly screened and washed as per IS 4097 |
| 17 | Development of Tube well by 600 PSI Compressor |
| 18 | Sodium Hexametaphosphate |
| 19 | Development of Tube well by 3 Cusec O.P. Unit |
| 20 | Extra works Unforeseen item as per site condition of tubewell for approach of units and T&Ps and necessary work around pin point of T/W and entrance of units and placing of such units and T&Ps at site as required as site condition. |
| 21 | Chemical and Bacteriological test of water sample from departmental approved lab |
| 22 | yield and verticality test of tubewell |
| 23 | Electrical Logging of the Bore |
| 24 | Rental charges for rig machine,compressor and op unit |
| 25 | SITC OF 1000 LPM, 50 M. head, 20 HP submersible clear water pumping plant suitable to operate on 415 ± 6% volt, 50 hz for AC supply (as per IS 8034-1989) including starter, control panel, cable complete in all respect with all required T&P Labour. |
| 26 | SITC OF MAIN PIPING & VALVES with 24 m 150 mm dia coloumn pipe, Electronic type Chlorinating plant, Power wiring, earthing, Printing, Tools sets, wiring of pump house (internal & external) Chain Pulley block and gauges complete in all respect with all required material T&P Labour. |
| 27 | 3 M Long Heavy Duty Coloumn Pipe same as above (spare) |
| 28 | Construction of pump house by Excavation of foundation, laying of P.C.C with 1:4:8 cement, sand , brick ballast. B/w in foundation with 1:6 cement sand. Laying of 40 mm thick D.P.C 1:2:4 with D.P.C powder, 23 cm. thick B/w in super structure with 1:6 cement sand casting of R.C.C lental and sun shed 1:1½:3 with cement, sand, steel, casting of R.C.C, slab with 1:2:4 cement, sand, stone grit, construction of of Brick Piller & fixing of M.S Gurder size of 2.45 Mtrs. length, fixing of M.S. Door of 2.10m x 0.90m size of 1 No. Fixing of M.S. window of 0,60m x 1.35 m size of 1 no. Fixing of M.S. Ventilator of size 0.30 x 0.30 M 2 Nos. Laying of P.C.C 1:4:8 thick in Pump House Plaster of Brick Piller, celling and brick wall in 1:6 cement, sand , making of C.C flooring in 1:2:4 cement sand and stone grit in Pump House. Making apron around the Pump House. Painting of Pump House with one coat white cement and two coat snowcem. painting of M.S. door, window, ventilator and gurder with one coat of primer and two coat of enamel paint. All work including of all materials, labours and T . & P. etc. as required for proper completion of work with the internal electrification of pump house. |
| 29 | S.I.T.C OF Servo volatge stablizer for tubewell to make a continuous supply for 20 HP submersible motor-30 kva |
| 30 | Inter connection from new rebore tubewell to existing rising main including supply & fitting of 150 mm dia MS/CIDF pipe & specials, different size nut-bolt washer. Rubber packing and laying of pipe line 80 m approximate including excavation tench in ordinary soil (loam clay or sand) incuding lift up to 1.50 m and lead up to 50 m. filling, watering and ramming of excavated earth in to the trench with side dressing and disposal of surplus earth up to a distance of 50 m from trench. Complete of rising main work in all respect including all materials T&P and labour charge. Please Enable Macros to View BoQ information |