| 1 | Supply of cooling radiator bank (element/fins) complet in all respect including paintsuitable for 80 MVA (132/33 KV) BHEL Make Transformer's as per following details.Fin Width : 525 mmHeight : 3000 mmNo. of fins : 28 Thickness of sheet : 1.2 mm |
| 2 | Supply of EHV Grade Transformer Oil Confirming to IS: 335/1993 in 209 Ltr. capacity sealed barrels including loading/unloading charges etc. |
| 3 | Shifting (to & fro) of oil storage tank for storage of Transformer oil from 400 KV Substation Rishikesh / 220 KV Substation Roorkee or any other S/s of PTCUL to 220 KV Substation SIDCUL, Haridwar with the help of crane, other T&P and truck etc. including loading & unloading. |
| 4 | Safely dismantling of existing UPVC water pipe line & sprinklers installed for cooling of transformer & radiators of 80 MVA transformers-2nd at 220 KV Substation SIDCUL, Haridwar. Work includes all associated work for dismantling complete in all respect with labour and T&P. |
| 5 | Work of draining of transformer oil form 80 MVA Transformers-2nd radiators, conservator, header & pipe line and storage of oil in oil tanker including all associated works, labour and T&P. |
| 6 | Dismantling of existing Cooling radiators banks (element/fins) form 80 MVA Transformers-2nd. Work includes all associated work for dismantling complete in all respect. |
| 7 | Cleaning of top header pipes/bottom header pipes etc. after dismantling of cooling radiators elements. |
| 8 | Replacing of valves & gaskets of top header pipes/bottom header pipes, sockets etc. as per requirement or as per directions of site incharge. |
| 9 | Erection of cooling radiator element/fins on 80 MVA Transformer -2nd. |
| 10 | Re-erction of dismantled UPVC water pipe line & sprinklers for cooling of transformer & radiators of 80 MVA tansformer-2nd at 220 KV Substation SIDCUL, Haridwar. Work includes all associated work for erection complete in all respect with labour, material and T&P. |
| 11 | Arresting oil leakage from various points of 80 MVA Transformers-2nd after cleaning the oily surface with proper oil cleaning agent & old plastic putty (if needed) and apply plastic steel putty / sealing agent to stop the oil leakage on cleaned surface including cost of all T&P required for proper completion of the work as per directions of site incharge. |
| 12 | Work of centrifuging & filling of transformer oil in 80 MVA Transformer-2nd including all associated works, T&P, labour etc. required for proper completion of work. |
| 13 | Shifting of material from site to store of 220 KV Substation SIDCUL, Haridwar including T&P, labour etc. required after proper completion of work. |
| 14 | Testing of power transformer after proper completion of work in all respect. Erection of 33KV indoor termination suitable for 3.5 x 400 Sqmm cable at ACDB panel. Please Enable Macros to View BoQ information |