| 1 | Tubewell |
| 2 | Constructing OHSR one No. of 25 KL (25000 litres) Capacity with sill level not less than 15.50 m height upto FSL 17.50 mtr from formation level complete with external RCC stair case with landing slabs at each staging RCC roof, ventilator single main hole cover lightening conductor and aluminium ladder inside OHSR and M.S. Ladder outside tank complete as described. Providing and fixing DI K-9 D/F expansion joints, bell mouth and D/F puddle collars as per DWSS design on basis of enclosed drawing. Duck foot bends, Conforming to ISI - 9523 and C.I. D/F sluice Valve duly ISI marked (IS-14846-2000 or latest) one each with inlet, outlet and scour pipes & overflow, DI double flanged pressure pipes DI K-9 horizontally as per IS 8329-2000 and latest duly ISI marked from bottom dome to duck foot bend and further up to 2.75 mtr as per detail specification. TMT steel of approved make & painting of all external surface. Providing and applying cystalline slurry of hydrophilic in nature for water proofing management etc. for vertical and horizontal surfaces and swellable type water stop tape complete in all respect.(Note:- The specifications & drawing are based on safe bearing capacity of soil of is not less than 8.75 tone per sqm. In case the safe bearing capacity of less than 8.75 tone per Sqm. than The contractor shall submit his own design for foundation portion based on actual safe bearing capacity as per DWSS specifications. The difference in quantities from the standard drawing based on 8.75 tone per sqm safe bearing capacity will be paid as per CSR+ Prevailing Ceiling Premium including providing and fixing automatic Electronic Water Level control Device and Construction of Plinth protection around OHSR with brick masonry toe wall with 40 mm thick CC 1:2:4 on top cover, 100 mm thick CC 1:8:16 & inside earth filling including overflow scour haudi complete in all respects. (all including carriage) |
| 3 | Providing, Stringing out PVC pipes ISI Marked as per ISI-4985 along the Trenches and laying the same in Trenches To correct alignment and gradients, Excavation, cutting. Jointing, testing & back filling complete as per specifications for more than 3 mtr street width (Mechanically)PVC Pipe 63mm o/d (6Kg/Cm2) |
| 4 | Providing, Stringing out PVC pipes ISI Marked as per ISI-4985 along the Trenches and laying the same in Trenches To correct alignment and gradients, Excavation, cutting. Jointing, testing & back filling complete as per specifications for more than 3 mtr street width (Mechanically)PVC Pipe 90mm o/d (6Kg/Cm2) |
| 5 | Providing, Stringing out PVC pipes ISI Marked as per ISI-4985 along the Trenches and laying the same in Trenches To correct alignment and gradients, Excavation, cutting. Jointing, testing & back filling complete as per specifications for more than 3 mtr street width (Mechanically)PVC Pipe 110mm o/d (6Kg/Cm2) |
| 6 | Providing, Stringing out PVC pipes ISI Marked as per ISI-4985 along the Trenches and laying the same in Trenches To correct alignment and gradients, Excavation, cutting. Jointing, testing & back filling complete as per specifications for less than 3 mtr street width (Manually)PVC Pipe 63 mm o/d (6Kg/cm2) |
| 7 | Dismantling brick or flagged stone flooring without concrete base and relaying of dry brick on edge paving with a dismantled bricks including sand grouting.For PVC Pipe 63 mm o/d (6Kg/cm2) |
| 8 | Dismantling brick or flagged stone flooring without concrete base and relaying of dry brick on edge paving with a dismantled bricks including sand grouting.For PVC Pipe 90mm o/d (6Kg/cm2) |
| 9 | Dismantling of metallic road with bituminous course 50 to 75mm thick C.C. 1:8:16 and making good the same to its original condition complete in all respectsNo. of cut 11x 5 (Width of road) |
| 10 | Providing & fixing C.I/D.I Flanged end, stem of SS (AIS 1410) and Bronze (gunmetal) working parts Sluice Valves ISI marked 14846-2000, including jointing, testing & cost of Nut, Bolt & insertion sheet, all carriage complete (with the approval of Engineer - in - charge) 80 mm I/d |
| 11 | Construction of Masonary Sluice Valve Chamber excluding Sluice Valve cover as per standard design & drawings of public health department.0.6 x 0.6 |
| 12 | Providing & fixing G.I. Barbed wire 3 ply fencing around the head works site in three rows complete in all respects including cost of winding wire & aluminum painting complete in all respects as per standard Drawing. |
| 13 | Providing & fixing angle iron pickets with angle 40mm x40mm x 6mm including cost of concrete block & painting complete in all respects as per standard Drawing. |
| 14 | Providing & fixing D.Hook complete with MS Bolts size 300mm x 18mm as per standard Drawing. |
| 15 | Construction of brick masonry corner pillar including cost of cement pointing including cost of material complete in all respects as per standard Drawing. |
| 16 | Construction of masonry gate pillar including cost of MS Steel Gate size 1.22mtr x 1.37 mtr as per standard Drawing complete in all respects |
| 17 | Construction of Cement Concrete, Foot Path with masonry toe wall & earth filling inside water works as per standard Drawing. |
| 18 | Providing & fixing MS Sign Board as per standard size of DWSS. |
| 19 | Providing Household connection laying, jointing, fixing testing MDPE pipes (as approved by Engineer-in-charge) including cost of excavation refilling with meter, C.I bib clock as IS:210 with stainless steel spindle 20 mm o/d MDPE pipe 4.50 mtr (2.00 mm MDPE & 2.50 mtr G.I, vertical pipe) 3\\" i/d uPVC clamps, GM ferrule ISI marked connection of 15 mm i/d ferrule medium, specials such as tees, bends, sockets, elbows, nipples (100 mm & 150 mm) union couplings, G.I Hooks etc and Gun metal peet valve (heavy pattern) with hand wheels on MDPE pipeline laid in the ground or inside building, cutting, treading, making hole in wall and testing in trenches in ground complete in all respect. |
| 20 | Construction of Pump Chamber size 3.05 m X 3.70 m including cost of gravel pit & electric wiring as per standard design complete in all respect. |
| 21 | Construction of 1 no. set of Toilet. |
| 22 | Digging of pits in all kinds of soil & refilling the same, with the excavated earth mixed with well decayed farm yard manure @ 30% of pit volume and insecticide for termite control |
| 23 | Supplying and planting permanent trees in prepared pits and watering (a) Sapling not less than 1.8m height and 2.5 m calliper |
| 24 | Planting seasonal flower in bedsPlanting seedlings including digging of beds to 15 cm depth and mixing FYM, fertilizer and insecticides, planting of seedlings at 20cm distance from plant to plant and row to row. |
| 25 | Planting ground covers (ordinary) including digging of beds to 15 cm depth and mixing FYM, fertilizer and insecticides, planting of sapling at 25cm distance from plant to plant and row to row. Please Enable Macros to View BoQ information |