| 1 | SUPPLY OF FOLLOWING MATERIAL |
| 2 | Supply of Nut, Bolt & Washer as per RESPO Norms. |
| 3 | Supply of Loop Insulator as per RESPO Norms. |
| 4 | Supply of clamp different sizes |
| 5 | supply of stay clamp |
| 6 | Safe loading,unloading carriage of following material from storage centre/temperory store to work site and vice versa if required |
| 7 | PCC POLE 8.5MTR LONG |
| 8 | STP 11/13MTR LONG |
| 9 | 11KV XLPE CABLE 3X185MMSQ |
| 10 | 33KV XLPE CABLE 3X300MMSQ |
| 11 | ACSR WEASEL/RABBIT/DOG CONDUCTOR |
| 12 | GI WIRE |
| 13 | STAY SET |
| 14 | AB CABLE |
| 15 | LINE MATERAIL WITH JOINTING KIT |
| 16 | EXECUTION AS PER FOLLOWING |
| 17 | Laying of 11 kv xlpe cable for making temporary arrangement for restoration of supply after dismentaling existing infra |
| 18 | Laying of 33 kv xlpe cable for making temporary arrangement for restoration of supply after dismentaling existing infra |
| 19 | dismentaling of 11 kv under ground line after the ceremony as per direction from site incharge with carriage upto required storage.(Proper removing and safe loading/unloading of cable is responsibility of contractor) |
| 20 | dismentaling of 33 kv under ground line after the ceremony as per direction from site incharge with carriage upto required storage.(Proper removing and safe loading/unloading of cable is responsibility of contractor) |
| 21 | Erection of P.C.C/STP Double pole-11/13 MTR including the work of complete H.T. fittings/LT FITTINGS as per RESPO manual and as per direction of engineer Incharge including the cost of labour, T & P and carrier etc. required for proper completion of work. (only Pole, Providing By Department) |
| 22 | Grouting of P.C.C/STP Double pole 11 mtr. The support shall be grouted with cement, sand and brick ballast/stone ballast In ratio 1:4:8 including the cost of arrangement of cement, sand, brick ballast/stone ballast, stone pad etc. as per actual site requirement. |
| 23 | Erection of P.C.C Single pole 8.5 mtr including the work of complete H.T. fittings/LT FITTINGS as per RESPO manual and as per direction of engineer Incharge including the cost of labour, T & P and carrier etc. required for proper completion of work. (only Pole, Providing By Department) |
| 24 | Grouting of P.C.C 8.5 mtr. The support shall be grouted with cement, sand and brick ballast/stone ballast In ratio 1:4:8 including the cost of arrangement of cement, sand, brick ballast/stone ballast, stone pad etc. as per actual site requirement. |
| 25 | Erection of P.C.C/STP Single pole 11 mtr including the work of complete H.T. fittings/LT FITTINGS as per RESPO manual and as per direction of engineer Incharge including the cost of labour, T & P and carrier etc. required for proper completion of work. (only Pole, Providing By Department) |
| 26 | Grouting of P.C.C/STP 11 mtr. The support shall be grouted with cement, sand and brick ballast/stone ballast In ratio 1:4:8 including the cost of arrangement of cement, sand, brick ballast/stone ballast, stone pad etc. as per actual site requirement. |
| 27 | Erection of stay set as per RESPO manual. |
| 28 | Grouting of stay set including the work of nozelling etc. as per RESPO manual and also including the cost of all grouting material, labour, T & P etc. required for proper completion of work. |
| 29 | Dismentling of Existing 11/33/.4 kv line of Weasal/Racoon /DOG conductor wire and G.I Wire as per RESPO manual and as per direction of supervising engineer. It includes the cost of labour, T & P, carries etc. required for proper completion of work. |
| 30 | Laying, Sagging, Stringing, Binding and Jumpering etc. of Weasal/Racoon /DOG conductor on the newly erected pole as per RESPO manual and as per direction of supervising engineer. It includes the cost of labour, T & P, carries etc. required for proper completion of work.(ONLY POLE,WIRE,INSULATOR PROVIDED BY DEPARTMENT) |
| 31 | Laying of LT ABC Cable of Different Sizes ( 3X120+1X95+1X16), ( 3X50+1X35+1X16), ( 3X95+1X70+1X16), ( 1X16+1X25) As per respo manual(ONLY ABC PROVIDED BY DEPARTMENT) |
| 32 | Fixing of cable jointing kit outdoor 11 kv 3*185 |
| 33 | Fixing of cable jointing kit st.th 11 kv 3*185 |
| 34 | Supply & erection of various types of Clamp with N&B as per RESPO Norms. (X-Arm Holding Clamp, F Clamp, PG Clamp, Dead End Clamp, Suspension Clamp, I Hook Clamp, Distribution Box Clamp etc.) |
| 35 | Guarding of 11 K.V. Line Crossing (Only G.I Wire P roviding by Department) |
| 36 | Trimming of Tree Branches |
| 37 | Fixing of cable jointing kit outdoor 33 kv 3*300 |
| 38 | Fixing of cable jointing kit outdoor 33kv 3*300 |
| 39 | Earthing Complete Body with Earth Rod as per RESPO Norms (Only Earthrod,G.I. Wire Provided by department) |
| 40 | Disconnection of EXISTING consumer's electricals connection . |
| 41 | Reconnection of consumer's electricals connection . |
| 42 | Dismentling of damage and old Pole |
| 43 | Dismentling of damage and old double pole with tf |
| 44 | Carriage of material pit site to Hardoi store Je dump store/store center of Hardoi.(With safe loading and unloading) Please Enable Macros to View BoQ information |