| 1 | Preparation and consolidation of sub grade with power road roller of 8 to 12 (Eight to twelve) tonne capacity after excavating earth to an average of 22.5 cm (Twenty two point five centimetre) depth, dressing to camber and consolidating with road roller including making good the undulations etcetra and re-rolling the sub grade and disposal of surplus earth with upto all leads including entire carriage of materials within all leads and lifts and as per drawings and technical specifications as per the direction of Engineer-in-Charge including all incidentals.The rates are inclusive of octroi, royality, malkana, toll tax, GST or other taxes imposed by the Government. |
| 2 | Providing, laying, spreading and compacting graded stone aggregate (size range 53 mm to 0.075 mm) (fifty three millimetre to zero point zero seven five millimetre) to wet mix macadam (WMM) specification including premixing the material with water at OMC in for all leads and lifts, laying in uniform layers with mechanical paver finisher in sub- base / base course on well prepared surface and compacting with vibratory roller of 8 to 10 tonne (eight to ten tonne) capacity to achieve the desired density, complete as per specifications and directions of Engineer-in-Charge as per direction of Engineer-in-Charge including entire carriage of materials within all leads and lifts and other incidentals. The rates are inclusive of octroi, royality, malkana, Toll tax, GST or other taxes imposed by the Government. |
| 3 | Providing and laying mechanically mixed and vibrated cement concrete nominal mix 1:3:6 (one cement :three Sand :six graded crushed stone aggregate 20mm (twenty millimetre nominal size) on ground or under water and curing complete including pumping or bailing out water, dewatering removal of slush as required at site which may arise at the time of laying under water complete for all heights and depths including cost of form work for plain concrete in drain and channel etc. open foundations complete as per drawing and technical specification clause 802,803, 1202 &1203 including carriage of material within all leads and lifts and other incidentals . The rates are inclusive octroi , royality , Malkana, toll tax, GST or other taxes imposed by the Government . |
| 4 | Providing and laying in position ready mixed plain cement concrete, M-25 (M-Twenty five) with cement content as per approved design mix and manufactured in fully automatic batching plant and transported to site of work in transit mixer for all leads, having continuous agitated mixer, manufactured as per mix design of specified grade for plain cement concrete work, including pumping of R.M.C. from transit mixer to site of laying and curing, excluding the cost of centering, shuttering and finishing, including cost of curing, admixtures in recommended proportions as per IS : 9103 to accelerate/ retard setting of concrete, improve workability without impairing strength and durability All works upto plinth level as per direction of the Engineer- in-charge including entire carriage of material within all leads and lifts and other incidentals.The rates are inclusive of octroi, royality, malkana, Toll tax, GST or other taxes imposed by the Government. |
| 5 | Earth work in excavation for all type of road structure such as retaining walls ,breast walls, culverts, drains and parapets etcetera in all type of classification of soil comprising of ordinary soil . ordinary rock, hard rock, chiseling/ wedging out of rock (where blasting is prohibited ) as per drawings and M.O.R.D technical specification clause 305-1 and as per direction of the Engineer-in- Charge including setting out, construction of shoring and bracing removal of stumps and other deleterious materials and disposal of materials upto any leads and lifts including dressing of sides and bottom and back filling in trenches with excavated suitable approved material to the original surface in layers not exceeding 150mm(one hundred fifty millimetre) compacted thickness including shoring and strutting and pumping and bailing out water ( surface and sub soil water) upto any depth and any quantum of water including cleaning of slush which may arise out during dewatering as per the direction of the Engineer-in- Charge including carriage of materials within all leads and lifts and other incidentals . The rates are inclusive octroi , royality , Malkana, toll tax, GST or other taxes imposed by the Government. |
| 6 | Providing and laying cement concrete 1:5:10 mechanically mixed (one cement : Five sand : ten graded crushed / broken stone aggregate 40mm (forty millimetre nominal size) and curing complete including the cost of form work with M.S plates for plain concrete on ground or under water and curing complete including pumping or bailing out water, dewatering removal of slush as required at site which may arise at the time of laying under water complete for all heights and depths. In retaining walls / breast walls as per drawing and technical specifications clause 802,803,1202and 1203 and as per direction of Engineer-in- Charge including entire carriage of material with in all leads and lifts and other incidentals . The rates are inclusive octroi , royality , Malkana, toll tax, GST or other taxes imposed by the Government . |
| 7 | Back filling behind abutment wing wall and return wall with granular material complete as per drawing and technical specification clause 1204.3.8 including carriage of material within all leads and lifts and other incidentals. The rates are inclusive octroi , royality , Malkana, toll tax, , GST or other taxes imposed by the Government. |
| 8 | Providing weep holes in brick masonry / stone masonry /plain and reinforced concrete abutment , wing wall ,return wall ,retaining and breast wall with 110mm (one hundred ten millimetre) dia PVC pipe (D-plast)/ Finolex/ Supreme having working pressure not less than 4 kg per centimeter square (Four Kilogram per centimeter square ) extending through the full width of the structures with slope of 1(V):20(H) towards drawing face complete as per drawing and technical specification clause 614, 709, 1204.3.7 as per direction of Engineer-in- Charge including entire carriage of material within all leads and lifts and other incidentals The rates are inclusive octroi , royality , Malkana, toll tax, GST or other taxes imposed by the Government. |
| 9 | Construction of embankment with approved material obtained from borrow pits within all lift transpotation to site spreading grading to required slope and comacting to meet requirement of table 300.1 and 300.2 as per direction of Engineer-in-Charge including entire carriage of material within all leads and lifts and other incidentals. The rates are inclusive of octroi, royality, malakana, toll tax, sale tax, GST or other taxes imposed by the Government. Please Enable Macros to View BoQ information |