| 1 | 25 KVA Trsanformer |
| 2 | Prov. Distribution Transformer (Ordinary), 11/0.4 kV, 25 KVA . |
| 3 | Prov. Steel Tubular Poles (9 m, Working Load > 200 kgf/m²) . |
| 4 | Prov. Muffs with concerete filling |
| 5 | Prov. X-Arm: [Channel Iron (100x50x6 mm), Length : 2800 mm X 2 Nos] for incomer line |
| 6 | Prov. MS Angle Iron (50X50x6 mm), Length: (2800 mm) x1 Nos for LA's |
| 7 | Prov. X-Arm: [Channel Iron (75x40x6 mm), Length : (2800 mm X 4 Nos] for supporting DO fuse unit & GO switch |
| 8 | Prov. Transformer Bed, Belting & Knee Bracing |
| 9 | Prov. X-Arm: [Channel Iron (100x50x6 mm), Length : 2800 mm X 2 Nos] for Transformer Bed |
| 10 | Prov. X-Arm [Channel Iron (100x50x6 mm), Length : (460 mm) x 2 Nos for supporting Main Channel of Transformer] |
| 11 | Prov. MS Angle Iron (50X50x6 mm), Length : (2800 mm) x 2 Nos |
| 12 | Prov. MS Angle Iron (35X35x5 mm), Length : (460 ) x 2 Nos |
| 13 | Prov. MS Angle Iron (50X50x6 mm), Length : (950 mm) x 2 Nos for Bed Knee Bracing |
| 14 | Prov. Transformer LT Distribution Box and GO Switch fixing Assembly |
| 15 | Prov. MS Angle Iron (50X50x6 mm), Length : (2800 mm) x 2 Nos |
| 16 | Prov. MS Angle Iron (50X50x6 mm), Length : (450 mm) x 1 Nos |
| 17 | Prov. GO Switch Handle Supporting: [Channel Iron (75x40x6 mm), Length : 460 mm |
| 18 | Prov. GO AB Switch Unit (11kV, 400A, 25 KA ) Tripple pole O/D type |
| 19 | Prov. D.O Fuse Unit |
| 20 | Prov. Lighting Arrester, 9 kV Station Class (Porcelain Type) |
| 21 | Prov. Discs insulator sets (comprising 1 No. Disc: ^^(Porcelain, BS, 12 kV, 90 kN) including Dead End Clamps etc.) |
| 22 | Prov. Stay set complete |
| 23 | Prov. Stay Wire (7/3.15 mm) (6.0 kg Per Stay Set) |
| 24 | Prov. Pipe Earthing Set |
| 25 | Prov. LT Distribution Panel Box With MCCB(160A, 10KA, 4P, 1No) & SFU(32A, 5No, rewirable) |
| 26 | Prov. Half Clamp (M.S. Flat 50X6 mm) |
| 27 | Prov. Full Clamps (M.S. Flat 50X6 mm) |
| 28 | Prov. Nuts and Bolts of Various Sizes (Galvanised / Coated) [Preferably 16 mm Φ or more (with flat and spring washers)] |
| 29 | Prov. Aluminium Thimble |
| 30 | Prov. Copper Thimble 35 Amp |
| 31 | Prov. Danger Plate |
| 32 | Prov. Barbed Wire |
| 33 | Prov. LT Cable (3.5 Core) 50 mm² |
| 34 | Prov. Energy Meter 3-ɸ, 4 wire CT operated Static Tri-Vector meter with Box(CT-100A) |
| 35 | Prov. Aluminum Paint. |
| 36 | Prov. 6/1/3.35, 50mm² . |
| 37 | Prov. Construction of Foundation of Transformer |
| 38 | Erection of 25 KVA S/Stn. i.e. digging of pit for pole & earthing two No. poles & 3 Nos. for earth drilling of holes in X-arms, preparation of plateform str. Members C.I., A.L. i.e. X-arms & K.B. set, errection of D/P, concreating of RCC muff errection of plateform, errection of X-arms, D.O., L.A., MCCB, Switch LT box, energy meter, errection of transformer, earthing connection to G.O. switch, Transformer L.A. etc., errection of stay set, jumper, pipe earthing 3 Nos set, L.T. cable, barbed wire and painting complete in all respect. |
| 39 | Transportation charges @10490/- |
| 40 | Prov. Transportation charges & Mannual carriage of 25 KVA pole mounted distribution S/Stn. (line length 0.500Km) |
| 41 | Erection of 3- Ph. LT Line |
| 42 | Prov. AAAC (7/3.15 50mm²) { Neutral conductor including 1% (Sag, Jumpering and wastage} |
| 43 | Prov. Steel Tubular Poles (8 m, Working Load > 200 kgf/m²). |
| 44 | Prov. Muffs with concerete filling |
| 45 | Prov. Shackle Insulator with D-Iron |
| 46 | Prov. LT Stay Set I/c Egg Insulator. |
| 47 | Prov. Nuts and Bolts of Various Sizes (Galvanised / Coated) [Preferably 16 mm Φ or more (with flat and spring washers)] |
| 48 | Prov. Stay Wire |
| 49 | Prov. G.I wire No 8SWG |
| 50 | Erection of 8 Mtr. ST pole single structure i.e. digging of pit, fixing of insulator, x-arms, K.B. set, Top clamp, barbed wire, danger plate, drilling of holes and filling of pit + ramming complete in all respect. |
| 51 | Sagging of conductor i.e. laying, stringing and sagging & binding with insulator (Single wire per KM). |
| 52 | Sagging of G.I i.e. laying, stringing and sagging & binding with insulator (Single wire per KM). |
| 53 | Erection of Stay set LT i.e. digging of pit, fixing of stay road, filling of pit, nozzeling & tightning |
| 54 | Transportation charges @10490/- |
| 55 | Mannual carriage of material 1 KM LT line considering average distance from road to site of work Quantities are mentioned above are tentative and Actual Quantity shall be worked out after Check Survey to be carried out by the successful Tender and detailed Engineering and finalization of Tower location Chart.Payment shall be made as per Approved Bill of Material/Actual Quantities measured at site. Please Enable Macros to View BoQ information |