| 1 | Supply & erection of Steel tubular pole with 1/6 over all length of pole grouted with cement concrete in 1:3:6 (1 cement : 3 coarse sand : 6 stone ballast) including plinthing of pole 30 cm above the ground level, plastering of plinth including excavation back filling etc. The rates includes all materials labour & T&P. etc. required for proper completion of work as per direction of E/I. 410 SP-62, 12mtr. (Approx. wt. 264kg.) YEIDA SOR-24 |
| 2 | S/F of cross arm made of 100X50X6 mm M.S. channel 2.5 mtr. long on poles with packing, piece, M.S. clamp, Nut bolts etc. complete in all respect, as directed by Engineer in charge YEIDA SOR-30 |
| 3 | S/F of 33 KV Polymeric pin insulator with pin on poles or anywhere specified including bolts to fasten on pole cap/cross arm with the poles. Complete in all respect, as directed by Engineer in charge. (Jaishree, BHEL, RR, Hindustan, Yamuna, AD, make). YEIDA SOR-87 |
| 4 | Painting of the electric pole with two coat of Al-paint over red oxide primer Complete in all respect, as directed by Engineer in charge PWD 2018 PS No-634 |
| 5 | Supply & fixing of MS rod for earthing with 2.5 m long, solid, 20 mm dia hot dipped galvanised MS rod buried till the top reaches 1.7 mts. Below the GL complete with bolts & nuts & GI earth wire 7/14. Complete in all respects as per direction of the Engineer-in-charge. YEIDA SOR-52 |
| 6 | S/F of G.I Pipe 150MM dia \\"B\\"class Zindal/tata make including required material T&P etc. Complete in all respect, as directed by Engineer in charge. as per the directions of the Engineer-in-charge. YEIDA SOR-65 |
| 7 | S/L of 200mm dia. H.D.P.E pipe for drawing of power cable across the road by drilling of 220mm dia. at 1mtr. Below the road level thereby doing the work of providing H.D.P.E pipe by Trenchless method PE-63/PN-6.Complete in all respects as per direction of the Engineer-in-charge. YEIDA SOR-54. |
| 8 | Supply, delivery, laying, testing & commissioning of 33KV (E) XLPE cable having compact circular stranded aluminium conductor The conductor should have screening of extruded semi conducting compound, cross linked polythylane (XLPE), insulation screening of the extruded semin conducting compound followed by copper tape, cores laid up, taped PVC inner sheath, single layer of steel strip armouring, overall PVC outer sheath conforming to IS: 7098 (Part-amendments) for following mentioned sizes. It should be operational at 33 KV, 50 Hz. AC system in ground at a depth of 1200 mm below ground level over a cushion of 75 mm thick sand alround and protected with bricks on sides and at the top surface the cable run shall be fixed on M.S. clamps etc of suitable size or as directed by the E/I with Complete in all respect. The price are inclusive of all earth work such as digging, back filling, supply & spreading of good earth all around the cable, supply & providing cable identification markers. The installation should be complete in all respects and as per requirement of the job as per direction of Engineer-in-charge.Make- CCI, Gloster, Asian, Universal, Nicco, ICL, Diamond, Havells & KEI YEIDA SOR-3 3CX400 Sq.mm. |
| 9 | Supply, Delivery, Installation, Testing & Commissioning of 33KV, following type cable termination kit complete in all respect as required for proper completion of work As per direction of Engineer-in-charge. (Make Raychem, CCI, Frontec) YEIDA SOR-9 3CX400 Sq.mm Indoor type |
| 10 | Supply, Delivery, Installation, Testing & Commissioning of 33KV, following type cable termination kit complete in all respect as required for proper completion of work As per direction of Engineer-in-charge. (Make Raychem, CCI, Frontec) YEIDA SOR-9 3CX400 Sq.mm Outdoor type |
| 11 | Supply, Installation, Testing & Commissioning of Straight through cable jointing kit for 33KV XLPE armoured cable jointing. Complete in all respects as required for proper completion of work as per direction of Engineer-in-charge.(Make Raychem, CCI, Frontec) YEIDA SOR-8 3CX400 Sq.mm. |
| 12 | Supply & fixing of Cable route marker including Painting & Writing Complete in all respects as per direction of the Engineer-in-charge. YEIDA SOR-55. Please Enable Macros to View BoQ information |