| 1 | Scope of Work/Technical Specifications etc:-As per scope of work as mentioned in NIT |
| 2 | Job A:-Complete Repairing and rewinding of 06 Nos 30kW de-dust blower motor. |
| 3 | Providing of Super enameled Copper wire(25kg in each blower) |
| 4 | Nomex paper 3 mil. (01kg in each blower) |
| 5 | Insulating Varnish (Dr.Beck). (2.5Ltr in each blower) |
| 6 | Insulating Thinner. (0.8Ltr in each blower) |
| 7 | Cotton tape 1” (8 Roll in each blower) |
| 8 | Bearing 6311-ZZ(2 Nos. in each blower) |
| 9 | Heating Charges. (40Hrs in each blower) |
| 10 | Charges for dismantling of de-dust Blower and Complete repairing and rewinding. |
| 11 | Less Old Scrap(-)(25Kg for each) |
| 12 | Job B:-Complete Repairing and rewinding of 04 Nos 3kW axial fan blower motor |
| 13 | Providing of Super enameled Copper wire(5kg in each blower) |
| 14 | Nomex paper 3 mil. (0.1kg in each blower) |
| 15 | Insulating Varnish (Dr.Beck). (0.5Ltr in each blower) |
| 16 | Insulating Thinner. (0.25Ltr in each blower) |
| 17 | Cotton tape 1” (1 Roll in each blower) |
| 18 | Bearing 6207-ZZ(2 Nos. in each blower) |
| 19 | Heating Charges. (30Hrs in each blower) |
| 20 | Charges for dismantling of axial fan blower and Complete repairing and rewinding. |
| 21 | Less Old Scrap(-)(5Kg for each) |
| 22 | Job-C:- Complete repairing and rewinding of 7Nos 5.5 kW, 415V,2800 RPM, Drive Motor Blower |
| 23 | Providing of Super enameled Copper wire(8kg in each blower) |
| 24 | Nomex paper 3 mil. (0.16kg in each blower) |
| 25 | Insulating Varnish (Dr.Beck). (0.8Ltr in each blower) |
| 26 | Insulating Thinner. (0.5Ltr in each blower) |
| 27 | Cotton tape 1” (2 Roll in each blower) |
| 28 | Bearing 6208-ZZ(2 Nos. in each blower) |
| 29 | Heating Charges. (30Hrs in each blower) |
| 30 | Labour Charges for dismantling of drive blower motor and Complete repairing and rewinding. |
| 31 | Less Old Scrap(-)(8Kg for each) |