| 1 | Excavation for StructuresA. Without dewatering.Earthwork in excavation for structures as per drawing and MoRD technical specifications Clause 305.1 including setting out, construction of shoring & bracing, removal of stumps & other deleterious material and disposal upto a lead of 50 m, dressing of sides & bottom and backfilling in trenches with excavated suitable material.I Ordinary Soil(i) Upto 3 m depth |
| 2 | Filling in foundation trenches as per drawing & MoRD technical specification Clause 305.3.9, 1200.I Sand filling |
| 3 | Providing concrete for plain concrete (using jhama brick aggregate) in open foundations complete including formwork as per drawings & MoRD technical specifications Clauses 802, 803, 900, 1202 and 1203. (including centering, shuttering, staging etc. but excluding reinforcement)I P.C.C grade M 10 (using jhama brick aggregate)(i) Nominal mix 1:3:6 |
| 4 | Brick masonry work in cement mortar in substructure complete excepting pointing & plastering, as per drawing & MoRD technical specification Clauses 602, 603, 604, 1202 and 1204. II In 1:4 cement mortar |
| 5 | Providing & laying reinforced cement concrete in superstructure as per drawings & MoRD technical specifications Clauses 800, 900, 1205.4 & 1205.5 (including centering, shuttering, staging etc. but excluding reinforcement).(I) R.C.C grade M 20(i) For nominal mix 1:2:4 |
| 6 | Supplying, fitting & placing Thermo-Mechanically treated bar/ Cold twisted deformed steel bar in substructure complete as per drawings & MoRD technical specification Clauses 1002, 1005, 1010 and 1202. |
| 7 | Plastering with cement mortar (1:4) 12 mm thick on brickwork / C.C. work including a finishing coat of neat cement punning with 2.75 Kg of cement per sqm in substructure as per MoRD technical specification Clauses 613.4 & 1204. |
| 8 | Construction of Embankment with Material Obtained from Borrow PitsConstruction of embankment with approved material obtained from borrow pits with a lift upto 1.5 m, transporting to site, spreading, grading to required slope and compacting to meet requirement of Tables 300.1 and 300.2 with a lead upto 1000 m as per MoRD Technical Specification Clause 301.5 |
| 9 | Tack coat using hot straight run bitumen of grade VG-30 onbituminous surfaceProviding and applying tack coat using hot straight run bitumen ofgrade VG-30, including heating the bitumen, spraying thebitumen, cleaning and preparing the existing road surface as perspecifications: On bituminous surface @ 0.50 Kg/ Sqm. |
| 10 | 20 mm thick Open-Graded Premix Carpet using Bituminous (Viscosity grade/ modified bitumen) BinderProviding, laying and rolling of open-graded premix carpet of 20 mm thickness composed of 13.2 mm to 5.6 mm aggregates either using Viscosity grade bitumen or emulsion to required line, grade and level to serve as wearing course on a previously prepared base , including mixing in a suitable plant, laying and rolling with a three wheel 80 - 100 kN static roller capacity, finished to required level and grades to be followed by seal coat of either Type A or Type B or Type C or Type D as per MoRD Technical Specification Clause 508.Case - I : By Manual Means(I) Bitumen of VG-30 |
| 11 | Seal CoatProviding and laying seal coat sealing the voids in a bituminous surface laid to the specified levels, grade and cross fall using Type A or Type B or Type C or Type D as per MoRD Technical Specification Clause 510.A By Manual MeansCase - IV : Type D (premix with fine sand)(I) Bitumen of VG-30 |
| 12 | Construction of toe walls for protection of slopes as per Drawing and MoRD technical specifications Clause 1302.5 (including centering, shuttering staging etc. but excluding reinforcement)I. Cement concrete grade M 10 (using jhama brick aggregate) in case of concrete block pitchingi) Nominal mix 1:3:6 Please Enable Macros to View BoQ information |