| 1 | Construction of Subgrade and Earthen Shoulders Construction of sub-grade and earthen shoulders with approved material obtained from borrow pits with all lifts & leads, transporting to site, spreading, grading to required slope and compacted to meet requirement of Table No. 300-2 l (Lead 8km) |
| 2 | Earth work in excavation of foundation of structures as per drawing and technical specification, including setting out, construction of shoring and bracing, removal of stumps and other deleterious matter, dressing of sides and bottom, backfilling the excavation earth to the extent required and utilising the remaining earth locally for road work. Ordinary soil |
| 3 | PCC 1:3:6 in Foundation Plain cement concrete 1:3:6 nominal mix in foundation with crushed stone aggregate 40 mm nominal size mechanically mixed, placed in foundation and compacted by vibration including curing for 14 days. |
| 4 | Construction of granular sub-base by providing close graded Material, mixing in a mechanical mix plant at OMC, carriage of mixed Material to work site, spreading in uniform layers with motor grader on prepared surface and compacting with vibratory power roller to achieve thedesired density, complete as per clause 401 (for small project upto 50 Crore.) |
| 5 | Wet Mix Macadam (Plant Mix Method) Providing, laying, spreading and compacting graded stone aggregate to wet mix macadam specification includingpremixing the Material with water at OMC in mechanical mix plant carriage of mixed Material by tipper to site, laying in uniform layers with grader in sub- base / base course on well prepared surface and compacting with vibratory roller to achieve the desired density. (for small project upto 50 Crore.) |
| 6 | Providing and laying dense graded bituminous macadam with higher capacity batch type HMP using crushed aggregates of specified grading, premixed with bituminous binder @ 4.0 percent by weight of total mix and filler, transporting the hot mix to work site, laying with a hydrostatic paver finisher with sensor control to the required grade, level and alignment, rolling with smooth wheeled, vibratory and tandem rollers to achieve the desired compaction as per MoRT&H specification clause No. 505 complete in all respects. (for small project upto 50 Crore.) |
| 7 | Providing and applying tack coat with VG-10 bitumen using bitumen pressure distributor @0.25 Kg/sqm on prepared bituminious surface cleaned with mechanical broom inchading supply of all materials, labour, T&P etc. required for proper completion of the work as per clause 503 of MORT&H specification and as per direction of the Engineer-in-Charge (for small project upto 50 Crore.) |
| 8 | Providing and applying primer coat with SS2 grade bitumen emulsion on prepared surface of granular Base including clearing of road surface and spraying primer at the rate of 0.70 kg/sqm using mechanical mens. including supply of all materials, labour, T&P etc. required for proper completion of the work as per clause 502 of MORT&H specification and as per direction of the Engineer-in-Charge (for small project upto 50 Crore.) |
| 9 | Providing and laying bituminous concrete (Gr-II) with 120 TPH batch type hot mix plant using crushed aggregates from approved quarry of specified grading, premixed with bituminous binder (VG-40) @ 5.40 per cent of mix and filler, transporting the hot mix to work site, laying with a hydrostatic paver finisher to the required grade, level and alignment, rolling with smooth wheeled, vibratory and tandem rollers to achieve the desired compaction as per MORTH specification clause No. 507 complete in all respects. |
| 10 | Road Marking with Hot Applied Thermoplastic Compound with Reflectorising Glass Beads on Bituminous Surface. Providing and laying of hot applied thermoplastic compound 2.5 mm thick including reflectorising glass beads @ 250 gms per sqm area, thickness of 2.5 mm is exclusive of surface applied glass beads as per IRC:35-2015 The finished surface to be level, uniform and free from streaks and holes. |
| 11 | Retro-reflectorised Traffic sign as per IRC-67-2012 Providing and fixing of retro-reflectorised cautionary, mandatory and informatory sign as per IRC :67-2012 made of high intensity grade sheeting type-IV vide clause 801.3, fixed over aluminium sheeting 1.5 mm thick supported on a mild steel angle iron post 75 mm x 75 mm x 6 mm firmly fixed to the ground by means of properly designed foundation with M 15 grade cement concrete 45 cm x 45 cm x 60 cm, 60 cm below ground level as per approved drawing. The Retro reflective sheeting shall be tested for a certificate of having the sheeting tested for coefficient of retro reflection, daytime colour and luminance, shrinkage, flexibility, liner removal, adhesion, impact resistance, specular gloss and fungus resistance, 3 years outdoor weathering and its having passed these tests shall be obtained from International/Government Laboratory/ Institute by the manufacturer of the sheeting and in case the certificate is obtained from international condition, it should also be obtained from Indian condition within 3 years of launching of product by the manufacture in abroad. Alternatively, a certificate conforming to ASTM Specification (D 4956-09) on artificial accelerated weathering requirements from a reputed laboratory in India can be accepted provisionally. In such a situation, the Employer / Client, if so desires, could seek for a performance guarantee which would be released after receipt of certificate meeting the requirement of three years outdoor weathering of the sheeting as per IRC 67:2012. Legends , letters , numerals and borders etc should be as per MoRTH specification No801.3.7 P xi) |
| 12 | i) 90 cm equllateral triangle with diffinitation plate size (20cm x 60cm) |
| 13 | i) 60 cm equllateral triangle with diffinitation plate (20cm x 60cm) |
| 14 | v) 80 cm x 60 mm rectangular with diffinitation plate (20cm x 60cm) |
| 15 | v) 60 cm x 45 mm rectangular with diffinitation plate (20cm x 60cm) |
| 16 | Direction and place Identification signs up to 0.90 sqm size Board Providing and erecting direction and place identification retro- reflectorised sign as per IRC-67 made of high intensity grade sheeting The Retro reflective sheeting shall be tested for a certificate of having the sheeting tested for coefficient of retro reflection, daytime colour and luminance, shrinkage, flexibility, liner removal, adhesion, impact resistance, specular gloss and fungus resistance, 3 years outdoor weathering and its having passed these tests shall be obtained from International/Government Laboratory/ Institute by the manufacturer of the sheeting and in case the certificate is obtained from international condition, it should also be obtained from Indian condition within 3 years of launching of product by the manufacture in abroad. Alternatively, a certificate conforming to ASTM Specification (D 495609) on artificial accelerated weathering requirements from a reputed laboratory in India can be accepted provisionally. In such a situation, the Employer / Client, if so desires, could seek for a performance guarantee which would be released after receipt of certificate meeting the requirement of three years outdoor weathering of the sheeting as per IRC 67:2012. Legends , letters , numerals and borders etc should be as per MoRTH specification No-801.3.7 . Sheet fixed over aluminium sheeting ,2 mm thick with area not exceeding 0.9 sqm.Supported on a mild steel single angle iron post 75x75x6 mm firmly fixed to the ground by means of property designed foundation with M-15 grade cement concrete 45x45x60 cm.,below ground level as per approved drawing, complete. |
| 17 | Direction and place Identification signs more than 0.90 sqm size Board Providing and erecting direction and place identification retro- reflectorised sign as per IRC-67 made of high intensity grade sheeting The Retro reflective sheeting shall be tested for a certificate of having the sheeting tested for coefficient of retro reflection, daytime colour and luminance, shrinkage, flexibility, liner removal, adhesion, impact resistance, specular gloss and fungus resistance, 3 years outdoor weathering and its having passed these tests shall be obtained from International/Government Laboratory/ Institute by the manufacturer of the sheeting and in case the certificate is obtained from international condition, it should also be obtained from Indian condition within 3 years of launching of product by the manufacture in abroad. Alternatively, a certificate conforming to ASTM Specification (D 495609) on artificial accelerated weathering requirements from a reputed laboratory in India can be accepted provisionally. In such a situation, the Employer / Client, if so desires, could seek for a performance guarantee which would be released after receipt of certificate meeting the requirement of three years outdoor weathering of the sheeting as per IRC 67:2012. Legends , letters , numerals and borders etc should be as per MoRTH specification No-801.3.7 . Sheet fixed over aluminium sheeting ,2 mm thick with area not exceeding 0.9 sqm.Supported on a mild steel single angle iron post 75x75x6 mm firmly fixed to the ground by means of property designed foundation with M-15 grade cement concrete 45x45x60 cm.,below ground level as per approved drawing, complete. |
| 18 | Providing and laying at or near ground level factory made kerb stone of M-25 grade cement concrete in position to the required line, level and curvature, j ointed with cement mortar 1:3 (1 cement: 3 coarse sand), including making j oints with or without grooves (thickness of j oints except at sharp curve shall not to more than 5mm), including making drainage opening wherever required complete etc. as per direction of Engineer-in-charge (length of finished kerb edging shall be measured for payment). (Precast C.C. kerb stone shall be approved by Engineer-in-charge). |
| 19 | Finishing walls with Acrylic Smooth exterior paint of required shade : New work (Two or more coat applied @ 1.67 ltr/10 sqm over and including priming coat of exterior primer applied @ 0.90 litre/10 sqm) |
| 20 | Reflective Raised Pavement Markers (Cat Eye/Road Stud) Supply and fixing of raised pavement marker with Made of Plastic body of RPM/ Road Stud shall be moulded from ASA (Acrylic Styrene Acrylonitrite) or HIPS (High-Imoact Polystyrene) or Acryloniitrite Butadien Styrene (ABS) or Any other suitable material approved by the Engineer. The Marker shall support a load of 13,635 kg tested in accordance with ASTM D4280.The Reflective panels shall consist of number of lenses contatning single or dual prismatic cubes capable of providing total internal reflection of the light entring the lens face. Lenses shall be mouled of methyl methecrylate conforming to ASTM D788 of equivalent. The slop or retro-reflecting surface shall preferably be 35+/-5 degree to base and the area of each retro -reflecting surface shall not be less than 13.00 sq.cm. the marker height shall not be less than 10 mm and shall not exceed 20 mm & Width shall not exceed 130 mm. The base of the marker shall be flat within 1.3 mm all road studs shall be legibly marked with the name , trade or other means of identification of the manufacture. epoxy installations, excess adhesive around the edge of the marker, excess adhesive on the pavement and adhesive on the exposed surfaces of the markers shall be immediately removed. The contractor shall submit a two year warranty for satisfactory field performance including stipulated retro-reflectance of the reflecting panel , to the Engineer . In addition , a two year warranty for satisfactory infield performance of the finished road marker shall also be given by the contractor who carries out the work of fixing of reflective road markers. In case the markers are displaced , damaged , get worn out or lose their reflectivity compared to stipulated standards , the contractor would be required to replace all such markers within 15 days of the intimation from the Engineer , at his own cost. The rate shall include all materials, labour, T&P, transportation, installation and incidentals all complete as per direction of the Engineer-in-Charge. RPM (Without shank) Please Enable Macros to View BoQ information |