| 1 | Earth work in excavatin in foundation in odinary soil i/clift up to 1.5 mt and lead up to 50 mt and i/c filling, watering and ramming of excavated earth into the trenches or into the spece between thebuilding and the sides of foundation trenches or into the plinth and removal and disposal of surplus earth etc all complete work. as per S.I. No. 251 |
| 2 | Earth work in embankment in B.C. soil, excavation tobe in the from of regular bits not exceeding1/2 m depth 1/C ramming and dressing the surface to required level & slops 1/C lift upto 1.50 m and Lead up to 8.0 km as per S.I. No. 253(6) |
| 3 | Laying of Coarse sand in Blanket coat I/C Supply of all materials labour T&P |
| 4 | Concrete with 4 cm gauge appd. Stone ballast Fine sand F.M. 1.25 and cement in the proportion of 12:6:1 I/C supplying of all material labour T&P |
| 5 | Laying C.C. road slab 15 cm thick consisting of 1:1/2:3 cement coarse sand F.M. 2.60 snd appd. 2 cm gauge stone grit, over preordered sub grade after its rectification and bringing it to proper camber and I/C S/o all materials. Labour and T&P etc. required for proper completion of work. finisheed to required template as directed by E/1 but excluding cost of materials requird for rectification of sub grade. |
| 6 | 1st class brick M-I50 in 1:4 cement & fine sand FM 1.25 mortar in foundation and plinth I/C cost of materials, labour and T&P required for proper completion of work. |
| 7 | Providing &Laying cement Concrete cc grade M-20 1:2:4 ( 1:2:4 cement ,c sand and stone grit ) cement concrete as per clause 802,803,1202,1203 1:2:4 as per Data Book Item No 11.4(III) |
| 8 | 12 mm thick plaster with cement and fine sand FM 1.25 in 1:4 over brick work minimum thickness not to be less than 10 mm thick including all cost of material, labour allround. |
| 9 | Making construction joint with maxphalt seet board including all material, labour and T&P etc. |
| 10 | Supplying and laying of 125 micron polythen including all material, labour and T&P etc. |
| 11 | Supplying andMixng of admixture in Top Coat 1;2;4 including all material, labour and T&P etc. M-130 |
| 12 | Providing &Laying Reinforced cement Concrete cc grade M-25 1:1.5:3 in super structure ( 1:1.5:3 cement ,c sand and stone grit ) cement concrete as per clause 800,1205.5 1:1.5:3 as per Data Book Item No 13.1(II) |
| 13 | Supplying ,Fitting and Placing M.S. Bar Reinforcement in Foundation com. Tech. Specification 1000and 1202 Sr.No.11.9 |
| 14 | Supply of sign board./ Graynite Stone with Piller including all material, labour and T&P etc. Please Enable Macros to View BoQ information |