| 1 | Laying Distribution system |
| 2 | 100.1.1:Excavating trenches of required width for pipes, cables, etc., including excavation for sockets, and dressing of sides, ramming of bottoms, depth up to 1.5m, including getting out the excavated soil, and then returning the soil as required, in layers not exceeding 20cm in depth, including consolidating each deposited layer by ramming, watering, etc., and disposing of surplus excavated soil as directed, within a lead of 50m, in all kinds of soil. |
| 3 | 100.1.5:Excavating trenches of required width for pipes, cables, etc., including excavation for sockets, and dressing of sides, ramming of bottoms, depth up to 1.5m, including getting out the excavated soil, and then returning the soil as required, in layers not exceeding 20cm in depth, including consolidating each deposited layer by ramming, watering, etc., and disposing of surplus excavated soil as directed, within a lead of 50 m, in Ordinary Rock. |
| 4 | 100.2.7:Excavating trenches of required width for pipes, cables, etc., including excavation for sockets, and dressing of sides, ramming of bottoms, depth up to 1.5m, including getting out the excavated soil, and then returning the soil as required, in layers not exceeding 20cm in depth, including consolidating each deposited layer by ramming, watering, etc., and disposing of surplus excavated soil as directed, within a lead of 50m, in Medium Rock where Blasting is Prohibited. |
| 5 | 15.2.2:Demolishing cement concrete manually / by mechanical means including disposal of material within 50 metres lead as per direction of Engineer - in-Charge.Nominal concrete 1:4:8 or leaner mix ( including equivalent design mix) |
| 6 | 100.9.8:Laying uPVC pipes of class 2 to class 6 and specials, lowering to the trenches already made, placing in position aligning the pipeline to the lines and levels and jointing the pipes and specials with solvent cement and testing the pipeline with water to the required test pressure (excluding cost of pipes and specials): 90 mm nominal outside diameter pipes. |
| 7 | 18.12.8:Providing and fixing G.I. pipes complete with G.I fittings including trenching and refilling etc. External work80 mm dia nominal bore |
| 8 | 100.31.2.1:Conveying and fixing C.I. sluice valves (with cap) by providing bolts, nuts, rubber insertions etc., complete, but excluding the cost of the valve (tail pieces, if required, will be paid separately): 80mm diameter, Class II. |
| 9 | 4.1.3:Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:2:4 (cement : 2 coarse sand (zone-III)derived from natural sources : 4 graded stone aggregate 20 mm nominal size derived from natural sources) |
| 10 | OD244155/2022-2023:Interconnection of newly laid PVC pipe with existing AC/PVC pipe including cost of specials complete as per direction of Dept.officers. |
| 11 | OD246190/2022-2023:160 mm PVC pipe for Valve protection |
| 12 | OD247655/2022-2023:Supplying and fitting of 90 mm PVC End Cap in position as per direction. |
| 13 | Cost of Materials |
| 14 | 100.98.223:Supply of PVC Pipe, 8kg/cm2, 90mm Dia. |
| 15 | 100.98.457:Supply of CI Double Flanged Sluice Valve Conforming to IS 14846 - 2000, Sluice Valve with Cap PN 1.6, Size 80mm. |
| 16 | Providing water connection |
| 17 | 15.2.1:Demolishing cement concrete manually / by mechanical means including disposal of material within 50 metres lead as per direction of Engineer - in-Charge.Nominal concrete 1:3:6 or richer mix (i/c equivalent design mix) |
| 18 | 100.60.1.1.2:Providing 15mm (1/2 inch) house connection with 15mm (1/2 inch) water meter from existing PVC / HDPE mains up to 110 mm dia., up to a length of 5 m using 20mm Indian Standard Class 6 uPVC pipe and uPVC / GM / Brass specials viz. brass ferrule, GM full way wheel valve, Elbow, MTA, FTA, couplers, PVC Service Saddle of suitable size etc. and connecting with the mains, testing the joints etc. complete including trenching and refilling in all kinds of soil up to a depth of 1.50m for main line tracing and trench of average cross section 0.3m x 0.75m for laying connection pipe and service pipe, fixing water meter, lighting, watching, providing caution boards, traffic control etc. complete including cost of materials, hire for tools, cost of consumables and labour charges, including the cost of tested Class B Multijet water meter with ISI mark and weather resistant PP / PE meter box of minimum size 300mm x 200mm x 150mm, but excluding charges for cutting the concrete / tarred / bituminous roads etc, and as per the direction of the departmental officers. |
| 19 | 100.60.3.1.1:Providing additional length of house connection pipe using 20mm Indian Standard Class 6 uPVC pipe and specials and testing the joints etc., by trenching and refilling in all kinds of soil with trench of average cross section 0.3m x 0.75m for laying of connection pipe and service pipe, lighting, watching, providing caution boards, traffic control etc., including cost of materials, hire for tools, cost of consumables and labour charges etc. complete, but excluding the cost of cutting of concrete / tarred / bituminous roads etc., and as per the directions of the department officers |
| 20 | OD244106/2022-2023:Providing and fixing vertical stand post using 63 mm 6 kg PVC pipe for FHTCs , including necessary earth work excavation for fixing stand post etc as per direction |
| 21 | 100.60.10.4.1:Providing 20mm (1/2 inch) PVC Air Valve in the water meter assembly for 15mm connection, using 20mm Indian Standard Class 6 uPVC pipes and specials including cost of materials, consumables, hire for tools and labour charges etc. complete and as per the directions of the department officers. |
| 22 | 100.60.12.3.1:Providing 15mm PVC Tap in the water meter assembly for 15mm connection, using 20mm Indian Standard Class 6 uPVC pipes and specials including cost of materials, consumables, hire charges for tools and labour charges etc. complete and as per the direction of departmental officers. |
| 23 | 4.1.3:Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:2:4 (cement : 2 coarse sand (zone-III)derived from natural sources : 4 graded stone aggregate 20 mm nominal size derived from natural sources) Please Enable Macros to View BoQ information |