| 1 | Construction of embankment with approved material obtained from availble land as permitted and approved by Engineer-in-Charge and as per Technical Specitaion Clause 301.3.4.1, with all lifts and leads, spreading, grading to required slope and compacting to meet requirement of Tables 300.1and 300.2 as per Technical Specification clause 301.5 |
| 2 | Plain cement concrement 1:3:6 nominal mix in foundation with crushed aggregate 40 mm nominal size mechanically mixed,placed in foundation and compected by vibration including curing for 14 days. |
| 3 | Brick masonry work in 1:3 cement mortar in foundation complete excluding pointing and plastering as per drawing and technical speficiations clauses 600, 1202 & 1203 |
| 4 | Providing and laying reinforced cement concrete M 20 grade in superstructure as per drawing and technical specifications clauses 800, 1205.4 and 1205.5 |
| 5 | Construction of granular sub-base by providing well graded material, spreading in uniform layers with motor grader on prepared surface, mixing by mix in place method with rotavator at OMC, and compacting with smooth wheel roller to achieve the desired density, complete as per Technical Specification Clause 401. [MORD] |
| 6 | Providing, Laying, spreading and compacting stone aggregates of 63-45 mm size to water bound macadam specification including spreading in uniform thickness , hand packing ,rolling with Smooth wheel roller 80-100 KN in stages to proper grade and camber ,applying and brooming ,Stone screening,binding materials to fill up theinterstices of coarse aggregate ,watering and compacting to the required density as per Technical Specification Clause 405. [MORD] |
| 7 | Providing and Laying of Interlocking Concrete Block Pavements having thickness 80 mm as per drawings and Technical Specification Clause 1504. |
| 8 | Earthwork in excavation for structures as per drawing and technical specifications clause 305.1 including setting out, construction of shoring and bracing, removal of stumps and other deleterious materials and disposal upto a lead of 50 m, dressing of sides and bottom and backfilling in trenches with excavated suitable material. |
| 9 | Boring with 100 mm dia casing pipe for dewatering including cost of pipes , other materials, labour charges etc. complete. |
| 10 | Dewatering the ground water for trenches with hire, operational & fuel charges of pump with oprater complete. |
| 11 | Plain cement concrete 1:3:6 nominal mix in foundation with crushed aggregate 40 mm nominal size mechanically mixed, placed in foundation and compacted by vibration including curing for 14 days. |
| 12 | Brick masonry work in 1:3 cement mortar in foundation complete excluding pointing and plastering, as per drawing and technical specification Clauses 600, 1202 & 1203. |
| 13 | Providing and laying reinforced cement concrete pipe NP3 for cause way including fixing collar with cement mortar 1:2 but excluding excavation, protection works, backfilling, concrete and masonry works in head walls and parapets. As per clauses1106. |
| 14 | Pointing with cement mortar (1:3) on brick work as per drawing and technical specification Clauses 613.3 & 1204 |
| 15 | Colour washing 2 coat. As per SI No 675 |
| 16 | Sand filling in plingth including supply of necessary quantity of sand from a distance not exceeding 8 km. (5 miles) from the site of work and including watering, dressing etc. Rate to include cost of all materials. Labour and T&P etc required for proper completion of the work. |
| 17 | Construction of un-reinforced, dowel jointed, plain cement concrete pavement over a prepared sub base with 43 grade cement @ 400 kg per cum, coarse and fine aggregate conforming to IS 383, maximum size of coarse aggregate not exceeding 25 mm, mixed spread, compacted and finished in a continuous operation including provision of contraction, expansion, construction and longitudinal joints, joint filler, separation membrane, sealant primer as per approved, curing compound, finishing to lines and grades as per drawing 14 days curing. |
| 18 | Supplying fitting and placing HYSD bar reinforcement in superstructure complete as per drawing and Technical Specifications clauses 1002, 1010 and 1202 |
| 19 | Plastering with cement mortar (1:4) 15 mm thick on brickwork in substructure/ superstracutre as per technical specification clauses 613.4 & 1204 Please Enable Macros to View BoQ information |