| 1 | Loading, unloading and safe carriage of following materials from Store Centre, Gorakhpur to JE dump Store and JE dump Store to work site with proper stacking :- |
| 2 | 11/0.4 KV T/F 63 KVA |
| 3 | 11/0.4 KV T/F 100 KVA |
| 4 | ST Pole 11 mtr long |
| 5 | PCC Pole 8.5 mtr long |
| 6 | LT ABC (3X120+1X95+1X16)Sq Mm |
| 7 | X-Arm Ms Angle 65X65X6 Mm V-Type |
| 8 | 11 KV Dropper Angle |
| 9 | 11 KV Top Channel |
| 10 | Top Channel for TF Base |
| 11 | LT PVC Cable 1X400 Sq Mm |
| 12 | 11 KV Fuse set |
| 13 | 11 KV Polymeric Pin Insulator |
| 14 | 11 KV Polymeric Disc Insulator |
| 15 | ACSR Weasel Conductor |
| 16 | ACSR Dog Conductor |
| 17 | T-Off Channel |
| 18 | SS Base Channel |
| 19 | LT PVC Cable AI 1x240sq mm |
| 20 | Earthing complete |
| 21 | 11 KV Stay Set At Angle Location |
| 22 | 11 KV Disc Fitting |
| 23 | 11 KV TPMO Set |
| 24 | Supply of following material/fitting complete in all respect :- |
| 25 | Stone Pad |
| 26 | 11 kV Lightening Arrestor |
| 27 | GI Wire Barbed |
| 28 | Red oxide paint |
| 29 | Aluminium paint |
| 30 | Aluminium Lugs |
| 31 | Clamp for LT T-off with bolts & nuts |
| 32 | Copper L-piece 62x225x12 mm (LS) |
| 33 | Guarding Angle |
| 34 | Guarding Wire |
| 35 | LT Distribution Box with Clamp |
| 36 | LT Shackle insulator |
| 37 | Danger Board With Clamp |
| 38 | Number Plate |
| 39 | LT Clamps |
| 40 | PG Clamps |
| 41 | Insulated Dead end clamp with I hook |
| 42 | Eye hook |
| 43 | Suspension clamp with I hook (Insulated) |
| 44 | LT Insulated Piercing connector |
| 45 | LT PVC Cable 1X35 Sq Mm. for energizing D.B |
| 46 | F-Bracket |
| 47 | Holding Clamp etc with nuts & bolts for cross arm top channel dropper channel fuse set etc |
| 48 | GI Nuts & bolts of different sizes |
| 49 | The excavation of 2 No foundation pit of size 750mmX450mm and having depth of 1/6th of the full length of the pole. Fabrication & erection of double Pole with fixing of necessary clamps & accessories (Top Channel, Dropper Angle etc.) as per required. All required materials such as Holding clamp/STP clamp, Danger Board with Barbed wire, Number Plate, Nuts & Bolts off size etc will be provided by the contractor.Grouting of Pole in cc 1:4:8 (Cement, sand & 40 mm brick ballast), Grouting will be done in the block of size 450x450 mm x depth upto ground level and backfilling of pits with mud completely and leveling etc (Material provided by Contractor).Making plinth around Pole height 300 mm above ground level with top 100 mm is kept tapered so that No rainwater gets accumulated on the top. All work will be done as per RESPO Norms & relevent IS Specification. |
| 50 | The excavation of 1 No foundation pit of size 750mmX450mm and having depth of 1/6th of the full length of the pole. Fabrication & erection of Single Pole with fixing of necessary clamps & accessories (Top Channel, Dropper Angle etc.) as per required. All required materials such as Holding clamp/STP/PCC clamp, Danger Board with Barbed wire, Number Plate, Nuts & Bolts off size etc will be provided by the contractor.Grouting of Pole in cc 1:4:8 (Cement, sand & 40 mm brick ballast), Grouting will be done in the block of size 450x450 mm x depth upto ground level and backfilling of pits with mud completely and leveling etc (Material provided by Contractor).Making plinth around Pole height 300 mm above ground level with top 100 mm is kept tapered so that No rainwater gets accumulated on the top. All work will be done as per RESPO Norms & relevent IS Specification. |
| 51 | Painting of Pole by double coating Aluminum & Red oxide paint. Paint will be provided by contractor |
| 52 | Earthing of ST Pole by MS earthing Rod & 6 SWG earthing Wire as per RESPO Norms. |
| 53 | Erection of Danger Board with Barbed wire & Number Plates |
| 54 | Fabrication, errection, commissioning & Testing of 63 kVA/100 kVA T/F on Double Pole with all accessories including make its LT and HT connection. All necessary materials such as Holding clamp, Al.Lugs (Confirming to IS 8309), L Piece Clamp, Nuts & Bolts will be supplied by the Contractor. |
| 55 | Erection of TPMO & Fuse set |
| 56 | Laying, stringing, sagging, binding and jumpering of ACSR Weasel/Dog conductor for LT/HT Line with fixing of V Cross Arm, LT Clamps/other clamps, F Bracket, Shackle insulator and nuts&bolts off size as per required. |
| 57 | Laying & sagging of LT ABC (3X120+1X95+1X16) Sq.mm. Cable of LT Line with fixing of Distribution Box with Clamp, Insulated Dead end clamp with I hook, Suspension clamp with I hook(Insulated), LT insulated Piercing connector, XLPE 1X35 Sq.mm. Al. cable for enerzing DB, XLPE 1X16 Sq.mm. Al. cable for giving connection to Street Light and nuts&bolts off size by the contractor. |
| 58 | Pipe earthing of Transformer (Body+Neutral) as per IS Code 3043 - 1987 specification (Materials will be provided by contractor) |
| 59 | Shifting along with Testing, Commissioning, Making HT/LT Connection of 400 kVA Transformer |
| 60 | Construction of T/F plinth of size 2x2x1.2 M with the help of first class brick & 9\\" masonary in the ratio 1:4 cement & sand coarse. Filling the structure completely and plastering outer surface as per RESPO norms. Top of the plinth covered with 4\\" RCC Slab of ratio 1:1.5:3 (Cement, sand & concrete) grouting with 2 No ISMC size 125X65X6 MM (confirming to IS 808:1989) of 2000 mm long for resting. All required materials will be provided by the contractor. |
| 61 | Grill fencing of 11/0.4 KV S/S shall be made of rectangular of size (13X11X7) Ft as per site requirement with fabrication 50X50X5 mm angel the frame is also have 1 No Horizontal runner of MS flat 40x5 welded in middle to support of grill, having a gate on road side must have provision of locking arrangement. The work is including painting of fencing as per norms. Work will be done as per RESPO specification. |
| 62 | Erection of 11 kV Lightening Arrestor |
| 63 | Guarding of overhead Line |
| 64 | Supply, Complete installation of 2 No Henley-Type Tailless Units, 300 AMP, in each box. The installation will include the use of 3 copper bus bar strips, each sized 500x50x5 mm (one strip per tailless unit), and 1 aluminum bus bar strip sized 500x50x5 mm as per drawing enclosed. The work will involve the use of LT XLPE. cable, LT crimping lugs, nuts, bolts, and other materials as per site requirements on an 11/0.4 KV distribution transformer. (Note: Only cable will be provided by the Department.) |
| 65 | Supply, fabrication, erection of LT Pillar Box for Tailless Unit after making Plinth of Height 300 mm above ground level. LT Pillar Box Size- 1650X1050X520 mm with Gate and Proper Locking arrangement (Canopy of 15 Degree Slope) as per drawing enclosed . All work will be done as per RESSPO Norms & relevent IS Specification. |
| 66 | Erection of Stay Complete |
| 67 | Dismantling of following Line materials and safe loading, unloading and carraige of dismantled material from work site to departmental store |
| 68 | 25 kVA Transformer |
| 69 | STP pole 11/9 meter long |
| 70 | Conductor |
| 71 | ABC Conductor Please Enable Macros to View BoQ information |