| 1 | Earth work in excavation by mechanical means (Hydraulic excavator) / manual means over areas (exceeding 30cm in depth, 1.5m in width as well as 10 sqm on plan) including getting out and disposal of excavated earth, lead up to 50m and lift up to 1.5m,as directed by Engineer-in-Charge., All kinds of soil |
| 2 | Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level :, 1:4:8 (1 Cement : 4 coarse sand (zone-III) derived from natural sources : 8 graded stone aggregate 40 mm nominal size derived from natural sources). |
| 3 | Centering and shuttering including strutting, propping etc. and removal of form work for :, Foundations, footings, bases for columns. |
| 4 | Mild steel or iron work in plain work such as in R.C.C. or R.B. (when not included in an over all rates ) including bending for proper completion of the work and including supply of steel and its wastage , bends, hooks and authorised overlaps shall be measured up to floor two level |
| 5 | Providing and fixing double scaffolding system (cup lock type) on the exterior side, up to seven story height made with 40 mm dia M.S. tube 1.5 m centre to centre, horizontal & vertical tubes joining with cup & lock system with M.S. tubes, M.S. tube challies, M.S. clamps and M.S. staircase system in the scaffolding for working platform etc. and maintaining it in a serviceable condition for the required duration as approved and removing it there after. The scaffolding system shall be stiffened with bracings, runners, connection with the building etc wherever required for inspection of work at required locations with essential safety features for the workmen etc. complete as per directions and approval of Engineer-in-charge. The elevational area of the scaffolding shall be measured for payment purpose. The payment will be made once irrespective of duration of scaffolding. |
| 6 | Repairs to plaster of thickness 12 mm to 20 mm in patches of area 2.5 sq.meters and under, including cutting the patch in proper shape, raking out joints and preparing and plastering the surface of the walls complete, including disposal of rubbish to the dumping ground, all complete as per direction of Engineer-in-Charge. |
| 7 | Providing & fixing of Concrete drain cover Concrete Drain Covers Sandstone Colour 550X750X50MM Ultra High Performance Pigmented Concrete With Steel Fiber Reinforcement Load Capacity Suitable for 40 Tonne Vehicle Passing Bayferrox Lanxess Fe203 Colour Index 77491.0000 etc all complete in direction of engineer in charge |
| 8 | \\"Providing and erecting 2.00 metre high temporary barricading at site; each panel of size 2.50mx2.00m made of 40x40x6mm angle iron or 50x50x3mm hollow MS tube posts/horizontal members/bracings covered with 1.63mm thick MS sheet. The sheet shall be fixed with 30x5mm MS flat by suitable welding/riveting. The panels shall be made so that gap of 50cm above the ground is available making overall height as 2.5m. MS channel ISLC 75 @ 5.70 kg/m, 50cm long shall be provided at the bottom having oval shaped holes of size 50x25mm at both ends with 50cm long MS angle 40x40x6mm bracing. Suitable arrangement shall be made to fix the barricading to avoid from overturning by providing 250mm long expansion fasteners at both ends. The work shall be executed as per drawing/direction of Engineer-in-Charge which includes writing and painting, arrangement for traffic diversion such as traffic signals during construction at site for day and night, glow lamps, reflective signs, marking, flags, caution tape as directed by the Engineer-in-Charge. The barricading provided shall be retained in position at site continuously i/c shifting of barricading from one location to another location as many times as required during the execution of the entire work till its completion. Rate include its maintenance for damages, painting, all incidentals, labour materials, equipments and works required to execute the job. The barricading shall not be removed without prior approval of Engineerin- Charge. (Note :- One time payment shall be made for providing barricading from start of work till completion of work i/c shifting. The barricading provided shall remain to be the property of the contractor on completion of the work).\\" |
| 9 | S/L of following cable \\"Al\\" conductor P.V.C. insulated armoured served sheathed cable 1100V grade at a depth of 750mm. Below ground level over a cushion of 75mm with DWC Pipe approved make UPPPCL as per direction of E/I. complete in all respects. 501/2018. Approved Makes:- Gloster/Polycab/KEI/SCI/Havells PWD SOR 501 @343.00 |
| 10 | Reinforced cement concrete work in walls (any thickness), including attached pilasters, buttresses, plinth and string courses, fillets, columns, pillars, piers, abutments, posts and struts etc. above plinth level up to floor five level, excluding cost of centering, shuttering, finishing and reinforcement :, 1:1.5:3 (1 cement : 1.5 coarse sand(zone-III)derived from natural sources : 3 graded stone aggregate 20 mm nominal size derived from natural sources) |
| 11 | Brick work with common burnt clay F.P.S. (non modular) bricks of class designation 7.5 in foundation and plinth in:, Cement mortar 1:4 (1 cement : 4 coarse sand) |
| 12 | Half brick masonry with common burnt clay F.P.S. (non modular) bricks of class designation 7.5 in superstructure above plinth level up to floor V level., Cement mortar 1:3 (1 cement :3 coarse sand) |
| 13 | 12 mm cement plaster of mix :, 1:4 (1 cement: 4 coarse sand) |
| 14 | Providing and applying white cement based putty of average thickness 1 mm, of approved brand and manufacturer, over the plastered wall surface to prepare the surface even and smooth complete. |
| 15 | Finishing walls with Premium Acrylic Smooth exterior paint with Silicone additives of required shade:, New work (Two or more coats applied @ 1.43 ltr/10 sqm over and including priming coat of exterior primer applied @ 0.90 litre/10 sqm) |
| 16 | The rectangular metal drain covers made of 6mm thick MS flat bar with CNC cutting design often finished with a powder coating or matte paint to protect against corrosion while highlighting the contrast between the fluid cast iron patterns and the rigid steel frame. The pattern features a repeating sunburst or fan-like motif. It consists of radial slots emanating from solid circular centers. The intricate laser-cut slots serve a dual purpose: they function as drainage holes to let water pass through while being narrow enough to prevent large debris (or pedestrian heels) from getting stuck. The Cost Includes CNC MS Fabrication, Transportation, and all other labour cost are included. Make in or Equivalent. |
| 17 | Supplying and installing of Branding and Glowing Signage Board over Aluminium Composite Panel incuding the cost of printing and designing along with graphics and illustrations in font and language of approved size, with acrylic sheet work and light work, including the cost of suspended frame work from the existing wall. Also including cost of providing and fixing of fasteners complete in all respects as per Architect in charge. |
| 18 | Polymer-based PU coating epoxy for footpaths is a high-performance, multi-layered surfacing system designed to combine the mechanical strength of epoxy with the UV stability and flexibility of polyurethane (PU). This system is typically used to create a seamless, non-slip, and aesthetically pleasing surface that can withstand heavy pedestrian traffic, weathering, and thermal expansion. |
| 19 | \\"Supply & Fixing of floral & ornate cast iron bollard and ornamental chain as per design casted dise grinded & pin grinded for smooth surface finish with proepr removeal of casting, suitably spray preminered dried and then base surfacer caosted & subsequently spray painted with premium quality high glass enamel paint of colour approved by enginner-in-charge. Including cast of fastner. etc. (LDA Approved Item) \\" |
| 20 | \\"Decorative Railing made of cast iron which provide a classic and timeless architectural appeal. These ornamental sections are securely framed by a 6mm thick MS flat bar border, creating a sleek, clean-edged perimeter that transitions the decorative core into a modern, structured silhouette. The entire assembly is anchored by vertical MS poles on either side, providing the necessary lateral stability and heavy-duty support required for safety. This combination of materials ensures a high-strength barrier with a slim profile, often finished with a powder coating or matte paint to protect against corrosion while highlighting the contrast between the fluid cast iron patterns and the rigid steel frame. The Cost Includes Transportation, and all other labour cost are included. Make in or Equivalent. |
| 21 | LOGO PILLAR is a rectangular, freestanding pillar or bollard, likely functioning as an outdoor light fixture or decorative boundary marker. It features a dark brown metal casing of MS flat bar 5mm of thickness with intricate CNC cutting designs, backed by a translucent Acrylic white panel intended to diffuse light, often finished with a powder coating or matte paint to protect against corrosion. The full name \\"LUCKNOW DEVELOPMENT AUTHORITY\\" is engraved or cut out in an arc along the bottom half of the circle on one side and other side \\"ANDAAZ E AWADH\\" logo is engraved. The Cost Includes CNC MS Fabrication,Transportation, and all other labour cost are included. Make in or Equivalent.(1200MM) |
| 22 | Stone work (machine cut edges) for wall lining etc. (veneer work) upto 10 metre height, backing filled with a grout of average 12 mm thick cement mortar 1:3 (1 cement : 3 coarse sand) including pointing in white cement mortar 1:2 (1 white cement : 2 stone dust) with an admixture of pigment matching the stone shade : (To be secured to the backing and the sides by means of cramps and pins which shall be paid for separately) :, Red sand stone - Exposed face machine cut and table rubbed with rough backing., 40 mm thick |
| 23 | Providing and fixing of Terrakota Jali Size 205x205x62.5 mm etc all complete in direction of engineer in charge S.R N.S.I |
| 24 | Providing & fixing of Dustbin made in mild steel frame with painting & polish and frame wooden member fixed in m.s. frame including painting polishing as per drawing & design all complete in direction of engincer in charge. PSR @16500.00 |
| 25 | Providing and fixing stainless steel ( Grade 304) railing made of Hollow tubes, channels, plates etc., including welding, grinding, buffing, polishing and making curvature (wherever required) and fitting the same with necessary stainless steel nuts and bolts complete, i/c fixing the railing with necessary accessories & stainless steel dash fasteners , stainless steel bolts etc., of required size, on the top of the floor or the side of waist slab with suitable arrangement as per approval of Engineer-in-charge, (for payment purpose only weight of stainless steel members shall be considered excluding fixing accessories such as nuts, bolts, fasteners etc.). (PWD SOR 2020-21 DAR No. 10.28) Providing and fixing stainless steel ( Grade 304) railing made of Hollow tubes, channels, plates etc., including welding, grinding, buffing, polishing and making curvature (wherever required) and fitting the same with necessary stainless steel nuts and bolts complete, i/c fixing the railing with necessary accessories & stainless steel dash fasteners , stainless steel bolts etc., of required size, on the top of the floor or the side of waist slab with suitable arrangement as per approval of Engineer-in-charge, (for payment purpose only weight of stainless steel members shall be considered excluding fixing accessories such as nuts, bolts, fasteners etc.). (PWD SOR 2020-21 DAR No. 10.28) |
| 26 | 8 Layer Acryflex Synthetic System Paint (Lda Approved Rate) |
| 27 | Extra for CNC design & cutting on MS/ SS Sheet of thickness less then 3 mm thickness |
| 28 | This is a heritage-style, Ornamental cast iron street light pole, designed with dual-tone \\"Antique Gold\\" finish (gold highlights over a dark bronze/black base) to accentuate the intricate relief work. The pole stands on a heavy, robust pedestal base in shape. The panels of the base feature high-relief carvings. The 6-meter shaft is fluted (vertical grooves running along the length), a classic architectural feature that adds elegance and slender appearance. Lighting Configuration; Side A (Roadway Light - 90W): The main arm extends outwards to hold a large, pendant-style lantern. The housing is decorative but contains a modern LED module for high-intensity street lighting. Side B (Pedestrian Light - 60W): While less visible in the primary angle, the opposite side is designed to hold a smaller matching lantern or bracket for pedestrian pathway lighting, providing a softer 60W output. The Cost Includes Transportation, and all other labour cost are included. Make in or Equivalent. |
| 29 | Demolishing cement concrete manually/ by mechanical means including disposal of material within 50 metres lead as per direction of Engineer - in - charge., Nominal concrete 1:4:8 or leaner mix (i/c equivalent design mix) |
| 30 | Demolishing cement concrete manually/ by mechanical means including disposal of material within 50 metres lead as per direction of Engineer - in - charge., Nominal concrete 1:3:6 or richer mix (i/c equivalent design mix) |
| 31 | Demolishing brick work manually/ by mechanical means including stacking of serviceable material and disposal of unserviceable material within 50 metres lead as per direction of Engineer-in-charge.., Demolishing brick work manually/ by mechanical means including stacking of serviceable material and disposal of unserviceable material within 50 metres lead as per direction of Engineer-in-charge. In cement mortar |
| 32 | Dismantling tile work in floors and roofs laid in cement mortar including stacking material within 50 metres lead., Dismantling tile work in floors and roofs laid in cement mortar including stacking material within 50 metres lead. For thickness of tiles 10 mm to 25 mm |
| 33 | Dismantling manually/ by mechanical means including stacking of serviceable material and disposal of unserviceable material within 50 metres lead as per direction of Engineer-in-charge :, Bituminous road |
| 34 | Dismantling steel work in built up sections in angles, tees, flats and channels including all gusset plates, bolts, nuts, cutting rivets, welding etc. including dismembering and stacking within 50 metres lead. |
| 35 | Providing and laying non-pressure NP2 class (light duty) R.C.C. pipes with collars jointed with stiff mixture of cement mortar in the proportion of 1:2 (1 cement : 2 fine sand) including testing of joints etc. complete :, 250 mm dia. R.C.C. pipe |
| 36 | Kota stone slab flooring over 20 mm (average) thick base laid over and jointed with grey cement slurry mixed with pigment to match the shade of the slab including rubbing and polishing complete with base of cement mortar 1 : 4 (1 cement : 4 coarse sand) :, Kota stone slab flooring over 20 mm (average) thick base laid over and jointed with grey cement slurry mixed with pigment to match the shade of the slab including rubbing and polishing complete with base of cement mortar 1 : 4 (1 cement : 4 coarse sand) 25 mm thick. |
| 37 | Providing and laying Polished Granite stone flooring in required design and patterns, in linear as well as curvilinear portions of the building all complete as per the architectural drawings with 18 mm thick stone slab over 20 mm (average) thick base of cement mortar 1:4 (1 cement : 4 coarse sand) laid and jointed with cement slurry and pointing with white cement slurry admixed with pigment of matching shade including rubbing , curing and polishing etc. all complete as specified and as directed by the Engineer-in-Charge., Polished Granite stone slab jet Black, Cherry Red, Elite Brown, Cat Eye or equivalent Please Enable Macros to View BoQ information |