| 1 | Part (A) Box Culvert |
| 2 | Earth work in excavation of foundation of structures as per drawing and technical specification, including setting out, construction of shoring and bracing, removal of stumps and other deleterious matter, dressing of sides and bottom and backfilling with approved material. as per MORT&H specification No 12.1& 304 and including all material, labour, labour cess, T&P royalty, all tasex etc. complete as per diretcion by i-in-c but excluding G.S.T. |
| 3 | Sand Filling complete as per Drawing and Technical Specifications. 12.21 1207 and including all material, labour, labour cess, T&P royalty, all tasex etc. complete as per diretcion by i-in-c but excluding G.S.T. |
| 4 | Plain Cement Concrete in Open Foundation complete as per Drawing and Technical Specifications. (M-15) and including all material, labour, labour cess, T&P royalty, all tasex etc. complete as per diretcion by i-in-c but excluding G.S.T. |
| 5 | Cement Concrete M-25 with stone aggregate and viberated in foundation upto depth 1.5m below ground level and 1.5m above ground level and including all material, labour, labour cess, T&P royalty, all tasex etc. complete as per diretcion by i-in-c but excluding G.S.T. |
| 6 | Reinforced Cement Concrete in Open Foundation complete as per Drawing and Technical Specifications. (RCC Grade M30) 12.8 G ii and including all material, labour, labour cess, T&P royalty, all tasex etc. complete as per diretcion by i-in-c but excluding G.S.T. |
| 7 | Supplying, fitting and placing HYSD bar reinforcement in super-structure complete as per drawing and technical specifications and including all material, labour, labour cess, T&P royalty, all tasex etc. complete as per diretcion by i-in-c but excluding G.S.T. |
| 8 | Painting with synthetic enamel paint of approved brand and manufacture to give an even shade : Two or more coats on new work DSR 13.61.1 and including all material, labour, labour cess, T&P royalty, all tasex etc. complete as per diretcion by i-in-c but excluding G.S.T. |
| 9 | Providing and laying Cement concrete Wearing Coat M-30 grade including reinforcement complete as per drawing and as per Technical Specifications No. 2702 and including all material, labour, labour cess, T&P royalty, all tasex etc. complete as per diretcion by i-in-c but excluding G.S.T. |
| 10 | Providing and filling joint sealing compound as per drawings and technical specifications with coarse sand and 6 per cent bitumen by weight and including all material, labour, labour cess, T&P royalty, all tasex etc. complete as per diretcion by i-in-c but excluding G.S.T. |
| 11 | Part (B) Protection Work |
| 12 | Earth work in excavation of foundation of structures as per drawing and technical specification, including setting out, construction of shoring and bracing, removal of stumps and other deleterious matter, dressing of sides and bottom and backfilling with approved material. as per MORT&H specification No 12.1& 304 and including all material, labour, labour cess, T&P royalty, all tasex etc. complete as per diretcion by i-in-c but excluding G.S.T. |
| 13 | Plain Cement Concrete in Open Foundation complete as per Drawing and Technical Specifications. (M-15) and including all material, labour, labour cess, T&P royalty, all tasex etc. complete as per diretcion by i-in-c but excluding G.S.T. |
| 14 | Cement Concrete M-25 with stone aggregate and viberated in foundation upto depth 1.5m below ground level and 1.5m above ground level and including all material, labour, labour cess, T&P royalty, all tasex etc. complete as per diretcion by i-in-c but e |
| 15 | Reinforced Cement Concrete in Open Foundation complete as per Drawing and Technical Specifications. (RCC Grade M30) 12.8 G ii and including all material, labour, labour cess, T&P royalty, all tasex etc. complete as per diretcion by i-in-c but excluding G |
| 16 | Supplying, fitting and placing HYSD bar reinforcement in super-structure complete as per drawing and technical specifications and including all material, labour, labour cess, T&P royalty, all tasex etc. complete as per diretcion by i-in-c but excluding G.S.T. |
| 17 | Providing and laying filter material underneath pitching in slopes complete as per drawing and technical specificatoin and including all material, labour, labour cess, T&P royalty, all tasex etc. complete as per diretcion by i-in-c but excluding G.S.T. |
| 18 | Providing and laying boulder apron for bed protection with stone boulders of minimum size and weight (25kg) laid dry complete as per drawing and technical specification and including all material, labour, labour cess, T&P royalty, all tasex etc. complete as per diretcion by i-in-c but excluding G.S.T. |
| 19 | Providing weep holes in Brick masonry/Plain/ Reinforced concrete abutment, wing wall/ return wall with 100 mm dia AC pipe, extending through the full width of the structure with slope of 1V :20H towards drawing foce. Complete as per drawing and Technical Specifications and including all material, labour, labour cess, T&P royalty, all tasex etc. complete as per diretcion by i-in-c but excluding G.S.T. |
| 20 | Daiversion |
| 21 | Construction of embankment with approved material obtained from borow pits with all lifts and leads trancporting 3 km up to sites, spreading, grading to required slope and compected to meet requirement of table 300.2 and including all material, labour, labour cess, T&P royalty, all tasex etc. complete as per diretcion by i-in-c but excluding G.S.T. |
| 22 | Laying brick soling layer on prepared sub-grade with brick on end edging according to lines, graded and cross-section shown on the drawing filling joints with sand and earth, spreading 25 mm thick layer of earth over brick soling, watering and rolliing the same with three wheeled road roller 80-100 kN as per Technical Specification Clause 412 and including all material, labour, labour cess, T&P royalty, all tasex etc. complete as per diretcion by i-in-c but excluding G.S.T. |
| 23 | Supply and fixing of 1000mm dia NP-3 hume pipe and including all material, labour, labour cess, T&P royalty, all tasex etc. complete as per diretcion by i-in-c but excluding G.S.T. |
| 24 | Approach Road (Part D) |
| 25 | Construction of subgrade and earthenshoulders with approved material obtained from borow pits with all lifts and leads trancporting to sites, spreading, grading to required slope and compected to meet requirement of table No. 300-2 and including all material, labour, labour cess, T&P royalty, all tasex etc. complete as per diretcion by i-in-c but excluding G.S.T. |
| 26 | Construction of granular sub-base Grade-1 by providing well graded material, spreading in uniform layers with motor grader on prepared surface, mixing by mix in place method with rotavator at OMC, and compacting with smooth wheel roller to achieve the desired density, complete as per Technical Specification Clause 401. and including all material, labour, labour cess, T&P royalty, all tasex etc. complete as per diretcion by i-in-c but excluding G.S.T. |
| 27 | Providing, laying, spreading and compacting stone aggregates of specific sizes to water bound macadam specification including spreading in uniform thickness, hand packing, rolling with smooth wheel roller 80-100 kN in stages to proper grade and camber, applying and brooming, stone screening/binding materials to fill-up the interstices of coarse aggregate, watering and compacting to the required density grading 2 as per Technical Specification Clause 405. and including all material, labour, labour cess, T&P royalty, all tasex etc. complete as per diretcion by i-in-c but excluding G.S.T. |
| 28 | Providing, laying, spreading and compacting stone aggregates of specific sizes to water bound macadam specification including spreading in uniform thickness, hand packing, rolling with smooth wheel roller 80-100 kN in stages to proper grade and camber, applying and brooming, stone screening to fill-up the interstices of coarse aggregate, watering and compacting to the required density Grading 3 as per Technical Specification Clause 405. and including all material, labour, labour cess, T&P royalty, all tasex etc. complete as per diretcion by i-in-c but excluding G.S.T. |
| 29 | Brick edging on both side of the road of first class (M-150) brick on edge laied with mud mortar including labour and supply of bricks finished to the recuired templete and in proper alignment and also including dressing and ramming the exavated earth as directed by the Engnieer-in-Charge and including all material, labour, labour cess, T&P royalty, all tasex etc. complete as per diretcion by i-in-c but excluding G.S.T. |
| 30 | Providing and applying primer coat with bitumen emulsion (SS) on prepared surface of granular base including cleaning of road surface and spraying primer at the rate of 0.70 kg/sqm using mechanical means as per Technical Specification Clause 502 and including all material, labour, labour cess, T&P royalty, all tasex etc. complete as per diretcion by i-in-c but excluding G.S.T. |
| 31 | Providing & applying tack coat with bitumen VG-10 using pressure distributor at the rate of 0.30 kg per sqm on the prepared bituminous/granular surface incliding supply of all meterial T&P and labour cess etc. and exluding cost of bitumen but excluding cost of GST as per direction of Engineer in charge. and including all material, labour, labour cess, T&P royalty, all tasex etc. complete as per diretcion by i-in-c but excluding G.S.T. |
| 32 | P/L of open graded premix carpeting of 20mm thick composed with 13.2 mm and 11.2mm grit aggregate or approved graded grit @ 0.27 cum/10Sqm. using 80/100 bitumen @ 146.00 Kg./100Sqm. as bearing course, including heating of bitumen to required temperature, and incliding supply of all meterial T&P and labour cess etc. and exluding cost of bitumen but excluding cost of GST as per direction of Engineer in charge. and including all material, labour, labour cess, T&P royalty, all tasex etc. complete as per diretcion by i-in-c but excluding G.S.T. |
| 33 | Providing and applying seal coat type ‘C’ with 6.8 mm gauge stone grit @ 0.90 cum/100 Sqm & bitumen 65 kg/100 Sqm including heating of bitumen to required temperature, mixing of stone gri with suitable mixol, laying and rolling with a smooth wheeled roller including cost of all material, Labour, royalty, T&P and all taxes etc required for proper completion of work and roller charges and exluding cost of bitumen but excluding cost of GST as per direction of Engineering in charge. and including all material, labour, labour cess, T&P royalty, all tasex etc. complete as per diretcion by i-in-c but excluding G.S.T. |
| 34 | Excavation for roadwork in soil with hydraulic excavator of 0.9 cum bucket capacity including cutting and loading in tippers, trimming bottom and side slopes, in accordance with requirements of lines, grades and cross sections, and transporting to the embankment location within all lifts and lead upto 1000m and including all material, labour, labour cess, T&P royalty, all tasex etc. complete as per diretcion by i-in-c but excluding G.S.T. |
| 35 | Plain cement concrete 1:3:6 nominal mix in foundation with crushed stone aggregate 40 mm nominal size mechanically mixed, placed in foundation and compacted by vibration including curing for 14 days. 2100 12.04 and including all material, labour, labour cess, T&P royalty, all tasex etc. complete as per diretcion by i-in-c but excluding G.S.T. |
| 36 | Plain/Reinforced PCC Grade M20 using batching plant transit mixer & manual placing Cement Concrete in Open Foundation complete as per Drawing and Technical Specifications. 1500, 1700 & 2100 12.08 and including all material, labour, labour cess, T&P royalty, all tasex etc. complete as per diretcion by i-in-c but excluding G.S.T. |
| 37 | Brick masonry work in 1:3 in sub-structure complete excluding pointing and plastering, as per drawing and Technical Specifications 1300 & 2200 13.01 and including all material, labour, labour cess, T&P royalty, all tasex etc. complete as per diretcion by i-in-c but excluding G.S.T. |
| 38 | Plastering with cement mortar (1:3 ) on brick work in sub-structure as per Technical Specifications 1300 & 2200 13.3 and including all material, labour, labour cess, T&P royalty, all tasex etc. complete as per diretcion by i-in-c but excluding G.S.T. |
| 39 | Mantinance Part B @ 2.50% |
| 40 | Maintenance of constructed work next five year after completion the contractor shall be paid total maintenance cost 2.50% of tender Civil Cost for five year in the form of instalment as below. The payment shall be inclusive of cess but excluding GST payment shall be done as per satisfaction of engineer in charge regarding maintenance work carried out by contractor (Including cess and Excluding GST)For 1st Year 0.00% |
| 41 | Item No. 30but for 2nd year 0.25% |
| 42 | Item No. 30but for 3rd year 0.50% |
| 43 | Item No. 30but for 4th year 0.75% |
| 44 | Item No. 30but for 5th year 1.00% Please Enable Macros to View BoQ information |