| 1 | (I) GENERATOR STATOR IR & PI test with 5 KV Microprocessor megger |
| 2 | DC winding resistance measurement. |
| 3 | Tan delta / Power Factor / Capacitance measurement measurement (with DOBLE kit only) |
| 4 | Computerized Digital ELCID test (a) Turbo Generator |
| 5 | Computerized Digital ELCID test (b) Hydro Generator |
| 6 | Partial discharge Probe test OR Offline PD Analysis. |
| 7 | DC Leakage Current / Step Voltage test |
| 8 | Stator Slot Wedging system check (Wedge tightness mapping) (a) By wedge deflection test if the ripple springs are installed |
| 9 | Stator Slot Wedging system check (Wedge tightness mapping) (b) By wedge knocking test (Wedge mapping) |
| 10 | RTD elements check (IR & DC resistance) |
| 11 | IR with 1000V DC source and amp mtr. |
| 12 | Natural Frequency Test on End Windings |
| 13 | Rated core flux test |
| 14 | Fibro Scope Inspection with Video recording facility for Stator core and winding |
| 15 | (II) GENERATOR ROTOR IR with digital Megger |
| 16 | Digital RSO Test |
| 17 | AC Impedance measurement (with 50A Variac) |
| 18 | DC winding resistance measurement. |
| 19 | Voltage balance test |
| 20 | Purge test (Upto 210 MW) |
| 21 | Purge test (Above 210 MW) |
| 22 | Fibro Scope Inspection with Video recording facility for Rotor winding |
| 23 | (III) EXCITER IR with digital Megger |
| 24 | DC winding resistance measurement. |
| 25 | Pole Impedance test |
| 26 | Pole drop test |
| 27 | Diode wheel check & Fuse Resistance measurement including HEAT SINKS IR measurement |
| 28 | (IV) ELECTRICAL TESTS ON GENERATOR MEASURING & PROTECTION EQUIPMENTS Testing of Surge Capacitors & Testing of Lightening Arrestors (Lumpsum) |
| 29 | Testing of CTs (Lumpsum) |
| 30 | Testing of PTs (Lumpsum) |
| 31 | Testing of NGT & NGR (Lumpsum) |
| 32 | (V) GENERATOR TRANSFORMER (DRY TYPE/OIL TYPE) Tan delta/Power factor/capitance test |
| 33 | DC winding resistance measurement. |
| 34 | (VI) ADDITIONAL TESTS IR/Contact Resistance Measurement of 1 No of Bushings/Connection Assemblies/Bus Bar Extensions/ Bar to Bar Connections/Other Electrical Connections etc |
| 35 | Demagnetisation of Generator Rotor including Mobilisation and Demobilisation IN-Situ/Outside. Please Enable Macros to View BoQ information |