| 1 | For Line Shifting BP Marg to Rudravart Mandir, Sitapur.The following works involves. |
| 2 | Supply of Holding Clamp for PCC Pole |
| 3 | Supply of Stay Clamp |
| 4 | Supply of F-Bracket |
| 5 | Supply of Holding Clamp for Top/Dropper Channel |
| 6 | Supply of Eye Hook |
| 7 | Supply of LTMS Clamp for PCC Pole |
| 8 | Carriage of PCC Pole From ESC, Sitapur to Dump Site |
| 9 | Carriage of ABC (3x50+1x35+1x16) sqmm From ESC, Sitapur to Dump site |
| 10 | Carriage of ACSR Weasel Conductor From ESC, Sitapur to Dump site |
| 11 | Carriage of other Line Material From ESC, Sitapur to Dump Site |
| 12 | Shifting of PCC Pole From Dump Site to work site |
| 13 | Shifting of ABC (3x50+1x35+1x16) sqmm From Dump site to work site |
| 14 | Shifting of ACSR Weasel Conductor From Dump site to work site |
| 15 | Shifting of other Line Material From Dump Site to work site |
| 16 | Errection of PCC Pole with fitting of accessories |
| 17 | Laying of ABC (3x50+1x35+1x16) sqmm |
| 18 | Laying stringing and sagging of ACSR Weasel conductor 11 KV line |
| 19 | Fabrication of Top, T-off, Dropper Channel etc |
| 20 | Fixing of stay |
| 21 | Earthing of Pole |
| 22 | Dismentling of Old Line |
| 23 | Grouting of PCC Pole |
| 24 | Grouting of Stay |
| 25 | Carrriage of Old used/ removel scrap material From work site to ESC, Sitapur/ J.E. Section Store |
| 26 | For DP Line Shifting Tejipurwa to Sidhauli.The following works involves. |
| 27 | Supply of Distribution Box 1 phase |
| 28 | Supply of Cross Arm Holding Clamp |
| 29 | Supply of Stay Clamp |
| 30 | Supply of Holding Clamp for PCC Pole |
| 31 | Supply of F Clamp for PCC Pole |
| 32 | Carriage of PCC Pole From ESC, Sitapur to Dump Site |
| 33 | Carriage of ST Pole From ESC, Sitapur to Dump Site Sitapur |
| 34 | Carriage of ABC 3x95+1x70+1x16 sqmm From ESC, Sitapur to Dump site |
| 35 | Carriage of ACSR Weasel Conductor From ESC, Sitapur to Dump site |
| 36 | Carriage of other Line Material From ESC, Sitapur to Dump Site |
| 37 | Shifting of PCC Pole From Dump Site to work site |
| 38 | Shifting of ST Pole FromDump Site to work site |
| 39 | Shifting of ABC 3x95+1x70+1x16 sqmm From Dump site to work site |
| 40 | Shifting of ACSR Weasel Conductor From Dump site to work site |
| 41 | Shifting of other Line Material From Dump Site to work site |
| 42 | Errection of ST Pole with fitting of accessories |
| 43 | Errection of PCC Pole with fitting of accessories |
| 44 | Laying stringing and sagging of ACSR Weasel conductor 11 KV line |
| 45 | Laying of ABC 3x95+1x70+1x16 sqmm |
| 46 | Fabrication of Top, T-off, Dropper Channel etc |
| 47 | Fixing of stay |
| 48 | Earthing of Pole |
| 49 | Dismentling of Old Line |
| 50 | Concreting of stay |
| 51 | Concreting of Pole |
| 52 | Carrriage of Old used/ removel scrap material From work site to ESC, Sitapur/ J.E. Section Store Please Enable Macros to View BoQ information |